Orion Minerals Limited · ASX:ORN

Orion Minerals — Africa Down Under Conference 2017

28 slides from Orion Minerals's conference presentation, Sep 6, 2017

  1. Slide 1: A rare consolidation opportunity in a proven minerals belt

    A rare consolidation opportunity For personal use only in a proven minerals belt ASX Code: ORN Africa Down Under Conference 6-8 Sep 2017 “Expediting development at Prieska while seeking to unlock the minerals potential of the land package through advanced exploration" 1

  2. Slide 2: Disclaimer and Forward-Looking Statements

    Disclaimer and Forward-Looking Statements  Certain statements contained in this presentation, including information as to the future financial or operating performance of Orion Minerals NL (Orion) and its projects, are forward-looking statements. Such forward-looking statements: For personal use on

  3. Slide 3: Orion: Corporate Summary

    Orion: Corporate Summary For personal use only Capital Structure Summary Board Shares on Issue 990M Denis Waddell Non Executive Chairman (chartered accountant) Options on Issue 217M Errol Smart CEO, Managing Director (geologist) Market Capitalisation (at 2.4cps) $24M Bill Oliver Non Executive Direct

  4. Slide 4: Orion – Secondary Listing on JSE

    Orion – Secondary Listing on JSE  Orion will seek a secondary listing on JSE September 2017 For personal use only ─ Facilitating Increased Equity Participation by South Africans  JSE KEY FACTS (as at June 2017) (source JSE) ─ Market capitalisation: R13.64 trillion (approximately A$1.4 trillion) ─

  5. Slide 5: Major consolidation play in a proven mineralised district

    Major consolidation play in a proven mineralised district For personal use only  Orion acted at bottom of cycle in 2015 and secured a large consolidated land package (1,790 km2) ─ Secured a potential company making project in Prieska ─ First time this highly prospective region has been consolidated

  6. Slide 6: Prieska ownership structure

    Prieska ownership structure For personal use only  Orion acquired option to purchase Agama Exploration & Mining in July 2015 Prieska BEE compliant ownership structure ─ Extensive DD process completion, including Orion Minerals NL technical, regulatory and economic work streams ─ Transaction conside

  7. Slide 7: Prieska – SA mining success story

    Prieska – SA mining success story Prieska in operation mode For personal use only  Operated from 1971-1991, employed 4,000 people by Anglovaal ─ Infrastructure rich with all key services remaining on site  Milled 46.8mt producing >430kt copper and >1mt zinc in concentrate  Post May 1987, no more

  8. Slide 8: Extended history of metallurgical success

    Extended history of metallurgical success Consistent concentrate grades and recoveries despite change in feed1 For personal use only 60 100  Proven metallurgical process flowsheet at 50 90 80 Metal recovery (%) operational scale to handle variable ore Concentrate grades (%) 40 70 feed 60 30 50  Mi

  9. Slide 9: Systematic and low risk path to advancing Prieska

    Systematic and low risk path to advancing Prieska Prieska target mineralisation and existing mine infrastructure For personal use only  BFS scheduled for completion Q4 2018 ─ DRA appointed as lead BFS consultants  Key BFS technical project parameters include ─ Construction of 1.2mtpa throughput fl

  10. Slide 10: Significant infrastructure footprint

    Significant infrastructure footprint Decline portal viewed from Prieska headframe For personal use only  Sealed access roads to project site  48km via bitumen road to existing rail siding  75MW operational solar power plant – 4 HV regional lines linked to national electricity grid  800km rail li

  11. Slide 11: Re-entry to underground development commenced

    Re-entry to underground development commenced For personal use only Mine infrastructure, development and Deep Sulphide target  Regulatory permits received and mine decline and shaft re-entry commenced in April 2017 – Initial findings indicate ground conditions and infrastructure in good order – Inc

  12. Slide 12: Shaft & Underground Roadway Conditions Inspected by Expert Safety Inspectors & Engineers

    Shaft & Underground Roadway Conditions Inspected by Expert Safety Inspectors & Engineers (Q2 2017) For personal use only 12

  13. Slide 13: Deep sulphide target drilling progressing rapidly

    Deep sulphide target drilling progressing rapidly Long section with current drilling and historical development For personal use only  Drilling underway with 14 rigs on site to confirm statistical validity of extensive historical drilling database, infill and extend delineated mineralisation ─ Prev

