Agl Energy Limited · ASX:AGL
Agl Energy — Corporate Update (March 2017)
35 slides from Agl Energy's corporate update, Mar 30, 2017
Slide 1: Silverton Wind Farm Community Consultative Committee
Silverton Wind Farm Community Consultative Committee Meeting No.CCC-021 Presented by AGL Energy Limited Date Thursday, 30 March 2017
Slide 2: Agenda
Community Consultative Committee | 2 Agenda 1 Welcome 5 Topics of interest • Visual impact assessment • Mobile reception program 2 Previous minutes 6 Other business Project update 3 • Overview • Wind Farm Works 7 Next meeting • Connection Works 4 Community relations update Silverton Wind Farm – 30 M
Slide 3: 2. Previous minutes
Community Consultative Committee | 3 2. Previous minutes Action items Item Action Status Who AGL invited community representatives to be involved in 4.20.03 Open KL – 4/17 developing a draft plan for the Silverton Community Fund. AGL to advertise further details on the industry briefing 4.20.07 Clos
Slide 4: Silverton Wind Farm
Community Consultative Committee | 4 3. Project update Silverton Wind Farm Silverton Wind Farm › Located in the Barrier Ranges approximately 5km north of the Silverton township. › Generation capacity of 200 MW › Wind turbines: 58 x GE 3.43-130 › Annual Energy Production (AEP) » ~780,000 MWh Capaci
Slide 5: Scope of Works
Community Consultative Committee | 5 3. Project update Silverton Wind Farm Scope of Works › The Silverton Wind Farm consists of two main scopes of work: » Wind Farm Works (GE-CATCON) » Connection Works (TransGrid) › AGL has prepared an Overview Environmental Management Strategy (OEMS) in accordance
Slide 6: Silverton Wind Farm - GE-CATCON wind farm works
Community Consultative Committee | 6 3. Project update Silverton Wind Farm Wind Farm Works › GE-CATCON (joint venture) has been engaged to deliver the wind farm works » Engineer, Procure and Construct (EPC) Contract › Scope of works, includes: » 58 x GE 3.43-130 wind turbines » 33kV electrical retic
Slide 7: Connection Works
Community Consultative Committee | 7 3. Project update Silverton Wind Farm Connection Works › TransGrid (Network Services Provider) has been engaged to deliver the connection works for the wind farm » Project Agreement (construction) › Scope of works, includes: » Wind farm 220kV substation » ~25km o
Slide 8: Industry Briefing
Community Consultative Committee | 8 3. Project update Silverton Wind Farm Industry Briefing › AGL together with GE-CATCON conducted an industry briefing on Tuesday, 31 January 2017 at Silverton and Broken Hill » Both sessions were well attended by local industry and people interested in employment
Slide 9: Pre-construction minor works
Community Consultative Committee | 9 3. Project update Wind Farm Works Pre-construction minor works › GE-CATCON is planning to mobilise early next week to commence the pre-construction minor works › The project approval defines the pre-construction minor works: » investigative drilling, excavation o
Slide 10: Wind Farm Environmental Management Strategy
Community Consultative Committee | 10 3. Project update Wind Farm Works Wind Farm Environmental Management Strategy › GE-CATCON has developed in accordance with condition 1 (schedule 4) of the project approval, including: » Biodiversity Management Plan » Heritage Management Plan » Traffic Management
Slide 11: Road Upgrade and Maintenance Strategy
Community Consultative Committee | 11 3. Project update Wind Farm Works Road Upgrade and Maintenance Strategy › GE-CATCON has developed in accordance with condition 24 (schedule 3) of the project approval: » Silverton Road upgrade » Silverton Road / Daydream Mine Road intersection » Daydream Mine Ro
Slide 12: Road Upgrade: Silverton Rd / Daydream Mine Road intersection
Community Consultative Committee | 12 3. Project update Wind Farm Works Road Upgrade and Maintenance Strategy › Silverton Rd / Daydream Mine Road intersection Silverton Wind Farm – 30 March 2017
Slide 13: Road Upgrade: Daydream Mine Road / Site Access intersection
Community Consultative Committee | 13 3. Project update Wind Farm Works Road Upgrade and Maintenance Strategy › Daydream Mine Road / Site Access intersection Silverton Wind Farm – 30 March 2017
Slide 14: Short bypass (Barrier Hwy intersection) – Option B
Community Consultative Committee | 14 3. Project update Wind Farm Works Road Upgrade and Maintenance Strategy › Short bypass (Barrier Hwy intersection) – Option B Silverton Wind Farm – 30 March 2017
Slide 15: Short bypass (Silverton Road intersection)
Community Consultative Committee | 15 3. Project update Wind Farm Works Road Upgrade and Maintenance Strategy › Short bypass (Silverton Road intersection) Silverton Wind Farm – 30 March 2017
Slide 16: Traffic Management Plan (TMP)
Community Consultative Committee | 16 3. Project update Wind Farm Works Traffic Management Plan (TMP) › GE-CATCON has developed in accordance with condition 27 (schedule 3) of the project approval. › TMP includes a route assessment study from Port Adelaide to site › Issued to the Roads and Maritime
Slide 17: Traffic Management Plan: heavy vehicle routes
Community Consultative Committee | 17 3. Project update Wind Farm Works Traffic Management Plan (TMP) › Heavy and over dimensional vehicle routes » Appendix 7 of the project approval › Site access is off Daydream Mine Road. › Primary access is via the site access (shown in green) › Construction will
