  1. Slide 1: Hamilton Works Community Liaison Committee (CLC) Meeting

    Hamilton Works Community Liaison Committee (CLC) Meeting July 31, 2024 1

  2. Slide 2: Agenda

    Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 1 May 2024 Meeting 4. Coke Battery Performance 5. Community Feedback 6. 2024 CLC Meeting Dates 7. Adjournment 2

  3. Slide 3: Agenda

    Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 1 May 2024 Meeting 4. Coke Battery Performance 5. Community Feedback 6. 2024 CLC Meeting Dates 7. Adjournment 3

  4. Slide 4: Coke Battery Performance – Method 303: Daily Performance Review

    Coke Battery Performance – Method 303 Performance Review – Daily (Q2 2024) Doors Lids Off-takes Date (% Leaks) (% Leaks) (% Leaks) 2015 Thresholds 54% 2% NA (July 2 start) 2016 Thresholds 32% 2% NA 2017-2019 Thresholds 10% 2% 5% 2020 - 2024 Thresholds 5% 1% 4% Apr - June 2024 Range 0 – 6.8% 0 – 0.52

  5. Slide 5: Coke Battery Performance – 30-Day Rolling Average

    Coke Battery Performance – Method 303 Performance Review – 30-Day Rolling Avg. (Q2 2024) Doors Lids Off-takes Charging (sec) Date (% Leaks) (% Leaks) (% Leaks) (log avg) 2015 Limits (July 2 start) 38% 0.8% 25% 12 sec 2016 Limits 22.5% 0.8% 15% 12 s 2017-2019 Limits 7% 0.8% 4.2% 12 s 2020 - 2024 Limi

  6. Slide 6: Coke Battery Performance – Daily Pushing Observations

    Coke Battery Performance – Method 303 Performance Review – Daily Observations (Q2 2024) Pushing Emission Date (opacity %) 2015 Threshold (July 2 start) ≥ 50% 2016 – 2018 ≥ 50% 2019 ≥ 40% 2020 - 2024 ≥ 30% Apr - June 2024 0 – 24% Range (4.62%) (Average) Apr – June Operational Adjustments • In complia

  7. Slide 7: Coke Battery Performance: Additional Items, Community Feedback

    Coke Battery Performance Additional Items Community Feedback • No community feedback was received by Stelco in Q2 2024 • MECP invited to provide verbal comments 7

  8. Slide 8: Agenda

    Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 1 May 2024 Meeting 4. Coke Battery Performance 5. Community Feedback 6. 2024 CLC Meeting Dates 7. Adjournment 8

  9. Slide 9: Community Feedback

    Community Feedback Additional Questions? • Please contact us with concerns or questions about our operations - environment@stelco.com 9

  10. Slide 10: 2024 CLC Meeting Dates

    2024 CLC Meeting Dates Wed. Jan. 31 Wed. May 1 Wed. July 31 Wed. Oct. 9 10

  11. Slide 11: Agenda

    Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 1 May 2024 Meeting 4. Coke Battery Performance 5. Community Feedback 6. 2024 CLC Meeting Dates 7. Adjournment 11

  12. Slide 12: Stelco – The Steel Company of Canada

    STELCO . The Steel Company of Canada