  14. Slide 14: First Deep Holes Intersect High Grade Massive Sulphides

    First Deep Holes Intersect High Grade Massive Sulphides Deep sulphide drilling For personal use only  First six drill holes in Deep Sulphide target have intersected massive sulphides ─ Provides proof of concept and validation of historical database  Hole OCOD048 intersected 22.45m at 5.33% Zn and

  15. Slide 15: Deep Sulphide - Resource Drill Out Underway

    Deep Sulphide - Resource Drill Out Underway Plan view of Deep Sulphide drilling program highlighting completed holes For personal use only refer ASX release 6 September 2017 15

  16. Slide 16: +105 Level Target - a high grade open pit opportunity

    +105 Level Target - a high grade open pit opportunity Interpreted section of +105 Level Target For personal use only  +105 Level Target is up-dip extension unmined mineralisation JORC resource estimate targeted for completion in late 2017  Step out drilling confirms continuity and tenor of mineral

  17. Slide 17: +105 Level Target - a high grade open pit opportunity

    +105 Level Target - a high grade open pit opportunity For personal use only 17

  18. Slide 18: Ground conditions support mining strategy

    Ground conditions support mining strategy For personal use only  Geotechnical solution to mining challenge Draw point on 105 mining level developed to unlock potential of this important target ─ Drilling techniques have allowed for successful testing of areas effected by sinkholes and mining subsid

  19. Slide 19: +105 Level Target drilling plan

    +105 Level Target drilling plan For personal use only refer ASX release 25 May 2017 19

  20. Slide 20: Generating significant momentum on the ground

    Generating significant momentum on the ground For personal use only  Orion Board approval to commence BFS in July 2017 with target completion in Q4 2018 – +105 Level Target, maiden JORC compliant Mineral Resource expected Q4 2017 – Deep Sulphide Target, maiden JORC compliant Mineral Resource expect

  21. Slide 21: Active CSR - Developing Social and Labour Plan

    Active CSR - Developing Social and Labour Plan • Orion is a catalyst for socio-economic development. For personal use only We strive for :- * Sustainability * Focus * Entrepreneurship *Impact Public participation meeting in Siyathemba - Prieska 21

  22. Slide 22: The regional potential of the Northern Cape district

    The regional potential of the Northern Cape district For personal use only  Established mining region without the challenges of gold, coal and platinum industries ─ Supportive and engaged local stakeholders Southern African Zinc deposits  Presence of leading global mining houses and robust institu

  23. Slide 23: Areachap - a highly prospective base metals belt

    Areachap - a highly prospective base metals belt Three superimposed geological events produce For personal use only exceptional exploration potential  The Areachap terrain is within a tectonic/mobile belt on western margin of Kaapvaal Craton and has subsequently been intensely altered & tectonised

  24. Slide 24: Strategy to unlock regional potential of the belt

    Strategy to unlock regional potential of the belt Marydale IP Survey For personal use only  Value of modern exploration techniques have already been demonstrated by recent geophysical surveys  Majority of historical surveys 1980’s  Techniques have been refined or superseded  Modern day geophysic

  25. Slide 25: Zinc: Raw materials constraints drive positive outlook

    Zinc: Raw materials constraints drive positive outlook Declining zinc stock and pricing impacts For personal use only  Key mine closures and reductions over the past year starting to bite, 2016 mine output down 5.2% – Discretionary supply cuts from Glencore (500ktpa) and Nyrstar (100ktpa) – Comment

  26. Slide 26: Copper: Growing demand with supply challenges

    Copper: Growing demand with supply challenges For personal use only  Chilean mine supply continues to struggle – Grade declines and labour issues at major mines – Power and water challenges increase cost pressures for future Chilean production  Large supply projects carry technical and/or geo-poli

  27. Slide 27: Competent Persons Statement

    Competent Persons Statement • The information in this report that relates to Exploration Targets at the Prieska Zinc Copper project complies with the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code) and is based on information

  28. Slide 28: Orion Minerals NL contact information

    Orion Minerals NL contact information: For personal use only Phone: +61 (0)3 8080 7170 Email: info@orionminerals.com.au Website: www.orionminerals.com.au 28