Kenya Electricity Generating Company Plc · NSEKE:KEGN

Kenya Electricity Generating — Technical Presentation (November 2016)

23 slides from Kenya Electricity Generating's technical presentation, Nov 10, 2016

  1. Slide 1: Site Visit & Pre-bid Meeting

    CONFIDENTIAL Tender for EPC+F of Modular Geothermal Power plants at Olkaria (KGN-BDD-10-2016) Site Visit & Pre-bid Meeting Moses Nthiga, Ass. Projects Execution Manager 10th November 2016, Olkaria, Naivasha, Kenya Disclaimer: No part of this report may be circulated, quoted, or reproduced for distri

  2. Slide 2: Programme

    0 PROGRAMME: Arrival at Olkaria Geothermal Spa (inside Hell's Gate National Park) 10:00 am Registration of Attendees 10:00 am to 10:30 am Safety Briefing 10:30 am to 10:35 am Welcome and Introductions 10:35 am to 10:45 am Overview of proposed EPC+F project 10:45 am to 11:15 am Coffee Break 11.15 am

  3. Slide 3: KenGen's Generation Mix

    0 KenGen’s Generation Mix 25 30 1667 259 Wind 2% 534 Thermal 17% Transforming from hydro dominated to Geothermal 32% geothermal by adding capacity 820 83% Renewable Hydro 49% KenGen Capacity Hydro Geothermal Thermal Wind EPP Total Mix 2016 2

  4. Slide 4: KenGen's Geothermal Power Plants

    0 KenGen’s Geothermal Power Plants  Geothermal utilizes natural heat from the earth  KenGen’s geothermal plants Olkaria I – 45 MWe Olkaria I AU – 150 MWe Olkaria II – 105 MWe Olkaria IV – 150 MWe  Wellheads – 81.1 MWe  Eburru – 2.4 MWe Total = 533.5 MWe  IPPs generate 139 + 3.21 MW at Olkar

  5. Slide 5: KenGen's Geothermal Power Plant Technology

    0 KenGen’s Geothermal Power Plant Technology • 1. Conventional Power plants with centralized steam gathering system • 2. Wellhead power plant at well sites • 3. Proposed Modular power plants- wellheads with limited steam gathering system 4

  6. Slide 6: Project located within Hell's Gate National Park

    0 THE PROJECT IS LOCATED WITHIN HELLS GATE NATIONAL PARK, CENTRAL DIVISION OF NAIVASHA SUBCOUNTY IN THE NAKURU COUNTY The project is located in Hell’s Gate National Park managed by Kenya Wildlife Service (KWS). All works associated with this project shall fully comply with Project Site the requireme

  7. Slide 7: Outline

    OUTLINE: 1 Project Implementation Structure 2 Employer Requirements 3 Evaluation Criteria 4 Selected Tender clauses 5 Addendums and Clarifications 6

  8. Slide 8: Project Implementation Structure: The EPC+F Model

    1 Project Implementation Structure The EPC+F Model: 7

  9. Slide 9: EPC+F Tender Structure

    1 Project Implementation Structure EPC+F Tender Structure Package 1- Design, procure (manufacture), Supply, install commission Geothermal Modular Power Plants, including all related infrastructure and services, with a guaranteed minimum net power output of 23 MWe. The contractor is required to arran

  10. Slide 10: Outline

    OUTLINE: 1 Project Implementation Structure 2 Employer Requirements 3 Evaluation Criteria 4 Selected Tender clauses 5 Addendums and Clarifications 9

  11. Slide 11: Employer's Requirements: Package 1

    2 Employer’s Requirements EPC Contractor scope include: Package 1- Design, procure (manufacture), Supply, install commission Geothermal Modular Power Plants including all related infrastructure and services with a guaranteed minimum net power output of 23 MWe using the wells Well Pressure Steam Brin

  12. Slide 12: Employer's Requirements: Package 2

    1 Employer’s Requirements EPC Contractor scope include Package 2- Design, procure (manufacture), Supply, install commission Geothermal Modular Power Plants including all related infrastructure and services with a guaranteed minimum net power output of 23.3 MWe using the wells Well Pressure Steam Bri

  13. Slide 13: Map of Olkaria Geothermal Field

    1 Employer’s Requirements MAP OF OLKARIA GEOTHERMAL FIELD Package 1 Package 2 12

  14. Slide 14: Project Locations: Package 1

    2 Employer Requirements Project Locations: Package 1 13

  15. Slide 15: Project Locations: Package 2

    2 Employer Requirements Project Locations: Package 2 14

  16. Slide 16: Outline

    OUTLINE: 1 Project Implementation Structure 2 Employer Requirements 3 Evaluation Criteria 4 Selected Tender clauses 5 Addendums and Clarifications 15

  17. Slide 17: Evaluation Criteria

    3 Evaluation Criteria • This is a Single Stage Two Envelope tendering process – Technical Bid and Financial Bid are submitted at the same time in two separate envelopes. – Technical bid is opened on the tender submission date and evaluated thereafter – Financial bids for bidders who pass the Technic

  18. Slide 18: Evaluation Criteria: Lowest Evaluated Bidder

    3 Evaluation Criteria Determination of lowest Evaluated Bidder EPC Price A Add Cost of Loan B Add Penalty for late completions C (ref Appendix A, clause 1.2.1 (a)) Subtract Value of Extra MW D (ref Appendix A, clause 1.2) Add Omitted obligations E (ref Appendix A, clause 1.2 (a)) SUM TOTAL EVALUATED

  19. Slide 19: Outline

    OUTLINE: 1 Project Implementation Structure 2 Employer Requirements 3 Evaluation Criteria 4 Selected Tender clauses 5 Addendums and Clarifications 18

  20. Slide 20: Selected Tender Clauses

    4 Selected Tender Clauses Clause TDS 20 – The two packages will be evaluated and awarded separately. Tenderers may tender for one or both of the packages. Clause TDS 30 – The deadline for Tender submission is: 22nd December 2016 at 10am Clause TDS 3 – project implementation period 20 months There ar

  21. Slide 21: Outline

    OUTLINE: 1 Project Implementation Structure 2 Employer Requirements 3 Evaluation Criteria 4 Selected Tender clauses 5 Addendums and Clarifications 20

  22. Slide 22: Addendums and Clarifications

    5 Addendums and Clarifications • Clarifications  About 35 request for clarifications have been so far received  29 of these are already answered • Addendums  1 batch of addendum containing 10 items has been issued Only Written Answers are accepted as clarifications 21

  23. Slide 23: Thank You

    THANK YOU… God Bless Kenya 22