Slide 1: Progress Update GC Project, Guangdong Province, China
Progress Update GC Project, Guangdong Province, China As of December 31, 2011
Slide 2: Completed 604 metres of Stage 1 Ramp since mid-August 2011
Completed 604 metres of Stage 1 Ramp since mid-August 2011 1 1
Slide 3: 6-metre Diameter Main Shaft Opening: Preparation for Cement Pouring
6-metre Diameter Main Shaft Opening: Preparation for Cement Pouring (Expected depth of 620 m) 2 2
Slide 4: Ventilation Shaft Opening: Preparation for Cement Pouring
Ventilation Shaft Opening: Preparation for Cement Pouring 3 3
Slide 5: Ore Bin Foundation: Preparation for Cement Pouring
Ore Bin Foundation: Preparation for Cement Pouring 4 4
Slide 6: Water Recycling Tanks Constructed for Mill
Water Recycling Tanks Constructed for Mill 5 5
Slide 7: Second Floor of Mine Office: Preparation for Cement Pouring
Second Floor of Mine Office: Preparation for Cement Pouring 6 6
Slide 8: Completed Two Floors of Mine Office Building
Completed Two Floors of Mine Office Building 7 7
Slide 9: Construction of Second Floor of Staff Accommodation Building
Construction of Second Floor of Staff Accommodation Building 8 8
Slide 10: GC Development Project: Progress towards production
GC Development Project: Progress towards production Construction of 1,600 tpd mine and mill underway 1,600 tpd floatation mill expected to be completed by July 2012 ($17 MM) Ying Mining District FY2012 Mine & Mill Development: $22.5 MM China 30 year mining permit has been obtained XBG + XHP