Slide 18: Traffic Management Plan: heavy vehicle routes
Community Consultative Committee | 18 3. Project update Wind Farm Works Traffic Management Plan (TMP) › Heavy and over dimensional vehicle routes » Appendix 7 of the project approval › Site access is off Daydream Mine Road. › Primary access is via the site access (shown in green) › Construction will
Slide 19: Type wind turbine – GE 3.43-130
Community Consultative Committee | 19 3. Project update Wind Farm Works Type wind turbine – GE 3.43-130 › Type Wind Turbine is installed in Wieringermeer, Holland (shown in photo). › Nameplate of 3.43 MW with a 130m rotor and hub height of 110m › The 3MW platform machines are an evolution of the 2.5
Slide 20: Wind turbine GE 3.43-130
Community Consultative Committee | 20 3. Project update Wind Farm Works Wind turbine GE 3.43-130 › Inside the GE 3.43-130 wind turbine Silverton Wind Farm – 30 March 2017
Slide 21: Connection Works: Existing 220kV Substation
Community Consultative Committee | 21 3. Project update Connection Works Existing 220kV Substation › The Point of Connection (POC) for the Silverton Wind Farm will be in TransGrid’s existing 220kV substation in Broken Hill. › The scope of works includes: » Foundations for electrical equipment / bay
Slide 22: Connection Works: 220kV Transmission Line
Community Consultative Committee | 22 3. Project update Connection Works 220kV Transmission Line › The Silverton Wind Farm is connected to the National Electricity Market (NEM) via the ~25km of 220kV transmission line to the Point of Connection (POC). › The scope of works includes: » Single galvaniz
Slide 23: Connection Works: 220kV Wind Farm Substation
Community Consultative Committee | 23 3. Project update Connection Works 220kV Wind Farm Substation › The Silverton Wind Farm is transformed to the 220kV network voltage via the 220kV wind farm substation. › The scope of works includes: » Bunded foundation » 220/33kV power transformer » Control / au
Slide 24: 220kV Wind Farm Substation preliminary design
Community Consultative Committee | 24 3. Project update Connection Works 220kV Wind Farm Substation › Preliminary design coordination Silverton Wind Farm – 30 March 2017
Slide 25: Community engagement
Community Consultative Committee | 25 4. Community relations update Community engagement Silverton Information Centre › AGL will be utilising the old butchers shop in Silverton during the construction of the wind farm to provide project information and updates Community information AGL contact detai
Slide 26: Construction planning
Community Consultative Committee | 26 4. Community relations update Construction planning Signage › Project signboard will be erect at the site entry Construction notifications › Notification will be provided through different means depending on the type of works and scope of works » Phone calls » E
Slide 27: Community Enhancement Commitments
Community Consultative Committee | 27 4. Community relations update Community engagement Community Enhancement Commitments › Silverton Community Fund » $15,000 per year + CPI (life of project) › Solar Silverton Program » 5kW solar PV for leaseholder and residences within 10 km of project. » Initial
Slide 28: Mobile Reception Program
Community Consultative Committee | 28 4. Community relations update Community Enhancement Commitments Mobile Reception Program › AGL has commenced feasibility studies with Telstra based on existing upgrade existing infrastructure » Options for 3G and 4G coverage » 4G is significantly above the budge
Slide 29: Visual impact assessment
Community Consultative Committee | 29 5. Topics of interest Visual impact assessment Modification 3 › AGL is proposing to prepare photo montages of the planned Silverton Wind Farm showing the 58 wind turbines – similar to the photo shown below Silverton Wind Farm – 30 March 2017
Slide 30: Visual impact assessment
Community Consultative Committee | 30 5. Topics of interest Visual impact assessment Silverton Wind Farm › Preliminary feedback on locations is shown below: » Silverton township » Mundi Mundi lookout » Umberumberka House » Desert Sculpture (Living Desert) Line of Load » North Silverton » Thackarin
Slide 31: Silverton Creek proposed sand extraction
Community Consultative Committee | 31 5. Topics of interest Silverton Creek Proposed sand extraction › Consolidated Mining and Civil (CMC) submitted their application to NSW Crown Lands in November 2017. › Sand extract is planned to commence shortly after receipt of the license – potentially April /
Slide 32: Horses and wind farms
Community Consultative Committee | 32 5. Topics of interest Horses and wind farms Delabole Wind Farm › Delabole Wind Farm is the UK’s first commercial wind farm, established in 1991. › A horse stud farm and riding centre has been operating at the Delabole Wind Farm since 1991 › Originally the wind f
Slide 33: 6. Other business
Community Consultative Committee | 33 6. Other business Silverton Wind Farm › AGL Viewing Platform Art and Design Competition (Broken Hill Solar Plant) › Questions from group and observers? Silverton Wind Farm – 30 March 2017
Slide 34: 7. Next meeting
Community Consultative Committee | 34 7. Next meeting Silverton Wind Farm Community Consultative Committee (CCC) › Next Meeting: » Date » Time » Location Silverton Wind Farm – 30 March 2017
Slide 35: End Presentation
End Presentation