Hastings Technology Metals Limited · ASX:HAS

Hastings Technology Metals — Macquarie Critical Minerals Forum 2023

33 slides from Hastings Technology Metals's conference presentation, Jun 28, 2023

  1. Slide 1: ASX Announcement: Presentation – Macquarie Group's Critical Minerals Forum

    \ ASX Announcement 28 June 2023 Presentation – Macquarie Group’s Critical Minerals Forum Australia’s next rare earths producer, Hastings Technology Metals (ASX: HAS) (Hastings or Company), advises that Teck Lim, Chief Financial Officer, is presenting at the Macquarie Group’s Critical Minerals Forum

  2. Slide 2: Australia's Next Rare Earths Producer

    Australia’s Next Rare Earths Producer Yangibana Rare Earths Project Macquarie Critical Minerals Forum Hastings Technology Metals Limited | ASX : HAS 28 June 2023

  3. Slide 3: Importance notices and disclaimer

    Importance notices and disclaimer All currency amounts are in A$ unless stated otherwise Disclaimer This presentation has been prepared by Hastings Technology Metals Limited (“Company” or “Hastings”). This The Company is under no obligation to, nor makes any undertaking to, update or revise such for

  4. Slide 4: Our investment proposition

    Our investment proposition Yangibana is positioned to supply rare earths needed for permanent magnets for the global energy transition Access to significant value adding Global energy transition creating opportunities through strategic investment in demand for rare earth magnets for TSX-listed rare

  5. Slide 5: Corporate snapshot

    Corporate snapshot Stage 2 Hydrometallurgical plant Developing the world-class Yangibana Rare Earths Project in Western Australia Halls Creek Share price1 Shares on issue Market capitalisation Broome $1.21 129.2m $156m Port Hedland Dampier Onslow Onslow Plant Cash at 30 April 2023 Exchangeable bonds

  6. Slide 6: Our markets

    Our markets Macquarie Critical Minerals Forum | 5

  7. Slide 7: Supplying the green economy

    Supplying the green economy Rare earth magnets are critical inputs for electric vehicle traction motors and wind turbine generators Significant government NdPr are critical elements of the global energy transition support for rare earths Inflation Reduction Act LCD / PDP Screens Speakers Defence US$

  8. Slide 8: Capitalising on high growth market

    Capitalising on high growth market Fueled by the electrification trend – high growth in magnets for electric vehicles and wind turbines Anticipated Global REO Magnet Demand Growth by Industry1 216kt Electric drivetrains and wind energy to represent 59% of rare earth oxide demand for magnets by 2032

  9. Slide 9: Global supply deficit imminent

    Global supply deficit imminent Significant NdPr supply deficit expected – requiring around 13x Yangibana projects in the next decade NdPr Oxide – Forecast Supply – Demand Balance Supply Demand Demand • Demand for NdPr oxide expected double Forecast over the next decade, fuelled Q1 2025 Stage 1 conce

  10. Slide 10: Yangibana project summary

    Yangibana project summary Macquarie Critical Minerals Forum | 9

  11. Slide 11: Unique tier one asset

    Unique tier one asset World-class deposit with unrivalled high percentage of NdPr:TREO in the orebody Significant exploration targets providing growth optionality Average NdPr:TREO Ratio Yangibana Mineral Resources and Ore Reserves1 Mineral Resources Ore Reserves 60 Sichuan 14% 50 Exploration target

  12. Slide 12: Yangibana Rare Earths Project

    Yangibana Rare Earths Project Enhanced two-stage delivery model supporting a de-risked pathway to becoming Australia’s next rare earths producer by Q1 CY2025 Stage 1 – Concentrate Stage 2 – MREC Mining Beneficiation Hydrometallurgy Crushing, grinding, Cracking, leaching, 20.9 Mt Ore Reserve flotatio

  13. Slide 13: Yangibana project progress

    Yangibana project progress All primary approvals in place and ~$100m already invested in early infrastructure works at Yangibana Yangibana Airstrip – complete First flight on 18 May 2023 SipHon Well Borefield – complete 20km pipeline; 6 bores Kurrbili Accommodation Village SipHon Well Borefield Site

  14. Slide 14: Beneficiation plant contract

    Beneficiation plant contract Fixed-price contract for construction of beneficiation plant and associated infrastructure de-risking project delivery ~$210m binding terms sheet entered with GR Engineering Lowers project delivery risks, provides process and product quality guarantees Lower cost compare

  15. Slide 15: Stage 1 capex estimates

    Stage 1 capex estimates Capital intensity per % NdPr produced remains competitive with other developers Stage 1 capital cost Capex (as at 31-May-23) Total Cost Spent to Date Remaining % (A$M) (A$M) (A$M) 55 12% Plant Earthworks 30 - 30 6% Plant & NPI 180 - 180 38% 59 12% Total Plant 210 - 210 44% 21

  16. Slide 16: Stage 1 opex estimates

    Stage 1 opex estimates Opex intensity per % NdPr produced remains competitive with other developers Stage 1 operating cost Cost Cost 1.8 Total Cost 3.1 Operating Costs % A$/kg US$/kg 8% (A$M pa) 14% REO REO 2.3 10% Labour 25.8 14 3.1 2.1 1.8 8% Power 14.9 8 1.8 1.2 A$22.7/kg Reagents and Consumables

