First Quantum Minerals Ltd. · TSX:FM
First Quantum Minerals — Investor Presentation (January 2014)
42 slides from First Quantum Minerals's investor presentation, January 2014
Slide 1: Introduction - The Trident Project
Introduction - The Trident Project January 2014 www.first-quantum.com TSX: FM LSE: FQM LuSE: FQMZ
Slide 2: Trident Project Location
TRIDENT PROJECT LOCATION January 2014 2
Slide 3: About the Trident Project
ABOUT THE TRIDENT PROJECT Trident Project: Located in the Solwezi District of Northwestern Province, Zambia Approximately 150km from Solwezi on the T5 main road to Mwinilunga Comprises five prospecting large scale licences A number of attractive base metal prospects including the Sentinel de
Slide 4: Trident Project Layout
TRIDENT PROJECT LAYOUT January 2014 4
Slide 5: Sentinel Mine in Construction – Commissioning Mid 2014
SENTINEL MINE IN CONSTRUCTION – COMMISSIONING MID 2014 Updated resource published May 2012: 514 boreholes for 172,692m defined an NI43-101 resource of: Total measured & indicated : 1,027Mt @ 0.51% Cu Inferred : 165Mt @ 0.42% Cu Cut-off : 0.2% Cu Mineral Reserve: 774 Mt @ 0.50% Cu Proved
Slide 6: Enterprise Mine in Approval – Early Works Underway
ENTERPRISE MINE IN APPROVAL – EARLY WORKS UNDERWAY Maiden resource published December 2012: 359 boreholes for 116,000m defined an NI43-101 resource of: Total measured indicated : 40.1Mt @ 1.07% Ni Inferred : 7.1Mt @ 0.70% Ni Cutoff : 0.15% Ni Mineral Reserve: 32.7 Mt @ 1.10% Ni Further p
Slide 7: Regional Exploration
REGIONAL EXPLORATION Regional exploration: Over US$60m expenditure on exploration to date across Trident. Airborne magnetic, radiometric and time domain electromagnetic surveys and geological mapping over all licences Soil geochemical sampling over all licences amounting to 20,652 samples Re
Slide 8: Sentinel Mine Under Construction
SENTINEL MINE UNDER CONSTRUCTION January 2014 8
Slide 9: About the Sentinel Mine – Project Scope
ABOUT THE SENTINEL MINE – PROJECT SCOPE 55Mtpa target throughput 3 semi mobile in pit crushers and assembly of large scale mining equipment Largest operating SAG/Ball mill trains in the world (100MW milling power) 265,000t of freight = 14,500 truckloads of materials 2 rivers to be dammed/d
Slide 10: Progress Photos – Sentinel Plant Area
PROGRESS PHOTOS – SENTINEL PLANT AREA AERIAL PHOTO 31-DEC-2013 January 2014 10
Slide 11: Construction Progress – End Dec 2013
CONSTRUCTION PROGRESS – END DEC 2013 120% PROJECT BASELINE SCHEDULE CREATED ON JULY 2012 100% OVERALL PROGRESS ACTUAL = 74.02 % PLAN = 75.09 % 80% Plan Monthly Progress Actual Monthly Progress 60% Plan Total Progess Actual Total Progress 40% 20% 0% 2012 2013 2014 May12 May13 May14 Mar13 Mar14 Nov12
Slide 12: Capital Expenditure – End Dec 2013
CAPITAL EXPENDITURE – END DEC 2013 SENTINEL PROJECT COST REPORT Budget Approved Current Incurred AREA / COST $M Committed Forecast Estimate Changes Budget to Date TOTAL $1,725.0 $159.8 $1,884.8 $1,706.9 $1,884.8 $1,213.3 Schedule: Train 1 = commissioning Q2 2014 Train 2 = commissioning Q4 2014, de
