Inter Pipeline Ltd

Inter Pipeline — Investor Presentation (March 2020)

42 slides from Inter Pipeline's investor presentation, March 2020

  1. Slide 1: Investor Presentation March 2020

    INVESTOR { PRESENTATION — a TSX | IPL MARCH 2020 ® inter pipeline

  2. Slide 2: Forward-Looking Information

    FORWARD-LOOKING INFORMATION Certain information contained herein may constitute forward-looking statements that involve known and unknown risks, assumptions, uncertainties and other factors. Some of the forward-looking statements may be identified by words like ‘‘anticipates’’, ‘‘estimates’’, ‘‘expe

  3. Slide 3: Investment Highlights

    INVESTMENT HIGHLIGHTS ▪ Top tier energy infrastructure business that has significant growth potential ▪ Progressing $3.7 billion in active projects today ▪ Demonstrated track record of delivering large-scale projects on time and on budget ▪ Reliable operations, with stable cash flow and a sustainabl

  4. Slide 4: World-Scale Energy Infrastructure

    WORLD-SCALE ENERGY INFRASTRUCTURE Oil Sands NGL Conventional Bulk Liquid Transportation Processing Oil Pipelines Storage 2019 Annual EBITDA ($1,051 million) 55% 20% 15% 10% 2.3 million b/d Over 240,000 b/d 3,900 km pipeline 37 million barrels of contracted of production network in of storage capacit

  5. Slide 5: Value Creation

    VALUE CREATION ▪ $182 million CAPL expansion phases one and two both expected to be in service by mid-2020 ▪ Completed $110 million oil sands connection to Canadian Natural’s Kirby North project ▪ Constructing Canada’s first integrated propane dehydrogenation and polypropylene complex for $3.5 billi

  6. Slide 6: Business Strategy

    BUSINESS STRATEGY OWN AND OPERATE HIGH-QUALITY ENERGY INFRASTRUCTURE ASSETS EBITDA from ▪ Well-contracted to provide cash flow stability ▪ Industry-leading project execution, with exceptional 84% cost-of-service and fee-based contracts* EH&S performance Payout ratio MAINTAIN STRONG FINANCIAL POSITIO

  7. Slide 7: EBITDA by Contract Type

    EBITDA BY CONTRACT TYPE Oil Sands Transportation NGL Processing Cost-of-Service 67% ($579 million) ($215 million) 100% 9% 25% Fee-Based 17% 66% Commodity-Based 13% Conventional Oil Pipelines Bulk Liquid Storage ($153 million) ($104 million) Product Margin 3% 21% 22% 29% Total EBITDA: $1,051 million

  8. Slide 8: Dividend Growth

    DIVIDEND GROWTH Dividends per share 5.3% CAGR2014-2019 $1.69 $1.71 $1.63 $1.57 $1.49 $1.32 $1.18 $1.06 $0.97 $0.91 $0.85 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 7.3% CAGR 2009-2019 7

  9. Slide 9: Dividend Stability

    DIVIDEND STABILITY $ Million $1,200 $1,000 $800 $600 $400 $200 $0 2014 2014 2015 2015 2016 2016 2017 2017 2018 2018 2019 2019 FFO Dividend FFO Dividend FFO Dividend FFO Dividend FFO Dividend FFO Dividend Cost-of-Service Fee-Based Commodity-Based Product Margin Dividends supported by cost-of-service

  10. Slide 10: Growth Projects

    “= GROWTH PROJECTS TSX |

  11. Slide 11: Growth Profile

    GROWTH PROFILE Target Est. Capital Cost Active Projects Segment In-Service Date ($ Million) Heartland Petrochemical Complex NGL Late-2021 $3,500 CAPL Expansion Phase 1 (Stettler) Conventional Mid-2020* $82 CAPL Expansion Phase 2 (Viking Connector) Conventional Q2-2020 $100 Total ~$3,700 Announcement

  12. Slide 12: Heartland Petrochemical Complex (HPC)

    HEARTLAND PETROCHEMICAL COMPLEX (HPC) ▪ Transformational growth opportunity ✓ Capacity to consume ~22,000 b/d of propane to produce ~525 kilotonnes per annum (KTA) of polypropylene (PP) ✓ Expected to add approximately $450-500 million of long-term average annual EBITDA ✓ Target 70-85% of processing

  13. Slide 13: Canadian Propane Supply Advantage

    CANADIAN PROPANE SUPPLY ADVANTAGE 000’s b/d ▪ Canadian propane market to remain 300 oversupplied over the long-term ✓ More than 100,000 b/d of expected 250 oversupply that will have to be exported ✓ Forecast petrochemical demand and potential international LPG exports will not 200 balance the Canadi

  14. Slide 14: Polypropylene Is a Premium Product

    POLYPROPYLENE IS A PREMIUM PRODUCT USD per Tonne $2,500 North American PP to Edmonton Propane Price Differential $2,000 $1,500 $1,000 Spread ~$1,400 USD per Tonne $500 $0 2013 2014 2015 2016 2017 2018 2019 IHS General Purpose Homopolymer PP Edmonton Propane* Average PP to Propane Spread** Converting

