First Quantum Minerals Ltd. · TSX:FM
First Quantum Minerals — Non-Deal Roadshow (April 2013)
12 slides from First Quantum Minerals's roadshow presentation, April 2013
Slide 1: The New Leader in Global Copper
The New Leader in Global Copper April 2013 Global Diversified TSX: FM; LSE: FQM
Slide 2: Disclaimer
Disclaimer Certain statements and information contained in this presentation, including all statements that are not historical facts, contain forward-looking statements and forward-looking information within the meaning of applicable securities laws. Such forward-looking statements or information in
Slide 3: Creating the New Leader in Global Copper
Creating the New Leader in Global Copper First Quantum is one of the world’s leading copper producers, with a geographically diversified portfolio of high-quality operations and projects Uniquely positioned to deliver Cobre Panama more effectively by leveraging our global project development exp
Slide 4: A Premier Base Metals Company
A Premier Base Metals Company Seven producing mines and six world class projects across eight countries and five continents Unmatched Portfolio of World Solid Platform of Diversified, Class Development Projects Stable Operations Kansanshi Expansion and Las Cruces, Spain Cu Cu Au Smelter, Zambia Kevi
Slide 5: High Quality Operations
High Quality Operations Asset Location Ownership (1) 2012 Production 2012 Cash Cost Mine Life Reserves & Resources (Contained) Reserves 5,782 kt Cu, 3.3 Moz Au 261 kt Cu Kansanshi Zambia 80% US$1.49 / lb Cu 2037 M&I Resources 6,252 kt Cu, 3.3 Moz Au 136 koz Au Inferred 2,593 kt Cu, 1.3 Moz Au Reserv
Slide 6: Unmatched Portfolio of Development Projects
Unmatched Portfolio of Development Projects Expansion Projects Target Asset Location Ownership Completion Production Kansanshi Expansion 80% Zambia 400 kt Cu Mid – 2014 and Copper Smelter (100% smelter) Greenfield Projects Target Asset Location Ownership (1) Completion Reserves & Resources (Containe
Slide 7: A World Class Growth Profile
A World Class Growth Profile Proven Track Record of Developing & Operating Mines Unmatched Project Pipeline ktpa Cu production ktpa Ni production Well-positioned to deliver Cobre Haquira 1,200 industry-leading growth Panama 90 Enterprise 80 Sentinel 70 Kansanshi Expansion 800 Successfully Commission
Slide 8: Leading Copper Growth
Freeport-McMoRan 1.8 Glencore Xstrata 1.5 Codelco 1.5 2018E Copper Production, Mt First Quantum 1.3 Source: BrookHunt BHP Billiton 1.2 Leading Copper Growth Southern Copper 0.9 Rio Tinto 0.8 Anglo American 0.8 KGHM 0.6 Kazakhmys 0.5 Teck Resources 0.5 Vale 0.5 Antofagasta 0.4 Norilsk 0.4 First Quant
Slide 9: Cobre Panama – A Tier-One Project
Cobre Panama – A Tier-One Project Cobre Panama is the world’s largest copper project currently under construction Major Copper Development Projects (Contained Cu Mt) – Over 50 Blbs of contained copper, and 13 Moz of contained gold resources 0 10 20 30 – Commercial production is expected to commenc
Slide 10: Building Cobre Panama Using the First Quantum Project Philosophy
Building Cobre Panama Using the First Quantum Project Philosophy Our Project Development Philosophy Outcomes • A finished project must perform to expectations – Set ambitious targets for schedule, cost • Industry leading performance and performance – Lowest capital intensity achieved – Adhere to tim
Slide 11: Sentinel – On-Schedule and On-Budget
Sentinel – On-Schedule and On-Budget Key Project Developments Total project progress to date is ~27% on a cumulative basis Construction 57% concrete poured (total of 41,920 m3) – Continued works on pipe rack, surge area, e-buildings and concentrate area concrete Mill assemblies and installations
Slide 12: The New Global Copper Leader
The New Global Copper Leader The New Go-To Copper Producer Attractive Diverse Geographic Exposure A Long-Standing Commitment to Social and Environmental Excellence Creating Value with Our Project Development Expertise An Exciting Future Ahead 12
First Quantum Minerals — Non-Deal Roadshow (April 2013) on 6ix