Slide 1: Livengood: A Leveraged Gold Opportunity
LIVENGOOD A Leveraged Gold Opportunity Corporate Update Alaska Headquarters Tower Hill Mines, Inc. September, 2017 506 Gaffney Road, Suite 200 Fairbanks, AK 99701 1-‐855-‐428-‐2825 TSX: ITH | NYSE MKT: THM www.ithmines.com
Slide 2: Forward-Looking & Cautionary Statements
Forward-‐Looking & CauHonary Statements This presentaSon contains forward-‐looking statements and forward-‐looking informaSon (collecSvely, “forward-‐looking statements”) within the meaning of applicable Canadian and US securiSes legislaSon. All statements, other than statements of historical fa
Slide 3: The Livengood Advantage: Size - Leverage - Location
The Livengood Advantage: Size -‐ Leverage -‐ LocaHon § Largest North American gold-‐only deposit by Reserves and Resources not wholly owned by a Major or Producer § Quality asset provides long-‐term leverage & opportunity § Located in a stable jurisdicSon with rich mining history § Easy acce
Slide 4: Livengood Gold Reserve and Resource
Livengood Gold Reserve and Resource § 9.0M ounce Gold Reserve at $1,250 oz Proven & Probable Reserve (392 MT, Grade Avg. 0.71 g/t, cut-‐off grade varies*) § 11.5M ounce Gold Resource at $1,230 oz Measured & Indicated Resource (525 MT, Grade Avg. 0.68 g/t, cut-‐off grade varies**) § 783 Drill hole
Slide 5: Largest Gold-Only Reserve in North America Not Wholly Owned by a Major
Largest Gold-‐Only Reserve in North America Not Wholly Owned by a Major Proven & Probable Reserves (m oz) 10 8 Au -‐ Oz Millions 6 4 2 0 Sources: ITH -‐ April 10, 2017 NI 43-‐101 All others -‐ public documentaAon TSX: ITH | NYSE MKT: THM 5 www.ithmines.com
Slide 6: Largest Gold-Only Resource in North America Not Wholly Owned by a Major
Largest Gold-‐Only Resource in North America Not Wholly Owned by a Major Measured & Indicated Resource (m oz) 12 10 8 Au-‐Oz Millions 6 4 2 0 Sources: ITH -‐ April 10, 2017 NI 43-‐101 All others -‐ public documentaAon TSX: ITH | NYSE MKT: THM 6 www.ithmines.com
Slide 7: ITH - Impressive Leverage to Gold Price
ITH -‐ Impressive Leverage to Gold Price A]er Tax NPV (US$) A]er Tax NPV @5% ($M) A]er Tax NPV@0% ($M) $6,000 NPV(A]er-‐Tax, $US million) $5,000 $4,000 $3,000 $2,000 $1,000 $-‐ $(1,000) Based on financial model used in Gold Price (US$/oz) April 10, 2017 NI 43-‐101 TSX: ITH | NYSE MKT: THM 7 www.i
Slide 8: Share Structure & Cash
Share Structure & Cash TSX: ITH -‐ NYSE MKT: THM (as of August 7, 2017) Issued & Outstanding Shares 162,392,996 Shares Fully Diluted 168,332,996 Working Capital (as of June 30, 2017) $4.6 Million Major Shareholders Shares Held % Paulson & Co. Inc. 55,487,842 34.2 Tocqueville Asset Management LP 31,
Slide 9: Alaska: Rich Mining Jurisdiction
Alaska: Rich Mining JurisdicHon Red Dog Mines (Teck/NANA) • OperaSng since 1989 • Zinc-‐lead mine -‐ top producer of zinc concentrate Fort Knox (Kinross) • OperaSng since 1996 • Surface gold mine -‐ produced >7,000,000 oz Pogo (Sumitomo) • OperaSng since 2006 • Underground gold mine -‐ produced
Slide 10: Great Access To Infrastructure
Great Access To Infrastructure § Adjacent to Ellioe Highway and Trans-‐ Alaska Pipeline System corridor § Minimal transmission line required to connect to electric grid § No need for a camp TSX: ITH | NYSE MKT: THM 10 www.ithmines.com
Slide 11: Livengood - Gently Rolling Terrain of Interior Alaska
Livengood – Gently Rolling Terrain of Interior Alaska TSX: ITH | NYSE MKT: THM 11 www.ithmines.com
Slide 12: Excellent Project Fundamentals: Jurisdiction & Infrastructure
Excellent Project Fundamentals: JurisdicHon & Infrastructure § 70 miles northwest of Fairbanks via year-‐round paved highway § 50 miles from electric grid power § Livengood Mining District acSve since 1914 and the State designated the primary surface use as mineral development § Alaska has a hi
Slide 13: Optimization Study Results: Improved Livengood Gold Project
OpHmizaHon Study Results: Improved Livengood Gold Project § Project size opSmized at 52,600 tons/day § Lowered CAPEX by $950 million to $1.84 billion (34%) § Reduced Process OPEX by $2.97/ton to $7.48/ton (28%) § 6.8 million ounces of gold produced over 23 years § ProducSon Costs before Capital