  15. Slide 15: Polypropylene Demand

    POLYPROPYLENE DEMAND North American PP Demand ▪ PP is the world’s single largest polymer ✓ Accounts for ~30% of global demand Canada 6% ✓ Used in many common goods such as Mexico consumer packaging, automobile parts, 18% medical equipment, currency and textiles ▪ Types of PP include homopolymer as ~

  16. Slide 16: Propane Producer Value Proposition

    PROPANE PRODUCER VALUE PROPOSITION ▪ Benefits for propane producers: ✓ Offers a higher realized propane price relative to selling in the local, oversupplied market ✓ Creates ratable demand for propane ✓ Adds diversification to propane sales portfolio ▪ Commercial framework: ✓ Producer delivers propa

  17. Slide 17: Indicative Propane Producer Uplift

    INDICATIVE PROPANE PRODUCER UPLIFT Propane Value Increase Edmonton Propane Price 500% $1.25 415% 400% $1.00 300% $0.75 200% 166% $0.50 133% 100% 65% 75% $0.25 29% 0% $0.00 2014* 2015 2016 2017 2018 2019 Heartland Polypropylene Edmonton Propane (USD per USG) Propane producers would have realized a 10

  18. Slide 18: PP Buyer Value Proposition

    PP BUYER VALUE PROPOSITION ▪ Benefits for PP buyers: ✓ Offers lower realized PP feedstock price relative to buying on the spot market ✓ Provides supply diversification ✓ Allows vertical integration without capital outlay ▪ Commercial framework: ✓ Counterparty pays a fixed capital fee as well as a pr

  19. Slide 19: Indicative PP Buyer Savings

    INDICATIVE PP BUYER SAVINGS Polypropylene Savings Edmonton Propane Price 30% $1.25 27% 26% 24% 22% $1.00 18% 18% $0.75 14% 12% 10% $0.50 6% $0.25 0% $0.00 2014* 2015 2016 2017 2018 2019 Heartland Polypropylene Edmonton Propane (USD per USG) PP buyers would have saved 20%* through the Heartland Compl

  20. Slide 20: Project Status

    PROJECT STATUS ▪ Approximately 65% of the $3.5 billion project cost de-risked ✓ Based on lump-sum contracts, firm purchase orders, and substantially completed design and construction activities ▪ Well-advanced PDH project ✓ Over $500 million lump-sum/unit rate contract for construction awarded to Ki

  21. Slide 21: Operational Expertise & Readiness

    OPERATIONAL EXPERTISE & READINESS ▪ Extensive NGL operating experience ✓ Full operational responsibility for the Cochrane straddle plant, as well as the Pioneer 1 & 2 offgas plants ✓ Management oversight of the Redwater Olefinic Fractionator, as well as the Empress II & V straddle plants ▪ De-riskin

  22. Slide 22: Capital Profile & Financing Strategy

    CAPITAL PROFILE & FINANCING STRATEGY $ Million Heartland Complex financing sources Total project cost of ~$3.5 billion ▪ Potential proceeds from the sale of Inter ~$2,200 Terminals ▪ Capacity available under existing $1.5 billion committed credit facility ✓ Over $1.4 billion available as at Q4 2019

  23. Slide 23: Central Alberta Pipeline System Expansion

    CENTRAL ALBERTA PIPELINE SYSTEM EXPANSION EDMONTON ▪ Phase 1: Stettler Station expansion ✓ Product batching and 10,000 b/d of additional Phase 4: Mainline truck unloading capacity completed; two Expansion 130,000 barrel tanks under construction Phase 1: HARDISTY Stettler Station ✓ Forecast annual EB

  24. Slide 24: Oil Sands Growth Opportunities

    OIL SANDS GROWTH OPPORTUNITIES ▪ Identified ~$2.8 billion of long-term growth opportunities KEARL FRONTIER DEBOTTLENECK SUNRISE PHASE 2 ✓ Over 2.3 million b/d of available HORIZON & DEBOTTLENECK ASPEN PHASE 1 & 2 capacity that can be marketed across MACKAY RIVER CLARKE CREEK all three systems ALGAR

  25. Slide 25: NGL Processing Opportunities

    NGL PROCESSING OPPORTUNITIES ▪ Cochrane expansion ✓ Potential to add 400 mmcf/d of processing capacity, increasing plant total to 2.9 bcf/d ✓ Currently operating near capacity and bypassing natural gas ▪ Acrylic acid & derivatives facility ✓ Opportunity to develop Canada’s first acrylic acid facilit

  26. Slide 26: Financial Overview

    FINANCIAL OVERVIEW Ne TSX | IPL

  27. Slide 27: Financial Objectives

    FINANCIAL OBJECTIVES 2019 Post-HPC Target Dividends underpinned by cost-of-service Greater than Greater than Dividends and fee-based cash flow 100% 100% Less than Payout ratio, after sustaining capital 88% 80% Greater than Leverage FFO to recourse debt 16% 23% Sr. recourse debt to total capitalizati

