Xcel Energy Inc. · NASDAQ:XEL

Xcel Energy — Technical Presentation (October 2011)

21 slides from Xcel Energy's technical presentation, Oct 12, 2011

  1. Slide 1: SPS IRP Fundamentals

    SPS IRP Fundamentals Craig Berg, Senior Resource Planner October 12, 2011 1

  2. Slide 2: Agenda

    Agenda „ Resource Planning Objectives „ Resource Planning Process „ Resource Planning Tools/Concepts ‹ L&R Table ‹ Supply Curve ‹ Load Duration Curves ‹ Dispatch Models „ Key Planning Considerations 2

  3. Slide 3: Resource Planning Objectives

    Resource Planning Objectives 1. Plan for capacity additions to promote the reliable operation of the electrical system 2. Minimize present worth of costs (fixed & variable) 3. Adhere to laws/regulations (environmental) 3

  4. Slide 4: Resource Planning Process

    Resource Planning Process Load Existing SPS DSM Impact Forecast System Info Strategist Generation Generic Simulate And Fuel Technologies SPS System Spot Market Bid Offers Resource Expansion Plans 4

  5. Slide 5: After initial modeling using generic resources, solicit RFP Responses

    After initial modeling using generic resources, solicit RFP Responses „ Issue RFP ‹ Bids are due 90 –120 days after issuance of RFP ‹ Bid information includes: „ Markup of Model PPA „ Project development schedule „ Capacity MW offered & Price ($/kW-mo) „ Guaranteed Heat Rates „ VOM, FOM, EFOR, Maint

  6. Slide 6: Screen Bids

    Screen Bids „ Objective: Reduce the number of bids down to a more manageable group ‹ Eliminate bids that don’t meet minimum bid criteria ‹ Eliminate bids that cannot be developed within proposed schedule ‹ Eliminate bids based on screening analysis using spreadsheet models 6

  7. Slide 7: Develop Resource Portfolios

    Develop Resource Portfolios „ Model bids as “Alternatives” from which STRATEGIST can construct Least-Cost Plans under a variety of future assumptions ‹ Gas Prices ($4.00, $6.00, $8.00) ‹ High and low peak demand and sales ‹ Inflation rates ‹ Environmental regulations (SO2, NOx, Hg, CO2) „ Select mul

  8. Slide 8: Select Winning Bidders

    Select Winning Bidders „ Considering Capital RR/ECC, system dispatch costs, transmission infrastructure costs, and proposed markups to Model PPA „ Complete contract negotiations with winning bidders „ File for appropriate regulatory approvals 8

  9. Slide 9: Graphical Representation of L&R

    “Graphical Representation of L&R” 6,500 6,000 5,500 5,000 4,500 Wholesale + 13.6% 4,000 Retail + 13.6% Net Dep. Gen (Incl. J4) 3,500 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 9

  10. Slide 10: SPS Supply Curve

    SPS Supply Curve $180.00 30.00 $160.00 25.00 $140.00 Gas equiv. HR (mmBTU/MWh) Production cost ($/MWh) $120.00 20.00 $100.00 15.00 $80.00 $60.00 10.00 $40.00 5.00 $20.00 $0.00 0.00 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 Cumulative MW 10

  11. Slide 11: SPS 2013 & 2020 Load Duration Curves

    SPS 2013 & 2020 Load Duration Curves SPS 2013 & 2020 Load Duration Curves 5,800 5,300 4,800 4,300 MW 3,800 3,300 2,800 2,300 1,800 0% 20% 40% 60% 80% 100% % of Hours 2013 L 2020 L Coal&Wind NG Gen 11

  12. Slide 12: STRATEGIST Dispatch Model

    STRATEGIST Dispatch Model SPS Supply Generation Resources Alternatives CER Module GAF Module LFA PROVIEW Module Optimization Demand and Energy Least-Cost Plans Forecast 12

  13. Slide 13: Capital Expenditure and Recovery Module (CER)

    Capital Expenditure and Recovery Module (CER) Function: ‹ Model the revenue requirements and provide other key financials with respect to different capital projects Applications: ‹ Comparison of alternative projects/portfolios ‹ Expansion planning analysis for PROVIEW 13

  14. Slide 14: Capital Cost Recovery Profiles

    “Capital Cost Recovery Profiles” $100 Million Investment $20,000,000 $18,000,000 $16,000,000 $14,000,000 RR $12,000,000 Levelized $10,000,000 ECC $8,000,000 $6,000,000 $4,000,000 1 4 7 10 13 16 19 22 25 28 31 34 37 40 Years 14

  15. Slide 15: Generation and Fuel Module (GAF)

    Generation and Fuel Module (GAF) Function: Calculate System Production Costs Applications: „ Evaluate generation fuel mix „ Examine emissions compliance „ Analyze high/low fuel prices & portfolio risk 15

  16. Slide 16: Identify Resource Need by Type

    Identify Resource Need by Type „ Demand and Energy Forecast ‹ Monthly demand forecast at the generator level for 20 years ‹ Monthly energy sales forecast at customer meter for 20 years „ Use Historical Load Shape ‹ Take 8760 load shape => EEI processor => Typical week load duration curve ‹ One load

  17. Slide 17: PROVIEW

    PROVIEW Function: Determine the most cost effective mix and timing of possible resource additions and rank them based upon objective function (NPV of Revenue Req.) Applications: „ Develop optimal mix of owned and purchased resources by resource type „ Plans ranked by the defined objective function (

  18. Slide 18: Key Planning Considerations

    Key Planning Considerations „ Available Resource Options „ Multiple Jurisdictions (TX, NM and FERC) ‹ Different rules in various jurisdictions ‹ Different modeling assumptions ‹ Different cost allocation and cost recovery „ Load Forecast Uncertainty „ Capital lease issues „ Model Inputs (fuel prices

  19. Slide 19: Available Resource Options

    Available Resource Options „ Nuclear ‹ Escalating capital cost & waste issue not resolved „ Energy Efficiency and Load Management ‹ Minimizes use of societal resources ‹ Hedge against fuel cost uncertainties „ Coal ‹ Community opposition ‹ Capture/sequestration not resolved ‹ Exposure to carbon cost

  20. Slide 20: Available Resource Options (cont.)

    Available Resource Options (cont.) „ Natural Gas ‹ Fuel price uncertainty ‹ Exposure to carbon costs „ Renewables ‹ Escalating capital cost ‹ Transmission limited ‹ Integration costs 20

  21. Slide 21: Xcel Energy

    Xcel Energy’ RESPONSIBLE BY NATURE™ Q

Xcel Energy — Technical Presentation (October 2011) on 6ix