Slide 13: Employment – End Dec 2013
EMPLOYMENT – END DEC 2013 Department Local Expat Filipinos / Indonesians TOTAL Infrastructure 524 11 105 640 FQML Plant 688 26 412 / 144 1270 Operations and Support 526 30 - 556 FQMO Roads 670 15 - 685 Subcontractors 1456 115 - 1571 Overall Manpower 3,864 197 661 4,722 Percentage (%) 82% 4% 14% 100%
Slide 14: 3 x Rope Shovels - 1,350t, 57m3 Bucket
3 X ROPE SHOVELS - 1,350T, 57M3 BUCKET January 2014 14
Slide 15: 3 x PCX5500 Loaders - 205t, 21m3 Bucket
3 X PCX5500 LOADERS - 205T, 21M3 BUCKET January 2014 15
Slide 16: 36 x Trucks – 21 x 960E + 15 x 860E
36 X TRUCKS – 21 X 960E + 15 X 860E January 2014 16
Slide 17: In Pit Crush – 3 x (ThyssenKrupp) 63-89 20Mtpa
IN PIT CRUSH – 3 X (THYSSENKRUPP) 63-89 20MTPA January 2014 17
Slide 18: 100MW Milling – 2 x 40' SAG + 2 x 28' Ball
100MW MILLING – 2 X 40’SAG + 2 X 28’BALL January 2014 18
Slide 19: Progress Photos – Plant Area
PROGRESS PHOTOS – PLANT AREA MILL BUILDINGS 31-DEC-2013 FLOTATION AREA 31-DEC-2013 STOCKPILE VAULT 20-JAN-2014 CONVEYOR LINE 21-JAN-2014 January 2014
Slide 20: Progress Photos – Plant Area
PROGRESS PHOTOS – PLANT AREA CABLE PULLING 31-DEC-2013 ROUGHER FLOTATION 31-DEC-2013 CLEANER FLOTATION 2-JAN-2014 TAILS THICKENER 31-DEC-2013 January 2014
Slide 21: Progress Photos – Plant Area
PROGRESS PHOTOS – PLANT AREA REAGENTS, DEPRESSANTS AREA & CONCENTRATE STORAGE BUILDING 31-DEC-2013 PIPERACK LINE 31-DEC-2013 CRUSHER ASSEMBLY YARD 31-DEC-2013 CAT EQUIPMENT ASSEMBLY YARD 31-DEC-2013 January 2014
Slide 22: January 2014
January 2014 &
Slide 23: Progress Photos – Mine Area
PROGRESS PHOTOS – MINE AREA MSA, RUBBER TYRE WORKSHOP 31-DEC-2013 MSA, KOMATSU ASSEMBLY YARD 31-DEC-2013 MINING EQUIPMENT AT BOX CUT 2-JAN-2014 NORTHWEST BOXCUT AERIAL PHOTO 01-DEC-2013 January 2014 23
Slide 24: Progress Photos – Infrastructure
PROGRESS PHOTOS – INFRASTRUCTURE CHISOLA DAM INLET 20-JAN-2014 CHISOLA DAM, OUTLET PIPE & TUNNEL 2-JAN-2014 RAW WATER LINE 2-JAN-2014 33KV SITE POWER 02-SEPT-2013 January 2014 24
Slide 25: Progress Photos – ZESCO Substation
PROGRESS PHOTOS – ZESCO SUBSTATION ABB SWITCHYARD, EAST GANTRY FOOTINGS 01-NOV- ABB SWITCHYARD, CONTROL BUILDING FDN 01-NOV- 2013 2013 POWERLINE CLEARING & EARTHWORKS ABB SWITCHYARD 30-DEC-2013 20-DEC-2013 January 2014
Slide 26: Power Line Development Connecting the West of Zambia
POWER LINE DEVELOPMENT CONNECTING THE WEST OF ZAMBIA January 2014 26
Slide 27: Upgrades to ZESCO Network
UPGRADES TO ZESCO NETWORK January 2014 27
Slide 28: ZESCO Power Infrastructure Project
ZESCO POWER INFRASTRUCTURE PROJECT First Quantum commitments to ZESCO grid upgrades: First Quantum to provide upfront finance : 68km Lumwana – Kalumbila 330kV transmission line + substations; 400km Kalumbila – Mumbwa 330kV transmission line; 145km Mumbwa – Lusaka West 330kV transmission line
Slide 29: ZESCO Grid and Regional Transmission Line Interconnectors
ZESCO GRID 33kV to 330kV AND / REGIONAL TRANSMISSION LINE 4 INTERCONNECTORS a, et, 2 ‘KOLWEZ! D R CONGO LILONGWE > ZIMBABWE
