  1. Slide 1: Mardie Salt & Potash Project: $360M Capital Raising to Drive Development

    Mardie Salt & Potash Project Pilbara Western Australia $360M Capital Raising to Drive Development 18 November 2021 ASX:BCI www.bciminerals.com.au

  2. Slide 2: Important Notices

    Important Notices Not for release to US wire services or distribution in the United States. The following notice and disclaimer apply to this presentation (Presentation) and you are therefore advised to read this carefully before reading or making any other use of this Presentation or any informatio

  3. Slide 3: Important Notices (continued)

    Important Notices (continued) Past performance Past performance metrics and figures (including past share price performance of BCI), as well as pro forma financial information, included in this Presentation are given for illustrative purposes only and should not be relied upon as (and is not) an ind

  4. Slide 4: Important Notices (continued)

    Important Notices (continued) Risks An investment in BCI is subject to investment and other known and unknown risks, some of which are beyond the control of BCI. For further information please refer to slides 48-53 (inclusive) Disclaimer Canaccord Genuity (Australia) Limited is the underwriter, lead

  5. Slide 5: Corporate Structure

    Corporate Structure Strong Balance Sheet and Supportive Shareholders Capital Structure Pre-raise Board of Directors2 Shares on Issue 599.96M Brian O’Donnell Non-Executive Chairman Share Price (10-day VWAP at 16 Nov-2021) $0.481 Alwyn Vorster Managing Director 6-month liquidity (16 Nov-2021) $60.2M M

  6. Slide 6: Mardie Highlights

    Mardie Highlights Multi-generational and sustainable opportunity with annuity style income  Pilbara coast is a proven production region for high-quality, consistent salt with five existing solar evaporation salt projects, owned by Rio Tinto and major Japanese companies, operating here for up to 50

  7. Slide 7: Equity Raise Structure

    Equity Raise Structure $360 million capital raising represents last piece of $1.2 billion funding package  BCI has secured $740M of project finance debt (62% of funding requirement)  BCI to contribute $460M of equity before debt drawdown in 1H 2023  Successful $360M equity raise plus BCI cash and

  8. Slide 8: Funding for Development and Ramp-up

    Funding for Development and Ramp-up Up to $360M of new equity and Convertible Notes to be issued1  Forms part of BCI’s $460M total equity contribution to the Mardie Project, subject to shareholder approvals  Additional to the recently secured $740M of Mardie Project debt2 $740M BCI Minerals 38% Up

  9. Slide 9: Transaction Overview

    Transaction Overview Key Funding Terms Offer Size and The Company is conducting a capital raising of up to $360 million (before expenses), comprising: Structure  A share placement of up to 558,139,535 fully paid ordinary shares ('New Shares') at an issue price of $0.43 per New Share to raise up to

  10. Slide 10: Transaction Overview

    Transaction Overview Key Funding Terms Share Purchase  The SPP has been underwritten by Canaccord up to $20 million, subject to shareholder approval. Plan  AustralianSuper has committed to sub-underwrite the full underwritten amount of $20 million, subject to shareholder approval.  Under the SPP,

  11. Slide 11: Indicative Equity Timeline

    Indicative Equity Timeline Placement and Share Purchase Plan Event Date Trading Halt Wednesday, 17 November 2021 SPP record date 5pm WST Wednesday, 17 November 2021 Announcement of equity raising and Placement bookbuild Thursday, 18 November 2021 Notice of Extraordinary General Meeting released Thur

  12. Slide 12: Salt and Potash Markets

    BCI Minteots Salt and Potash Markets

  13. