Nextdecade Corporation · NASDAQ:NEXT

Nextdecade — Q4 2025 Earnings Presentation

47 slides from Nextdecade's earnings presentation, Mar 2, 2026

  1. Slide 1: Q4 2025 Investor Update

    Q4 2025 Investor Update March 2026 NASDAQ: NEXT Delivering Energy for What’s NEXT

  2. Slide 2: Disclaimer Statement

    Disclaimer Statement This Presentation contains certain statements that are, or may be deemed to be, “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. All statements other than

  3. Slide 3: 2025 Developments and Key Highlights

    2025 Developments and Key Highlights Fully funded Achieved positive • Signed over 7 million • Supported Trains 4 NextDecade $2.4 billion and 5 economics with final investment equity commitments tonnes per annum strong LNG prices with no material impact decisions (FIDs) and to common shares (MTPA) of

  4. Slide 4: NextDecade 2026 Priorities

    NextDecade 2026 Priorities Progress construction of Trains 1-5 safely, on budget, and ahead of schedule Phase 1 continues to track ahead of guaranteed substantial completion dates Finalize preparation for commissioning activities, first LNG, and transition to operations People, processes, and system

  5. Slide 5: Trains 1-5 Construction Continues Safely, on Budget, and Ahead of Schedule

    Trains 1-5 Construction Continues Safely, on Budget, and Ahead of Schedule Recent Construction Highlights Construction Progress as of January 2026 • Train 1 structural steel and equipment installation substantially 64.5% complete Trains 1 and 2 • Early electrical commissioning underway with ongoing

  6. Slide 6: Path to Additional Growth at Rio Grande LNG

    Path to Additional Growth at Rio Grande LNG: Developing and Advancing the Permitting Process for Trains 6-8 Train 6 • Initiated pre-filing process with FERC in November 2025 for Train 6 and a third marine berth, expect to file full application mid-2026 T6 • Projected operations could potentially beg

  7. Slide 7: Recent Financial Highlights

    Recent Financial Highlights • No incremental capital needs projected for construction of Trains 4 and 5, including NextDecade equity commitments • Closed $6.7 billion project financing in September 2025 to fully fund Train 4 • ~$2.8 billion in equity commitments: ~$1.7 billion equity partners and ~$

  8. Slide 8: LNG Sales Update and Additional Pricing Sensitivity

    LNG Sales Update and Additional Pricing Sensitivity: Robust Cash Flow Projected Across Range of Market Margins TBtu Projected LNG Production Volumes Train 1 Start-Up to Train 5 DFCD1 Projected NextDecade Share of Rio 5,000 (Early Volumes ~2027 – 1H 2031) Grande LNG Project-Level DCF TBtu $2.25 (~202

  9. Slide 9: Early Cash Flows Bridge to Strong, Optimized Balance Sheet

    Early Cash Flows Bridge to Strong, Optimized Balance Sheet • Balance sheet optimization and strength paramount for long-term success • Target 3.0-3.5x debt to Adjusted EBITDA at NextDecade1 level following Train 5 DFCD • Visible paths to optimize balance sheet and achieve target leverage • Expect to

  10. Slide 10: Steady State Annual Financial Guidance

    Steady State Annual Financial Guidance Pricing Sensitivities: Robust Cash Flow Expected Across Range of Market Margins Projected NextDecade Annual Steady State Distributable Cash Flow Additional Pricing Sensitivity Reaffirm Existing Guidance (Assumes ~2 MTPA additional SPAs and maximization of proje

  11. Slide 11: NextDecade Investment Highlights

    NextDecade Investment Highlights

  12. Slide 12: Providing the World Access to Lower-Carbon Energy

    Providing the World Access to Lower-Carbon Energy Maximizing shareholder value by safely and efficiently delivering lower-carbon energy through LNG infrastructure Rio Grande LNG Facility NextDecade is developing and constructing the Rio Grande LNG Facility, a natural gas liquefaction and export faci

  13. Slide 13: NextDecade Key Investor Highlights

    NextDecade Key Investor Highlights 1 Strong Asset Development Platform at Rio Grande LNG Facility 2 Valuable Relationships with High-Quality Counterparties Across the Value Chain 3 Growth Momentum Supported by Robust Market Fundamentals 4 Strong Commitment to Sustainability and Social Responsibility

  14. Slide 14: NextDecade Key Investor Highlights

    NextDecade Key Investor Highlights Trains 1-3 progressing safely, on budget, and ahead of schedule, with first LNG from Train 1 expected in 1H 2027 1 Train 4 FID achieved in September 2025, and Train 5 FID achieved in October 2025 Strong Organic Growth Platform at Developing and advancing permitting

  15. Slide 15: NextDecade Key Investor Highlights

    NextDecade Key Investor Highlights EPC partner has unmatched track record of liquefaction project deliverability on time and on budget 2 Commercial offtake agreements (LNG SPAs) with creditworthy, leading players in the global LNG market​ Valuable Relationships with Project design utilizes establish

  16. Slide 16: NextDecade Key Investor Highlights

    NextDecade Key Investor Highlights Signed over 7 MTPA of 20-year LNG SPAs in 2025 with creditworthy counterparties Aramco, TotalEnergies, JERA, EQT, and ConocoPhillips for Trains 4 and 5 at Rio Grande LNG 3 Expect to file full application with FERC for Train 6 in 2026, goal to leverage commercial mo

  17. Slide 17: NextDecade Key Investor Highlights

    NextDecade Key Investor Highlights NextDecade seeks to deliver secure, affordable, and cleaner energy through safe and efficient development and operation of liquefaction capacity at the Rio Grande LNG Facility 4 LNG displaces coal and other solid fuels in developing countries Strong Commitment worl

  18. Slide 18: LNG Market Update

    LNG Market Update

  19. Slide 19: Robust Global Gas Demand Growth Calls for Incremental LNG Supply

    Robust Global Gas Demand Growth Calls for Incremental LNG Supply bcm 6,000 • Expect growth in global gas demand to LNG Pipeline Gas remain strong into 2030s and beyond 5,000 - Economic growth and electrification driving demand in developing countries 4,000 - Increased focus on energy security across

  20. Slide 20: Global Market Well Positioned to Absorb Third Wave of LNG Supply

    Global Market Well Positioned to Absorb ‘Third Wave’ of LNG Supply Pace of LNG supply growth during third wave not expected to be as dramatic as previous waves 1st Supply 2nd Supply 3rd Supply Wave Wave Wave Faster 20% supply growth 15% 10% Relative market 5% absorption requirement 20-yr CAGR0% (Yea

  21. Slide 21: Global LNG Market Resilient and Increasingly Robust Over Time

    Global LNG Market Resilient and Increasingly Robust Over Time $/MMBtu Implied Rio Grande LNG Spot Margins1 2011-2025 Implied Spot Margin (JKM less estimated Rio Grande LNG gas cost and shipping) Composition 30 ($/MMBtu) 25 Average spot margin: $7.20 20 NextDecade guidance: $5.00 15 ~$6.90 LNG Margin

  22. Slide 22: Existing Regas Capacity Can Accommodate Substantial LNG Supply Growth

    Existing Regas Capacity Can Accommodate Substantial LNG Supply Growth Operational regas capacity is expected to accommodate over 1,400 MTPA of LNG by 2030, supporting significant additional LNG supply capacity • 47 countries around the globe have operational regas infrastructure • Robust existing gl

  23. Slide 23: Rio Grande LNG Facility

    Rio Grande LNG Facility

  24. Slide 24: Rio Grande LNG Site in Great Location for Liquefaction Development

    Rio Grande LNG Site in Great Location for Liquefaction Development Access to uncongested port Strong geotechnical conditions and waterway requiring less piling Area historically subject to Proximity to prolific natural fewer named storms than gas resources in Permian and other areas of U.S. Gulf Coa

  25. Slide 25: Potential to Be One of World's Largest LNG Production and Export Sites

    Potential to Be One of World’s Largest LNG Production and Export Sites MTPA ~12 MTPA ~60 MTPA 60 50 ~18 MTPA 40 ~30 MTPA 30 ~48 MTPA 20 currently under construction or 10 in development 0 Trains 1-5 under Trains 6-8 in Potential incremental Total potential capacity at construction development capaci

  26. Slide 26: Facility Site Plan Trains 1-5

    Rio Grande LNG Facility Site Plan Trains 1–5 World class ~1,000-acre site in south Texas with 15,000 feet of frontage on the Brownsville Ship Channel, advantaged by proximity to abundant Permian and Eagle Ford gas resources and uncongested port Texas State Pipeline Highway 48 interconnects Material

  27. Slide 27: Valuable Relationships with High-Quality Counterparties Across Value Chain

    Valuable Relationships with High-Quality Counterparties Across Value Chain LNG Customers Equity Partners Technology EPC Pipeline 26

  28. Slide 28: Partnering with Preeminent Global LNG EPC Contractor Bechtel

    Partnering with Preeminent Global LNG EPC Contractor Bechtel Construction of the Rio Grande LNG Facility is de-risked by Bechtel’s track record of successful LNG completions and by fully-wrapped, lump-sum, turnkey EPC contracts Project Scope Trains 1-5 • 5 liquefaction trains with expected productio

  29. Slide 29: Rio Grande LNG Facility Guaranteed Construction Progress Update

    Rio GrandePhase LNG Facility Guaranteed 1 Construction Construction Progress Update Schedule 2023 2024 2025 2026 2027 2028 2029 2030 2031 4Q 2027 Train 1 3Q 2028 Train 2 1Q 2029 Train 3 3Q 2030 Train 4 2Q 2031 Train 5 Guaranteed Construction Timeline Guaranteed Substantial Completion Date 28

  30. Slide 30: Rio Grande Phase 1 LNG Construction Progress

    Rio Grande Phase 1LNG Construction Facility Construction Progress Update Progress Train 1, December 2025 Train 2, December 2025 Train 3, December 2025 29

  31. Slide 31: Rio Grande Phase 1 LNG Construction Progress

    Rio Grande Phase 1LNG Construction Facility Construction Progress Update Progress Train 4 Area, December 2025 Train 5 Area, December 2025 30

  32. Slide 32: Feed Gas Sourcing and Transportation Strategy

    Rio Grande LNG Facility Feed Gas Sourcing and Transportation Strategy Developing a diversified gas sourcing and transportation strategy to capitalize on proximity to sources that are expected to produce significant quantities of low-cost natural gas for decades Gas Sourcing and Transportation Approa

  33. Slide 33: Long-Term LNG Sale and Purchase Agreements Overview

    Long-Term LNG Sale and Purchase Agreements Overview Phase 1 Train 4 Train 5 Counterparties 93% FOB SPA Type 100% FOB 100% FOB 7% DES Average Term 19.2 years 20 years 20 years 91% HH Index 100% HH 100% HH 9% Brent SPA volume (MTPA)1 16.2 4.6 4.5 % Capacity Contracted ~90%2 ~77% ~75% ~85% of five-trai

  34. Slide 34: Trains 1-5 Funding Summary

    Rio Grande LNG Trains 1-5 Funding Summary • Financed ~66% debt / ~34% equity Phase 1 • $6.2 billion total equity commitments1 from $18.0 billion NextDecade, Global Infrastructure Partners (GIP), GIC, estimated total Mubadala, and TotalEnergies • $9.2 billion construction term loan facilities project

  35. Slide 35: Facility Equity Partners

    Rio Grande LNG Facility Equity Partners Financial Investors Total Commitments $2.7 Billion Total Commitments $7.5 Billion Total Commitments $1.3 Billion • Phase 1 • Phase 1 • Phase 1 - ~$0.3 billion commitment completed - ~$4.8 billion total commitments - ~$1.0 billion commitment - Up to 20.8% econo

  36. Slide 36: Train 4 and 5 Equity Commitments Fully Funded

    NextDecade’s Train 4 and 5 Equity Commitments Fully Funded with No Material Impact to Equity Train 4 and 5 equity funding commitments of ~$2.4 billion fully funded utilizing approach with lowest estimated cost of capital and highest impact to cash flow per share ~$0.2 Billion Cash • Cash committed f

  37. Slide 37: Capital Structure and Financial Priorities

    Capital Structure and Financial Priorities

  38. Slide 38: NextDecade Summary Capital Structure

    NextDecade Summary Capital Structure NextDecade Corporation (NASDAQ: NEXT) NextDecade LNG, LLC $175 million1 13.50% senior secured loans due 2030 $100 million1 8.00% senior secured exchangeable Rio Grande LNG Super loans due 2030 Holdings, LLC Rio Grande LNG Phase 1 $1.20 billion1 13.0% senior secur

  39. Slide 39: NextDecade Capital Priorities

    NextDecade Capital Priorities 1. Protect safe and reliable operations by maintaining high-integrity assets 2. Maintain investment grade metrics for Rio Grande LNG Phase 1, Train 4, and Train 5 • Plan to term out project-level loans and stagger maturities via opportunistic debt capital markets transa

  40. Slide 40: Empowering the Rio Grande Valley Community

    Empowering the Rio Grande Valley Community

  41. Slide 41: NextDecade is Committed to the Rio Grande Valley Community

    NextDecade is Committed to the Rio Grande Valley Community Fostering a long-lasting partnership with local stakeholders to create value, provide opportunities, and contribute to a thriving community for all • Continuous engagement with local stakeholders to: - Obtain a greater understanding of commu

  42. Slide 42: NextDecade is Committed to the Rio Grande Valley Community

    NextDecade is Committed to the Rio Grande Valley Community Fostering a long-lasting partnership with local stakeholders to create value, provide opportunities, and contribute to a thriving community for all • NextDecade’s community engagement is founded on four core values: “The Rio Grande LNG proje

  43. Slide 43: Miradores Environmental Mitigation Project

    Miradores Environmental Mitigation Project Restoration of the Miradores Mitigation Site near Brownsville, Texas, began in September 2023 and was completed in June 2025, placing more than 1,500 acres under a conservation easement “As a longtime steward of this land, it’s incredibly meaningful to see

  44. Slide 44: Appendix

    RIO GRANDE LN Appendix

  45. Slide 45: Key Assumptions and Details

    Key Assumptions and Details Steady state period refers to the period beginning when respective trains have been completed and placed in operation and deliveries under each train’s LNG SPAs have commenced. Projected guidance assumes SPA contract price for all contracted volumes and a $3.00/MMBtu or $

  46. Slide 46: Non-GAAP Measures

    Non-GAAP Measures Rio Grande LNG Project-Level Adjusted EBITDA, Rio Grande LNG Project-Level Distributable Cash Flow, NextDecade Share of Rio Grande LNG Project-Level Distributable Cash Flow, and NextDecade Distributable Cash Flow are non-GAAP financial measures that we use to assess operating perfo

  47. Slide 47: Delivering Energy for What's NEXT

    Delivering Energy for What’s NEXT www.next-decade.com Investor Relations Megan Light John Montano Contacts: Vice President, Investor Relations Senior Analyst, Investor Relations mlight@next-decade.com jmontano@next-decade.com 832-981-6583 832-397-6140 46