    Forward-looking statements This presentation contains "forward-looking statements" within the meaning of applicable securities laws, including statements relating to life of mine production plans and exploration plans and the growth and strategy of Mandalay. Readers are cautioned not to place undue

  3. Slide 3: Investment highlights for 2012

    Investment highlights for 2012 ¾ A significant and growing producer of gold, silver and antimony from two mines 2011E Forecast Production 2012E Forecast Production Gold (oz) 18,000 – 22,000 25,000 – 35,000 Silver (oz) 1,500,000 – 1,900,000 2,700,000 – 3,000,000 Antimony (t) 1,500 – 2,500 1,800 – 2,2

  4. Slide 4: Strategy: Build a portfolio of high quality producing assets

    Strategy: Build a portfolio of high quality producing assets with excellent exploration potential What differentiates Mandalay is the discipline we bring to implementing the following principles: Producing Assets ¾ We acquire assets that are in production, or can be brought into production quickly.

  5. Slide 5: Record Revenue and EBITDA

    Record Revenue and EBITDA GROWING PRODUCTION, REVENUE, EBITDA 18,000 30,000,000 16,000 25,000,000 Ounces Au Equivalent Sold 14,000 20,000,000 12,000 10,000 15,000,000 US $ 8,000 10,000,000 6,000 5,000,000 4,000 0 2,000 ‐ ‐5,000,000 Q4‐09 Q1‐10 Q2‐10 Q3‐10 Q4‐10 Q1‐11 Q2‐11 Q3‐11 Au Equiv Sold Revenu

  6. Slide 6: Pacific Rim locations and tradeflow

    Pacific Rim locations and tradeflow ¾ Increasingly diverse • Metals, • Regions, • Customers ¾ 100% ownership of all projects & mines Q3, 2011 6

  7. Slide 7: Cerro Bayo district, Chile: target-rich land position

    Cerro Bayo district, Chile: target-rich land position NI43-101 Reserve-Resource veins ¾ 2011 Infill Drilling and Step-Out Drilling Laguna Verde Esperanza 2011 Scheduled blue sky targets 2012 Scheduled blue sky targets Identified targets extending historic veins ¾ (+40 of these, systematic review nee

  8. Slide 8: Exploration @ Laguna Verde – 2X goal for 2011

    Exploration @ Laguna Verde – 2X goal for 2011 • Delia NW, SE infilled to Ind. • Dagny & Fabiola have approx • Yasna added to reserves • Delia SE ext. discovered 2X more ore than planned • Bianca discovered & mined DAGNY Dalila FABIOLA YASNA Coyita Mill DELIA NW Delia SE BIANCA Tailings LAGUNA VERDE

  9. Slide 9: Delia vein SE & SE extension - infill and discovery

    Delia vein SE & SE extension - infill and discovery Area of next figure 9

  10. Slide 10: Delia vein SE extension discovery

    Delia vein SE extension discovery Coeur Holes MND Holes g/t AuEq g/t AuEq 2.87m @ 51.89 1.64m @ 3.01 1.31m @ 6.29 3.70m @ 13.64 1.15m @ 7.70 1.53m @ 5.11 2.59m @ 76.65 1.43m @ 5.65 4.06m @ 23.97 10

  11. Slide 11: Delia vein NW - successful infill of previously inferred resource

    Delia vein NW - successful infill of previously inferred resource and initial ore production Q3 ore development 11

  12. Slide 12: Fabiola vein - more ore found than expected

    Fabiola vein - more ore found than expected 12

  13. Slide 13: Cerro Bayo operating performance

    Cerro Bayo operating performance Mining Rate and Unit Cost Processing Rate and Unit Cost 100,000 70.00 100,000 70.00 USD/tonne USD/tonne 90,000 90,000 60.00 60.00 Tonnes per Quarter Tonnes per Quarter 80,000 80,000 70,000 50.00 70,000 50.00 60,000 40.00 60,000 40.00 50,000 50,000 40,000 30.00 40,000

  14. Slide 14: Cerro Bayo operating plan 2011 – 2012

    Cerro Bayo operating plan 2011 – 2012 Cerro Bayo Plan 2011E 2012E Saleable Gold Produced (oz) 6,000 -10,000 12,000 -16,000 Saleable Silver Produced (oz) 1.5 m -1.9 m 2.7 m -3.0 m Operating Costs (US$ m) 23-25 35 -39 Concentrate Shipping & Treatment (US$ m) 4-6 8-10 Cash Cost/oz Ag net Au Credit 10.0

  15. Slide 15: Costerfield mine, Australia

    Costerfield mine, Australia 15

  16. Slide 16: Costerfield drilling

    Costerfield drilling Successes to date • Multiple Alison intercepts ¾ Up to 1 m thick ¾ High grade • Multiple N-Lode intercepts Alison • Infill W-lode at depth N-lode W-lode 16

  17. Slide 17: Costerfield brownfield targets in NW-SE long section

    Costerfield brownfield targets in NW-SE long section 17

  18. Slide 18: Alison vein – high grade intercepts

    Alison vein – 2 high grade intercepts 18

  19. Slide 19: Costerfield performance

    Costerfield performance Mining Rate and Unit Cost 20,000 350 6,000 tpm design rate; AUD/tonne 300 $/t rising: water, ground conditions Tonnes per Quarter 15,000 250 200 10,000 150 Milling Rate 100 and Unit Cost 5,000 20,000 120 6,000 tpm design rate; AUD/tonne 50 Costs well controlled Tonnes per Qua

