  1. Slide 1: Stakeholder Consultation Meeting

    Stakeholder Consultation Meeting Oakdale West Estate March 2020 1

  2. Slide 2: Overview

    Overview • Welcome and Introductions • Environmental Performance Update • Community Interactions & Traffic Arrangements Update • Safety Update • Upcoming Project Program • Stakeholder Feedback & Questions 2

  3. Slide 3: Welcome and Introductions

    Welcome and Introductions Project Team: Organisation Goodman AT&L Burton Robson Civil SLR Ersed Ecologique Contractors Projects Consulting Role Proponent Project Manager Oakdale West Western Stakeholder Environmental Kat Duchatel & Contract – Stage 1 North South Engagement Representative Superintend

  4. Slide 4: Environmental Performance

    Environmental Performance ER INSPECTIONS AND AUDITS INCIDENTS AND COMPLAINTS AS INCLUDED IN MONTLY REPORTS 4

  5. Slide 5: Community Interactions & Traffic Arrangements

    Community Interactions & Traffic Arrangements • Targeted consultation meetings held with Emmaus College, Trinity Primary and Mamre Anglican Schools to discuss the use of Bakers Lane for construction traffic (as requested by TfNSW instead of Goodman’s proposal to use Abbotts Road/Aldington Road). • C

  6. Slide 6: Traffic Arrangements

    Traffic Arrangements oan | Be <> global environmental and advisory solutions S L Re 6

  7. Slide 7: Safety

    Safety • No external safety incidents • Minor internal safety incidents. No injuries • Minor unexpected finds onsite, including asbestos finds, have now all been addressed, with the last of the impacted material having been removed in accordance with EPA, the Unexpected Finds Protocol and Council gu

  8. Slide 8: Project Program – March/April

    Project Program – March/April Oakdale West Estate – Burton Western North South Link Road – Contractors Robson Civil Northern Section: • Acceleration works to Lot 2B • Importation of fill to pavement • Earthworks to Western Noise Bund subgrade level • Cut to Fill in Precinct 1 • Continuation of storm

  9. Slide 9: Communications and Consultation Channels

    Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: community.oakdalewest@goodman.com • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E

  10. Slide 10: Stakeholder Feedback & Questions

    Stakeholder Feedback & Questions 10