Slide 14: 2017 Work Plan: Improve & De-risk
2017 Work Plan: Improve & De-‐risk § $14.7 million land payment paid on January 12, 2017, which removed large financial risk § Now focused on project improvement § Board approved 2017 budget of $6.3 million ØPursue opSmizaSon opportuniSes idenSfied in October 2016 Pre-‐Feasibility Study § Goal
Slide 15: 2017 Work Plan: Update Block Model
2017 Work Plan: Update Block Model Examine opportunity for updated block model to improve producSon forecast compared to MulSple Indicator Kriging (MIK) § BBA Inc. retained for 2017 program § Assay stored pulps to improve geologic model § Isolate zones with varying recoveries The Company cauSons
Slide 16: 2017 Work Plan: Recovery Optimization
2017 Work Plan: Recovery OpHmizaHon AddiSonal metallurgical test work to idenSfy potenSal recovery improvements § ConSnue reagent and flow sheet opSmizaSon § Confirm and potenSally improve recovery and OPEX esSmates For example: § For each overall recovery improvement of 1% in RT7 and RT9, an NPV i
Slide 17: 2017 Work Plan: Environmental Baseline
2017 Work Plan: Environmental Baseline Ongoing programs prepare for future permijng § Rock CharacterizaSon § Geohydrology § Surface Water & Hydrology § Meteorology § Air Quality § Wetlands & VegetaSon § AquaSc Studies § Cultural Resources § Noise Studies § Wildlife & Habitat Studies TSX: I
Slide 18: Excellent Management Team
Excellent Management Team Track Record of Large Mine Development and Permijng Success Mr. Hanneman has over 35 years of Alaska-‐based mining industry experience and most recently was COO of ITH. Prior to joining the Company in 2010, he played a key role on the team that Karl L. Hanneman worked to r
Slide 19: Opportunity To Invest At Low Valuation
Opportunity To Invest At Low ValuaHon Peer Comparison to ITH Market Cap/Oz P&P $80 $60 $40 $20 $-‐ Outstanding Shares, Market Price and Proven & Probable Reserves based on corporate websites as of Sept. 12, 2017. ITH taken from April 10, 2017 NI 43-‐101. TSX: ITH | NYSE MKT: THM 19 www.ithmines.co
Slide 20: Meaningful Potential Upside to the ITH Share Price
Meaningful PotenHal Upside to the ITH Share Price NPV/Share (US$) NPV@5%(A]er-‐Tax, US$)/share $20 $15 $10 $5 $-‐ $(5) Based on financial model used in Gold Price (US$/oz) April 10, 2017 NI 43-‐101 TSX: ITH | NYSE MKT: THM 20 www.ithmines.com
Slide 21: Livengood: A Leveraged Gold Opportunity
LIVENGOOD A Leveraged Gold Opportunity Alaska Headquarters Investor RelaHons Tower Hill Mines, Inc. Richard Solie, Jr. 506 Gaffney Road, Suite 200 rsolie@ithmines.com Fairbanks, AK 99701 1-‐855-‐428-‐2825 Telephone: (907) 328-‐2800 TSX: ITH | NYSE MKT: THM www.ithmines.com
Slide 22: Solid Shareholders Who Understand Long-Term Leverage
Solid Shareholders Who Understand Long-‐Term Leverage Major shareholders parScipated in recent financings: § CAD 8.4M private placement in December 2014 § USD 22.0M private placement in December 2016 Private Placement ParHcipants Dec. 2014 Dec. 2016 Paulson & Co. Inc. C$6,509,000 $15,566,324 Tocqu
Slide 23: Board of Directors
Board of Directors Partner at Paulson & Co. Inc. since 2011, where he oversees natural resource investments, specializing in gold, base metals, bulk Marcelo Kim commodiSes and oil & gas. Prior to that, commencing in 2009, he was a generalist analyst covering event arbitrage investment Chairman oppor
Slide 24: 2017 Pre-Feasibility Study: Gold Production
2017 Pre-‐Feasibility Study: Gold ProducHon Year 1-‐5 -‐ Average: 378,300 oz/yr Life of Mine -‐ Average: 294,100 oz/yr Source: April 2017 Pre-‐Feasibility Study, as reported in the April 10, 2017 NI 43-‐101. The Company cauSons that it has not demonstrated that it will be economically viable t
Slide 25: Livengood Reserves and Recovery by Rock Type
Livengood Reserves and Recovery by Rock Type Livengood Reserves from designed ulHmate pit (April 10, 2017 NI 43-‐101) Mineralized Material Kmt Contained Au Koz Au Recovery (%) Rock Type 4 61,506 16% 1,298 14% 81.8 Rock Type 5 89,009 23% 1,747 19% 84.7 Rock Type 6 91,032 23% 2,023 23% 75.6 Rock Type