The Aes — Fact Sheet (February 2024)

23 slides from The Aes's fact sheet, Feb 26, 2024

  1. Slide 1: The AES Corporation Fact Sheet

    The AES Corporation Fact Sheet As of February 26, 2024

  2. Slide 2: AES Total: 34,596 Gross MW in Operation

    AES Total: 34,596 Gross MW in Operation Technology Segment Pet Coke & Oil 2% Energy Renewables1 Infrastructure Renewables2 Gas 27% 43% 47% 53% 18% Coal 10% Utilities 1. Includes hydro, solar, wind, energy storage, biomass and landfill gas. 2 2. Excludes renewables projects in Chile, currently report

  3. Slide 3: AES Total: 24,047 Proportional MW in Operation

    AES Total: 24,047 Proportional MW in Operation Technology Segment Pet Coke & Oil 2% Energy Renewables1 Infrastructure Renewables2 Gas 28% 48% 42% 49% 21% Coal 10% Utilities 1. Includes hydro, wind, solar, energy storage, biomass and landfill gas. 3 2. Excludes renewables projects in Chile, currently

  4. Slide 4: Renewables Total: 16,211 Gross MW in Operation

    Renewables Total1: 16,211 Gross MW in Operation Technology Energy Storage 6% 35% Hydro Wind 30% 29% Solar 1. Excludes renewables projects in Chile, currently reported as part of the Energy Infrastructure segment. 4

  5. Slide 5: Renewables Total: 10,050 Proportional MW in Operation

    Renewables Total1: 10,050 Proportional MW in Operation Technology Energy Storage 7% 39% Hydro Wind 29% 25% Solar 1. Excludes renewables projects in Chile, currently reported as part of the Energy Infrastructure segment. 5

  6. Slide 6: Renewables

    Renewables Date of Acquisition or AES Equity Contract Business Location Fuel Gross MW Commencement of Customer(s) Prior Segment Interest Expiration Date Commercial Operations AES Brasil Operações (AES Brazil Hydro 2,658 47% 1999 2032 Various South America Tietê)1 Alicura Argentina Hydro 1,050 100% 2

  7. Slide 7: Renewables

    Renewables Date of Acquisition or AES Equity Contract Business Location Fuel Gross MW Commencement of Customer(s) Prior Segment Interest Expiration Date Commercial Operations Chevelon Butte (OpCo D)1 US-AZ Wind 238 75% 2023 2043 APS US & Utilities Buffalo Gap II 1 US-TX Wind 233 100% 2007 US & Utili

  8. Slide 8: Renewables

    Renewables Date of Acquisition or AES Equity Contract Business Location Fuel Gross MW Commencement of Customer(s) Prior Segment Interest Expiration Date Commercial Operations Buffalo Gap I1 US-TX Wind 121 100% 2006 US & Utilities ENSA, Edemet, Chiriqui – Esti Panama Hydro 120 49% 2003 2030 MCAC Edec

  9. Slide 9: Renewables

    Renewables Date of Acquisition or AES Equity Contract Business Location Fuel Gross MW Commencement of Customer(s) Prior Segment Interest Expiration Date Commercial Operations Solar 60 McFarland B1 US-AZ 75% 2023 2043 Amazon US & Utilities Energy Storage 30 Solar 56 Southern California Estrella US-CA

  10. Slide 10: Renewables

    Renewables Date of Acquisition or AES Equity Contract Business Location Fuel Gross MW Commencement of Customer(s) Prior Segment Interest Expiration Date Commercial Operations Dominican Santanasol Solar 50 65% 2022 2038 Ede Sur MCAC Republic Southern California Mountain View IV (OpCo E)1 US-CA Wind 4

  11. Slide 11: Renewables

    Renewables Date of Acquisition or AES Equity Contract Business Location Fuel Gross MW Commencement of Customer(s) Prior Segment Interest Expiration Date Commercial Operations Laurel Mountain ES US-WV Energy Storage 16 100% 2011 US & Utilities Community Energy 1 US-Various Solar 14 75% 2022 2024-2043

  12. Slide 12: Utilities Total: 3,500 Gross MW in Operation

    Utilities Total: 3,500 Gross MW in Operation Technology Renewables1 1% Oil 8% Coal 56% Gas 35% 1. Includes solar, energy storage and landfill gas. 12

