Sandfire Resources Ltd · ASX:SFR

Sandfire Resources — Q4 FY2017 Earnings Presentation

20 slides from Sandfire Resources's earnings presentation, Jul 28, 2017

  1. Slide 1: June 2017 Quarterly Report Presentation and Webcast

    For personal use only June 2017 Quarterly Report Presentation and Webcast 28 July 2017 Access this presentation at: http://webcasting.boardroom.media/broadcast/5962ded2c8d9977c 89ce70f3 or http://www.sandfire.com.au Earthworks underway for the box-cut at the new Monty copper-gold mine 1

  2. Slide 2: Important Information and Disclaimer

    Important Information and Disclaimer Forward-Looking Statements For personal use only This presentation has been prepared by Sandfire Resources NL. This document contains background information about Sandfire Resources NL current at the date of this presentation. The presentation is in summary form

  3. Slide 3: Important Information and Disclaimer – Competent Person's Statements

    Important Information and Disclaimer Competent Person’s Statement – Ore Reserves and Mine Plan The information in this report that relates to Ore Reserves and Mine Plan is based on information compiled by Mr Neil Hastings who is a Member of The Australasian Institute of For personal use only Mining

  4. Slide 4: Agenda

    Agenda For personal use only ► Highlights ► Safety ► Operations ► Guidance and costs ► Development ► Exploration ► Summary 4

  5. Slide 5: June 2017 Quarterly Highlights

    June 2017 Quarterly Highlights Production and Operations For personal use only ► June 2017 Quarter: 17,092t copper and 9,721oz gold produced; C1 US$0.95/lb ► FY2017: 67,088t of contained copper, 38,623oz of contained gold; C1 costs US$0.93/lb ► Mining contract extension with Byrnecut Mining (4-year

  6. Slide 6: Safety

    Safety Total Recordable Injury Frequency Rate (TRIFR) of 4.9 at Quarter-end (vs. 5.7 at For personal use only ► March 2017 Quarter-end) ► Principal hazard management – ongoing ► Focus being applied to improving safety leadership, culture and assurance of critical controls 10 TRIFR 8 6 4 2 0 Sep'15 D

  7. Slide 7: Operations – Mining

    Operations – Mining For personal use only Underground production ► Total ore production for the Quarter of 393,286 tonnes grading 4.6% Cu ► Mine remains in balance between production and back-fill ► DeGrussa and Monty mining contract extension awarded to Byrnecut (4 year term) 7

  8. Slide 8: Operations – Processing

    Operations – Processing For personal use only Mill throughput ► 412,271 tonnes milled at average feed grade of 4.6% Cu Recovery ► Quarterly copper recovery of 90.8%; Gold recovery 46.7% (FY2018 guidance: copper ~92%, gold ~44%) ► Further improvements to recovery in FY2018 with additional rougher flo

  9. Slide 9: Operations – Capital programs

    Operations – Capital programs Underground pumping station For personal use only ► Expected to commence commissioning August 2017 ► Ahead of C4 and C5 drilling Rougher column cell ► Commenced commissioning early July 2017 ► Initial positive signs in copper recovery and concentrate grade – expecting ~

  10. Slide 10: Development – Monty Copper-Gold Project

    Development – Monty Copper-Gold Project For personal use only ► Sandfire is Manager of the Springfield JV – interests Sandfire 70%/Talisman 30% ► Mining contract awarded to Byrnecut (combined operations between DeGrussa and Monty JV) ► Approval for the Mining Proposal and Mine Closure Plan ► Civil w

  11. Slide 11: Operations – Sales

    Operations – Sales For personal use only ► June 2017 Quarter: Sales of 72,525 tonnes of concentrate (dry) containing 17,350 tonnes of copper (16,614 tonnes payable) and 9,135 ounces of gold (8,443 ounces payable) ► FY2017: Sales of 272,925 tonnes of concentrate (dry) containing 65,403 tonnes of copp

  12. Slide 12: Operations – FY2017 Unit Operating Costs

    Operations – FY2017 Unit Operating Costs Q4FY2017 FY2017 For personal use only Unit costs – DeGrussa Mine Result Result Commentary (US$/lb) (US$/lb) Mining (net of development) 0.37 0.39 Processing 0.25 0.28 Business services 0.14 0.14 Pleasing cost performance at both a gross and unit cost level fo

  13. Slide 13: Operations – FY2018 Operating, Unit Cost and Capital Guidance

    Operations – FY2018 Operating, Unit Cost and Capital Guidance DeGrussa Mine FY2018 Guidance Tonnes Cu Au Commentary For personal use only Mining 1.6M 4.4% 1.6g/t C1 – 43%, DG – 10%. C4 – 19%, C5 – 21%, Devt – 7% Maintaining stockpile volumes following drawdown in Processing 1.6M 4.3% 1.6g/t FY2017 L

  14. Slide 14: Development and Growth – Black Butte Copper Project, USA

    Development and Growth – Black Butte Copper Project, USA 61% stake in Black Butte Copper Project, central Montana (via For personal use only ► stake in Tintina Resources Inc) ► Advanced, high quality copper project in stable jurisdiction: – NI 43-101 Measured and Indicated Resources of 15.7Mt gradin

  15. Slide 15: Doolgunna Exploration Overview

    Doolgunna Exploration Overview ► Exploration continuing as a priority along highly prospective VMS For personal use only corridor that hosts the DeGrussa and Monty deposits: – RC drilling at the Red Bore East Prospect to test the C5 host stratigraphy along strike from DeGrussa – The continuation of

  16. Slide 16: Doolgunna Exploration Overview

    Doolgunna Exploration Overview ► Exploration advancing at multiple prospects within Greater Doolgunna area: For personal use only ► ~70,000m of AC/RAB and RC drilling during the quarter ► Committed to in-ground spend with over ~ 200,000m drilled FY to date ► Farm-in deal completed with Great Western

  17. Slide 17: Donnington Prospect, Temora – 100% Sandfire

    Donnington Prospect, Temora – 100% Sandfire ► 8 holes completed Schematic Section showing drilling results to date Location of Drilling on RTP Magnetic image Porphyry alteration over 1.2km strike Assays awaited For personal use only ► Extended mineralisation along strike, down dip to A A’ > 700m and

  18. Slide 18: Summary & Outlook

    Summary & Outlook For personal use only ► Strong and consistent production and cost performance – FY2017: 67,088t contained copper, 38,623oz contained gold, C1 costs $0.93/lb – FY2018 Guidance: 63-66kt contained copper, 35-38koz contained gold, C1 costs $1.00-1.05/lb – Monty permitted and under deve

  19. Slide 19: Appendix: Mine Plan, Ore Reserve and Mineral Resource

    Appendix: Mine Plan, Ore Reserve and Mineral Resource ► Updated Mine Plan, incorporating the Monty Mine and OSPA (100% basis): For personal use only ► Total 7.0Mt grading 5.1% Cu and 1.6g/t Au for 359,000t of contained copper and 368,000oz of contained gold; ► DeGrussa’s 1.6Mtpa concentrator to be f

  20. Slide 20: Contact Details: Sandfire Resources NL

    For personal use only Contact Details: Sandfire Resources NL Registered Office and Principal Place of Business Level 1, 31 Ventnor Avenue, West Perth, Western Australia 6005 T +61 8 6430 3800 F +61 8 6430 3849 www.sandfire.com.au 20

Sandfire Resources — Q4 FY2017 Earnings Presentation on 6ix