  28. Slide 28: Credit Strength

    CREDIT STRENGTH Oil Sands NGL Conventional Bulk Liquid Transportation Processing Oil Pipelines Storage ($813 million) ($711 million) ($717 million) ($294 million) 97% 77% 75% 44% 12 customers ~25 customers 100+ producers ~130 customers Remaining contract Remaining contract Typical exposure of Remain

  29. Slide 29: Capital Structure

    CAPITAL STRUCTURE $ Billion ▪ Target capital structure of 50% to 55% $8 sr. recourse debt to total capitalization ✓ Credit facility covenant of 65% $6 ▪ $1.4 billion of consolidated debt is non- recourse to IPL ✓ Corridor pipeline system has its own capital $4 structure and credit ratings ✓ Flow thr

  30. Slide 30: EBITDA by Business Segment

    EBITDA BY BUSINESS SEGMENT $ Million $1,250 $1,000 $750 $500 $250 $0 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Oil Sands Transportation Conventional Oil Pipelines Bulk Liquid Storage NGL Processing 29

  31. Slide 31: World-Scale Energy Infrastructure

    > | =. WORLD-SCALE ENERGY INFRASTRUCTURE Ne Tx [PL ——_— .

  32. Slide 32: Oil Sands Transportation

    OIL SANDS TRANSPORTATION ▪ Three major pipeline systems ✓ Contracted capacity of ~2.3 million b/d; IMPERIAL KEARL ultimate capacity of ~4.6 million b/d AOSP HUSKY SUNRISE ✓ Over 3,300 km of pipeline, with 3.8 Polaris Pipeline Cold Lake Pipeline JACOS / NEXEN AOC HANGINGSTONE million barrels of stora

  33. Slide 33: NGL Processing

    NGL PROCESSING ▪ Large-scale NGL infrastructure Pioneer I & II ✓ Three straddle plants strategically located on the NGTL System ✓ Two offgas plants, Pioneer I & II, that Boreal Pipeline Offgas Extraction have dedicated supply agreements Facility Straddle Plant Redwater ✓ Ethane-plus fractionation fa

  34. Slide 34: Conventional Oil Pipelines

    CONVENTIONAL OIL PIPELINES ▪ Three pipeline systems ✓ 3,900 km of pipeline and over 1.3 million barrels of storage capacity Bow River Pipeline Central Alberta ✓ Transported ~190,000 b/d in Q4 2019 Pipeline Mid-Saskatchewan Pipeline ▪ Cost-of-service, fee-based and Viking Formation East Duvernay Form

  35. Slide 35: Bulk Liquid Storage

    BULK LIQUID STORAGE Terminal Location ▪ 23 petroleum and petrochemical storage terminals in Europe ✓ Operations in six different countries SWEDEN ✓ Approximately 37 million barrels of DENMARK total storage capacity ✓ Generally, serve the petroleum, IRELAND chemical and biofuel markets ENGLAND NETHER

  36. Slide 36: Environment, Social and Governance

    ENVIRONMENT, SOCIAL AND GOVERNANCE > TS PL

  37. Slide 37: Governance

    GOVERNANCE ▪ Commitment to sustainable practices and operational excellence ✓ Issued second sustainability report in accordance with SASB, GRI and TCFD frameworks ✓ Sustainability Steering Committee comprised of CEO and senior management ▪ Strong corporate governance ✓ Board of Directors have 30% fe

  38. Slide 38: Environment

    ENVIRONMENT ▪ Offgas facilities process waste gas from oil sands upgraders ✓ Extracting a valuable liquids stream and removing ~336,000 tonnes of GHG per year ▪ HPC-produced PP is expected to have a low GHG emissions profile ✓ PP is a fully recyclable plastic ✓ GHG footprint ~65% lower than the glob

  39. Slide 39: Social

    SOCIAL $ Million Hours (000’s) ▪ Meaningful engagement with $5 5 community members and indigenous 3,800 hours volunteered in 2019 peoples $4.0 $4 4 ✓ Fort McKay First Nation Joint Venture $3 $2.8 $3.0 3 ▪ Mental health recognized as part of $2.3 safety culture $2 2 ✓ Industry leader providing awaren

  40. Slide 40: Looking Forward

    LOOKING FORWARD ▪ Over $4.2 billion of identified future potential growth opportunities ▪ Management track record of increasing shareholder value ▪ Committed to maintaining a strong balance sheet and investment grade credit rating ▪ Well-positioned to sustain dividends, with upside growth potential

  41. Slide 41: HPC Site

    HPC SITE Site photo taken Q4 2019 40

  42. Slide 42: Contact Information

    CONTACT INFORMATION INTER PIPELINE LTD. SUITE 3200, 215 – 2ND STREET SW CALGARY, AB T2P 1M4 PHONE: 1 (866) 716 7473 PHONE: 1 (403) 290 6000 WEB: INTERPIPELINE.COM INVESTORRELATIONS@INTERPIPELINE.COM 41 41

Inter Pipeline — Investor Presentation (March 2020) on 6ix