  13. Slide 13: Utilities Total: 2,438 Proportional MW in Operation

    Utilities Total: 2,438 Proportional MW in Operation Technology 2% Oil Renewables1 7% Coal 56% Gas 35% 1. Includes solar, energy storage and landfill gas. 13

  14. Slide 14: Utilities

    Utilities Date of Acquisition or AES Equity Contract Business Location Fuel Gross MW Commencement of Customer(s) Prior Segment Interest Expiration Date Commercial Operations CAESS, EEO, CLESA, Bosforo El Salvador Solar 100 50% 2018-2019 2043-2044 US & Utilities DEUSEM CLESA, Cemento Metapan El Salva

  15. Slide 15: Energy Infrastructure Total: 14,884 Gross MW in Operation

    Energy Infrastructure Total: 14,884 Gross MW in Operation Technology 4% Pet Coke Renewables1 12% 51% Gas Coal 33% 1. Includes hydro, solar, wind, energy storage and biomass. 15

  16. Slide 16: Energy Infrastructure Total: 11,559 Proportional MW in Operation

    Energy Infrastructure Total: 11,559 Proportional MW in Operation Technology 5% Pet Coke Renewables1 14% 46% Gas Coal 35% 1. Includes hydro, solar, energy storage, wind and biomass. 16

  17. Slide 17: Energy Infrastructure

    Energy Infrastructure Date of Acquisition or AES Equity Contract Business Location Fuel Gross MW Commencement of Customer(s) Prior Segment Interest Expiration Date Commercial Operations Mong Duong 21 Vietnam Coal 1,242 51% 2015 2040 EVN Eurasia California Department Southland – Alamitos US-CA Gas 1,

  18. Slide 18: Energy Infrastructure

    Energy Infrastructure Date of Acquisition or AES Equity Contract Business Location Fuel Gross MW Commencement of Customer(s) Prior Segment Interest Expiration Date Commercial Operations ENSA, Edemet, Colón1 Panama Gas 381 65% 2018 2028 MCAC Edechi Ede Este, Ede Norte, Dominican DPP (Los Mina) Gas 35

  19. Slide 19: Energy Infrastructure

    Energy Infrastructure Date of Acquisition or AES Equity Contract Business Location Fuel Gross MW Commencement of Customer(s) Prior Segment Interest Expiration Date Commercial Operations Mesamávida Chile Wind 68 51% 2022-2023 2038 Google, Various South America Campo Lindo Chile Wind 65 51% 2023 Vario

  20. Slide 20: 5,116 Gross MW Under Construction

    5,116 Gross MW Under Construction Technology Segment Gas Renewables1 Energy Infrastructure Renewables2 13% 23% Utilities 11% 66% 87% 1. Includes solar, energy storage and wind. 20 2. Excludes renewables projects in Chile, currently reported as part of the Energy Infrastructure segment.

  21. Slide 21: 3,676 Proportional MW Under Construction

    3,676 Proportional MW Under Construction Technology Segment 4% Gas Energy Renewables1 Infrastructure Renewables2 17% Utilities 11% 72% 96% 1. Includes solar, energy storage, and wind. 21 2. Excludes renewables projects in Chile, currently reported as part of the Energy Infrastructure segment.

  22. Slide 22: 5,116 Gross MW of Generation Under Construction

    5,116 Gross MW of Generation Under Construction Expected Commercial Business Location Fuel Gross MW AES Equity Interest Prior Segment Operations Date Solar 10 High Mesa 1 US-CO 75% 1H 2024 US & Utilities Energy Storage 10 Westwing 1 1 US-AZ Energy Storage 3 75% 1H 2024 US & Utilities Delta 1 US-MS W

  23. Slide 23: 5,116 Gross MW of Generation Under Construction

    5,116 Gross MW of Generation Under Construction Expected Commercial Business Location Fuel Gross MW AES Equity Interest Prior Segment Operations Date Hardy Hills Solar (AES Indiana)1 US-IN Solar 80 70% 1H 2024 US & Utilities Pike County (AES Indiana) US-IN Energy Storage 200 70% 2H 2024 US & Utiliti