Slide 30: Town Development Upfront Investment in the Community
TOWN DEVELOPMENT UPFRONT INVESTMENT IN THE COMMUNITY January 2014 30
Slide 31: About the New Town
ABOUT THE NEW TOWN Located in the Solwezi District of Northwestern Province, Zambia : Approximately 150km from Solwezi on the T5 main road to Mwinilunga At the heart of the ‘New Copperbelt’ Proper planning and services for 10,000 homes Town plan approved by Solwezi Council on 7 March 2012 EI
Slide 32: Town – Potential Scope
TOWN – POTENTIAL SCOPE Potential employment Total Direct – KML Operations 2,000 Indirect – Mine Contractors 1,000 Multiplier Jobs 6,000 – 8,000 TOTAL Approximately 10,000 Potential housing Total KML committed – Phase 1 690 KML likely – Phase 2 900 Third parties 7,000 – 9,000 TOTAL Up to 10,000 At th
Slide 33: Expertly Designed & Fully Serviced Town
EXPERTLY DESIGNED & FULLY SERVICED TOWN Town design by Zambian and international firms. Water, sewerage and waste 11 Jul 2012 – MOU signed with NWW Weekly waste collection Metered electrical reticulation 31 Jan 2013 – Contracts signed with NWEC 28 Nov 2012 – ZESCO agreement signed Roads: F
Slide 34: MFEZ to Encourage Local Businesses
MFEZ TO ENCOURAGE LOCAL BUSINESSES Application to ZDA for MFEZ status: Substantial tax incentives to businesses setting up in the area: 1. 0% tax for first 5 years, next 3 years at 50%, next 2 years at 75%; 2. 0% tax on dividends for a period of 5 years; 3. 0% import duties on raw materials, capit
Slide 35: Zambian Investment and Job Opportunities
ZAMBIAN INVESTMENT AND JOB OPPORTUNITIES Business opportunities for: Retail; Hospitality and tourism; Financial services; Construction; Mine services; Manufacturing and light industrial; Warehousing and logistics; Agricultural services; Forestry; and Other. Accommodation : Purc
Slide 36: Worker Housing – Resettlement and Livelihood Program
WORKER HOUSING – FOR HOME OWNERSHIP RESETTLEMENT AND LIVELIHOOD PROGRAM January 2014 36
Slide 37: Progress Photos – Senior Housing
PROGRESS PHOTOS – SENIOR HOUSING SPORTS FACILITY 04-NOV-2013 SENIOR HOUSING - SINGLES 31-MAR-2013 SENIOR HOUSING AREA 28-FEB-2013 TRIDENT PREPARATORY SCHOOL 05-NOV-2013 January 2014
Slide 38: Progress Photos – Affordable Housing
PROGRESS PHOTOS – AFFORDABLE HOUSING AFFORDABLE HOUSING LAYOUT TEACHER’S HOME 3-JAN-2014 TRUST SCHOOL 05-NOV-2013 COMPLETED 4-BEDROOM HOUSE 3-JAN-2014 January 2014 38
Slide 39: Block Plant – Local Fabrication
BLOCK PLANT – LOCAL FABRICATION January 2014 39 39
Slide 40: Community Projects – Underway
COMMUNITY PROJECTS – UNDERWAY January 2014 40
Slide 41: Progress Photos – Resettlement
PROGRESS PHOTOS – RESETTLEMENT RESETTLEMENT HOUSES RESETTLEMENT HOUSES RESETTLEMENT SCHOOL RESETTLEMENT CLINIC January 2014 41
Slide 42: Progress Photos – CSR
PROGRESS PHOTOS – CSR MALARIA SCREENING 01-DEC-2014 MALARIA SCREENING 01-DEC-2014 LIVELIHOOD SUPPORT 01-DEC-2014 LIVELIHOOD SUPPORT MOSQUITO SPRAYING January 2014 42
First Quantum Minerals — Investor Presentation (January 2014) on 6ix