Patronus Resources Limited · ASX:PTN
Patronus Resources — Shareholder Meeting (December 2018)
16 slides from Patronus Resources's shareholder meeting presentation, Dec 6, 2018

Slide 1: AGM Presentation
1 PRESENTATION AGM 29 November 2018

Slide 2: Disclaimer
2 Disclaimer Disclaimer This presentation is not a prospectus nor an offer for securities in any jurisdiction nor a securities recommendation. The information in this presentation is an overview and does not contain all information necessary for investment decisions. In making investment decisions i

Slide 3: Corporate
3 Corporate KIN Mining NL – Share Price as at November 2018 Shareholders Share price (A$) 0.084 Shares outstanding (m) 373.6 Options (m) 37.2 Market capitalisation 31.4 (A$m) Net Cash/(Debt) (A$m)1,2 2.7 1. Unaudited cash and debt as at 22 November 2018, US$3 million debt converted to A$ at A$/$US r

Slide 4: Kin Share Price - Feb 17 to Nov 18
4 Kin Share Price - Feb 17 to Nov 18 Discovery of Release of DFS 249d #1 Curtailment of 249d #2 Lewis South Results Resignation of Construction Previous Board Primary $167M PFCF MD and Technical member and Debt Mineralisation Director Finance Broker replacement by seek to oust entire NED and new Boa

Slide 5: DFS Recap – Announced October 2017
5 DFS Recap – Announced 2 October 2017 Mining 373Koz Probable Ore Reserve (7.933Mt @ 1.5g/t Au) – LOM Grade 1.5g/t. First 3 years Grade 1.3g/t LOM 22 Open pits some with sub-pits. 17 Pits in the first 3 years LOM Strip Ratio 8:1 First 3 years Strip Ratio 8.3:1 62% of Ore is Oxide or Transi

Slide 6: Cardinia and Lawlers
6 Cardinia and Lawlers Construction commenced 8 February 2018, Curtailed 11 April 2018, Suspended 9 May 2018. Soft landing after Suspension. A$10 million spent US$5.0 million drawn from US$27 million facility Cardinia 2.5Mw Ball mill purchased and delivered- Refurbishment commenced Works

Slide 7: Cardinia Mining Centre – Simplify the Plan
7 Cardinia Mining Centre – Simplify the Plan ALL DRILLING DRILLING DEEPER THAN 50m DRILLING DEEPER THAN 100m DRILLING DEEPER THAN 150m Cardinia is a significantly mineralised area –DFS planned to exploit it with 16 Separate Pits…some insignificant Highly successful deeper drilling campaigns unde

Slide 8: Lewis – Baseload Pit #1
8 Lewis – Baseload Pit #1. Extensive shallow oxide mineralisation hosted within 3km- long Bruno-Lewis system The Oxide Ore (186k oz* Mineral Resource to circa 50m) has an underlying primary source that is yet to be fully understood Primary mineralisation discovered during extensional drilling

Slide 9: Helens – Satellite Pit #1
9 Helens – Satellite Pit #1 • Mineral Resources – 1.03Mt @ 2.14 g/t Au for 71koz Au • Consistent, primary mineralisation intersected between pits to 120m depth. • High grade oxide and primary mineralisation intersected over 1500m of strike. • Clear potential exists to increase the Mineral Resources

Slide 10: Opportunities - Mertondale
10 Opportunities - Mertondale 5 Mertondale 5 - Open Pit Mining was completed in 1991. • Discovered by Harbour Lights Mining Ltd in 1989 History • Mined 384,671 tonnes @ 3.06 g/t Au for 37,841 Ounces with A$450/ oz gold price in pit design • Transported and treated at Harbour Lights Processing Facili

Slide 11: Water – Providing a sustainable supply
11 Water – Providing a sustainable supply • Cardinia Creek. Two production bores PB1 and PB4 tested. 15 l/s combined. • Supply construction and dust suppression water. Two more sites identified for development • Bummer Creek. Two Production Bores PB2 and PB3 tested. 25-30 l/s combined. • Supply plan

Slide 12: Budget and Schedule
12 Budget and Schedule Budget New Mineral Resource estimate for Helens and Bruno Lewis. -Underway Increased Metallurgical Testwork, Ore Reserves, Mine plan and schedule. - Underway Definitive Capital estimates of Water, Power, Tailings Dam and Infrastructure Review Lawlers equipment and de

Slide 13: Key Takeaways
13 Key Takeaways Construction of the LGP suspended due to: • Uncertainty of the increase in the Cost to Complete • Other Project elements were not far enough advanced and needed to be addressed systematically • The Project was very unlikely to meet the DFS outcomes on which the Construction was ju

Slide 14: Contact details
14 Contact details: Level 1, 342 Scarborough Beach Road Osborne Park WA 6017 T: 61 8 9242 2227 E: info@kinmining.com.au ASX: KIN 14

Slide 15: APPENDIX A – Kin Mining NL Mineral Resources
15 APPENDIX A – Kin Mining NL Mineral Resources Leonora Gold Project Mineral Resources Leonora Gold Project (LGP) Project Area Lower Indicated Resources Cut off Tonnes Resources Inferred Total Resources Au Au Tonnes Au Au Tonnes Au Au – 1.06 Moz Au (g/t Au) (Mt) (g/t (k Oz) (Mt) (g/t (k Oz) (Mt) (g/

Slide 16: APPENDIX B – Kin Mining NL Ore Reserve
16 APPENDIX B – Kin Mining NL Ore Reserve Leonora Gold Project (LGP) – 373Koz Au Leonora Gold Project - Ore Reserve Estimate Ore Reserve Open Pit Mine Classification Tonnes (t) Grade (g/t) Metal (oz. Au) Tonto Probable 210,000 1.5 10,000 See ASX Announcement 2 October 2017 “Feasibility confirms Mert
Source: ASX announcement via 6ix News
More decks from Patronus Resources Limited
Resources Rising Stars (September 2026)28 slides · Sep 9, 2026
Diggers & Dealers 202629 slides · Aug 3, 2026
Noosa Mining Conference 202530 slides · Nov 12, 2025
Australian Gold Conference 202530 slides · Nov 12, 2025
RRS Gold Coast (September 2025)29 slides · Sep 17, 2025
Diggers & Dealers 202528 slides · Aug 4, 2025