  20. Slide 20: Costerfield production plan 2011-2012

    Costerfield production plan 2011-2012 Costerfield Plan 2011E 2012E Saleable Gold Produced (oz) 10,000-14,000 14,000-18,000 Saleable Antimony Produced (t) 1,500-2,500 1,800-2,200 Operating Costs (US$ m) 25-29 20-35 Concentrate Shipping and Treatment (US$ m) 1.0-1.5 1.0-1.5 Cash Cost/ oz Au Equiv. (US

  21. Slide 21: La Quebrada copper-silver exploration project

    La Quebrada copper-silver exploration project Casa de Tugal Piedra Pit Manto outcrop 21

  22. Slide 22: Casa de Piedra – geology & drill map

    Casa de Piedra – geology & drill map 22

  23. Slide 23: Casa de Piedra – cross-section B-B’

    Casa de Piedra – cross-section B-B’ ? 23

  24. Slide 24: Mandalay financials (as at September 30, 2011)

    Mandalay financials (as at September 30, 2011) ¾Revenues, Costs and Capital • Expected 2011E revenue ($1,250/oz Au, $27/oz Ag, $12,500/t Sb) = $90-100 million • Expected operational costs inclusive of overheads = $60-70 million • Planned capital and exploration expenditures = $25-30 million ¾Balance

  25. Slide 25: 2011-2012 price protection program

    2011-2012 price protection program Put price Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2011 2012 Product (US$) 2011 2011 2011 2011 2012 2012 2012 2012 Total Total Au Puts 1,400 - - - - 7,000 7,000 7,000 7,000 - 28,000 % Cover 0.00% 0.00% 0.00% 0.00% 76.98% 75.19% 66.01% 64.18% - 70.15% Expected Production Ag Puts 25

  26. Slide 26: Capital & share structure (1-Nov-2011)

    Capital & share structure (1-Nov-2011) Shares outstanding 270,221,575 Options (1) 13,703,446 Warrants (2) 105,389,312 Shares fully diluted 389,351,833 Approx. Ownership Major shareholders: Shares Owned (basic) West Face Capital 43.25% 116,883,045 Plinian Capital (Mills, Sander, Swarup) 11.60% 31,354

  27. Slide 27: Delivering excellent returns

    Delivering excellent returns • MND's share price performance is up 28.26% ytd and up 131.6% over twelve months • MND (131.6%) has been outperforming both indices. Its Peer group had returns of 84.2%, while the TSX Global Mining Index had negative returns of 9.77% MND share price vs. peer groups and

  28. Slide 28: 2011 goals: being delivered

    2011 goals: being delivered Cerro Bayo Costerfield Portfolio 9Prove up an additional 9Continue decline and 9La Quebrada – Drill 3-5 years of minable stope development to Casa de Piedras and reserves from drilling lower levels, increasing Leoncita targets inferred resources and measured resource – •

  29. Slide 29: Investment advantages

    Investment advantages Big company In production – experience with the generating cash flow Opportunity to invest at agility of a junior from diversified portfolio the right time • Company is • Cash flowing company, with • Management team with – Multi-mine access to projects and strong excellent trac

  30. Slide 30: Appendices

    TSX: MND, MND.WT Appendices For more information, please contact: Greg DiTomaso Tel: 647.260.1566 Email: g.ditomaso@mandalayresources.com Company Website: www.mandalayresources.com 30

  31. Slide 31: Management and Board of Directors

    Management and Board of Directors Brad Mills, CEO Former CEO Lonmin plc, over 30 years of experience in Copper, Gold, PGMs Sanjay Swarup, CFO Former Lonmin plc, over 20 years of industry experience Mark Sander, COO 27 years of experience in exploration, strategy, and operating improvements Belinda L

  32. Slide 32: Metal price history

    Metal price history Source: www.metalbulletin.com 32

  33. Slide 33: Mandalay Reserves – Costerfield & Cerro Bayo

    Mandalay Reserves – Costerfield & Cerro Bayo Resource Ag Grade Ag Au Grade Au Cerro Bayo Reserves1 (t) (g/t) (cont. oz) (g/t) (cont. oz) Proven Reserves 0 ? 0 ? - Probable Reserves 778,175 307 7,679,817 2.48 62,035 P&P Reserves 778,175 307 7,679,817 2.48 62,035 Ore Sb Grade Sb Au Grade Au Costerfiel

  34. Slide 34: Mandalay Resources – Costerfield & Cerro Bayo

    Mandalay Resources – Costerfield & Cerro Bayo Resource Ag Grade Ag Au Grade Au Cerro Bayo Resources1 (t) (g/t) (cont. oz) (g/t) (cont. oz) Measured Resources 5,000 514 82,637 2.60 418 Indicated Resources 740,269 468 11,134,227 3.31 78,688 M&I Resources 745,269 468 11,216,864 3.30 79,106 Inferred Res

Mandalay Resources — Investor Presentation (November 2011) on 6ix