Lydian International — Scotiabank Mining Conference 2016
16 slides from Lydian International's conference presentation, December 2016
Slide 1: Scotiabank Mining Conference
Scotiabank Mining Conference December 2016 Lydianinternational.co.uk | TSX:LYD 1
Slide 2: Cautionary Statements
Cautionary Statements Forward Looking Information & Estimates of Reserves and Resources Certain information contained in this presentation, including any information relating to Amulsar's expected future performance, is "forward looking". All statements in this presentation, other than statements of
Slide 3: Corporate Summary – Financing Structure Established
Lydian International Corporate Summary – Financing Structure Established Ordinary Shares: LYD Trading Symbols Publicly-trading Warrants LYD.WT Ordinary Shares 699 million Share Capital Publicly-trading Warrants 99 million Unlisted Warrants 5 million Market Capitalization Recent price of C$0.31 C$215
Slide 4: Amulsar Gold Project – Armenia
Amulsar Gold Project – Armenia Compelling Asset – Construction Re-rate Opportunity Producer Upside • 100%-owned, now among a select group of Further Upside – 57.7% high-quality gold development projects 1.2x Implied Upside – 84.6% • Large scale operation will be Armenia’s 0.8x largest gold mine P /
Slide 5: Amulsar Gold Project – Location
Amulsar Gold Project – Location Easy Access & In-place Regional Infrastructure • 170 km southeast of Yerevan • Located on Armenia’s primary infrastructure corridor • Paved access to site • Local workforce • High-voltage power on site • Internet connection in place • Telecomm available • Water on sit
Slide 6: Amulsar Operating Scale and Economics
Amulsar Operating Scale and Economics Amulsar Mine Profile Supports Powerful Economics Operating Profile (Source: Q4 2015 – NI 43-101) Initial Mine Life (Years) 10.0 Annual Tonnes Processed 9,700,000 Waste : Ore Ratio 2.4 Gold Grade (g/t) 0.78 Gold Recovery 87.2% Annual Gold Produced (oz) 211,000 Al
Slide 7: Large Scale Oxide Deposit
Large Scale Oxide Deposit Initial 10-Year Mine Plan from 2.4 Million Oz P+P Reserves • Over 100 Mt inferred resource outside initial 10-year mine plan • Pit design optimized at $912/oz gold; economic evaluation at $1,150/oz gold • Excellent operating profile • Waste : Ore ratio at 2.4 – including 26
Slide 8: Growth Potential
Growth Potential Upside within Inferred Resource and at Depth • Resource conversion • Within current pits: 26 million tonnes at 0.57 g/t inferred • Optimizing to include inferred adds: 40 million tonnes at 0.73 g/t; mostly limited by drilling density • Open potential below pit limits (below East-Wes
Slide 9: Amulsar Construction
Amulsar Construction Latest Update • Engineering progress now +60% complete • Basic engineering near completion • Detail engineering advancing overall and complete on – • Heap leach facility • Main haul road • Other near-term project elements • Key equipment and facilities advancing to detail engine
Slide 10: Amulsar Construction (continued)
Amulsar Construction Latest Update (continued) • RD-3 – Mine Haul Road Top Soil Removal at the Camp Platform • Pioneer road advancing • Evaluating optimization opportunity • Connects mine pits to the crusher location • RD-5 – Primary access from Gndevaz • Upgrade in process, for access to – • Portio
Slide 11: Near and Mid-term Catalysts
Near and Mid-term Catalysts Focus on Construction 2016 2017 2018 • Construction start with • Project construction • Ore to pad mass earthworks Heap leach facility • • Plant commissioning • Land acquisition & • Haul roads • First gold pour conversion • Crushing/screening • Ramp-up of gold • Project t
Slide 12: Comparable Development Stage Companies
Comparable Development Stage Companies Targeting to Re-Rate Central to Construction Strategy Further Upside – 14.6% 1.2x Implied Upside – 154.0% 1.0x 0.8x 0.7x 0.6x 0.6x 0.6x P / NAV 0.4x 0.4x 0.4x Senior Producer TMAC Pretium Lundin Gold Pershing Gold Atlantic Gold Victoria Belo Sun Lydian Producer
Slide 13: Thank You
Thank You Lydianinternational.co.uk | TSX:LYD
Slide 14: Mineral Reserves & Mineral Resources
Mineral Reserves & Mineral Resources Notes Notes to Mineral Reserves: 1. The pit design was based on an optimization shell generated on gold only at a gold price of $912/oz. 2. The economic evaluations were based on a gold price of $1,150/oz and a silver price of $16.00/oz. 3. A diluted gold cut-off
Slide 15: Management
Management Experienced, Committed to Construction/Operations Excellence Howard Stevenson • 25 years global mining experience • Alacer Gold President & COO (President & CEO) • Meridian & Gold Fields Douglas Tobler • 35 years finance, accounting and mining experience • Alacer Gold CFO (CFO) • PwC, plu
Slide 16: Board of Directors
Board of Directors Development Oriented – Independent, Diverse Experience Gordon Wylie • 32 yrs mining experience • AngloGold-Ashanti Global (Non-Executive Director & Chair) • Exploration manager Howard Stevenson • 25 yrs global mining experience • Alacer Gold President & COO (President & CEO) • Mer