  17. Slide 17: Strong project economics

    Strong project economics Providing attractive returns through all stages of the Yangibana Project Stage 1 – Concentrate - MREC Stage 2 – MREC Yangibana mine and beneficiation plant Hydrometallurgical plant Update CONSTRUCTION PHASE • Tolling (via a third party) of Stage 1 Total capital costs $470m $

  18. Slide 18: Stage 1 funding

    Stage 1 funding1 Expected funding envelope of $770m, which could include up to 60% debt Hastings Debt Equity Lender discussions Technology ~$380 - $420m ~$350 - $390m • Advanced discussions with NAIF ($220m Metals Ltd debt facility), EFA ($100m letter of support) and commercial financiers (banks, bo

  19. Slide 19: Project execution schedule

    Project execution schedule Staged development strategy enabling a quicker and lower risk pathway to cashflow to support funding of Stage 2 2023 2024 2025 2026 2027 2028 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 EPC terms Stage 1 - Yangibana agreed Enabling Works (Airstr

  20. Slide 20: Concentrate and MREC offtake

    Concentrate and MREC offtake Market-leading strategic counterparties Counterparty thyssenkrupp Materials Trading1 Neo Performance Materials2 Schaeffler Technologies AG3 Solvay4 Counterparty Essen, Germany Toronto, Canada Herzogenaurach, Germany LaRochelle, France headquartered Binding Framework Agre

  21. Slide 21: Approach to sustainability

    Approach to sustainability Helping to advance the Sustainability Development Goals as a signatory of the UN Global Compact Health and safety Maintained a loss time injury frequency rate of 0.0 during the period up to 31 March 2023 Climate Change Commitment of minimum 40 per cent renewables allowed f

  22. Slide 22: Neo strategic partnership

    Neo strategic partnership Macquarie Critical Minerals Forum | 21

  23. Slide 23: Hastings mine-to-magnet strategy

    Hastings mine-to-magnet strategy Focused on the staged delivery of the Yangibana Rare Earths Project, with optionality to pursue mine-to-magnet business strategy Stage 1 – Yangibana mine Stage 2 – Onslow Stage 3 – Mine-to-magnet strategy Mining Beneficiation Hydrometallurgy Oxide separation RE metal

  24. Slide 24: Strategic partnership with Neo

    Strategic partnership with Neo Offtake heads of agreement signed on 13 June 2023, building on the 19.9% shareholding in Neo Neo FY22 EBITDA of A$109m and net assets of A$703m Vertically integrated mine-to-magnet supply chain Potential rare earth sales to Neo • Stage 1 – Up to 25,000tpa concentrate R

  25. Slide 25: Conclusion

    Conclusion Macquarie Critical Minerals Forum | 24

  26. Slide 26: Potential value upside

    Potential value upside Strong correlation between benchmark NdPr price and Hastings share price over long term HAS 24-month share price vs NdPr oxide price1 8.00 Historical HAS Share Price (A$/sh) NdPr Price (Historical) NDPr Price (Blended Forecast) 200 180 7.00 160 6.00 Long-term NdPr Oxide Foreca

  27. Slide 27: Our investment proposition

    Our investment proposition Yangibana is positioned to supply rare earths needed for permanent magnets for the global energy transition Macquarie Critical Minerals Forum | 26

  28. Slide 28: Appendices

    Appendices Macquarie Critical Minerals Forum | 27

  29. Slide 29: Board of Directors

    Board of Directors Charles Lew Jean Claude Steinmetz Bruce McFadzean Guy Robertson Mal Randall Neil Hackett Executive Chairman Non Executive Director Non Executive Director Finance Director Non Executive Director Non Executive Director • Took over HAS in December • Joined the Board in July • Joined

  30. Slide 30: Executive Team

    Executive Team Alwyn Vorster Rudolph van Niekerk Teck Lim Robert Klug Rachael Ward-Pryce Gareth Fleming CEO (interim) Chief Operating Officer Chief Financial Officer General Counsel Head of People Acting Project Director • Joined Hastings in • Joined Hastings in early • Chartered accountant with • J

  31. Slide 31: Project milestones

    First resource to construction Aug 2022 Feb 2019 Jun 2020 Oct 21 22.1% investment Successful second Schaeffler master supply Maiden in Neo; Wyloo pilot plant test – agreement signed Sustainability Report $150m investment Q3 2023 higher yield PROJECT MILESTONES Apr 2021 Feb 2022 Jan 2023 Debt financi

  32. Slide 32: Neo Performance Materials

    Neo Performance Materials Listed on the TSX and headquartered in Toronto, with a market capitalisation of CAD362 (A$412m) Background Share Price Performance – Last 12 months • Neo Performance Materials Inc. (Neo or the Company) is listed on the TSX and headquartered in Toronto, 18 0.9 Canada and has

  33. Slide 33: Australia's next rare earths producer

    Maiden flight to Yangibana Airstrip Australia’s next rare earths producer hastingstechmetals.com Macquarie Critical Minerals Forum | 32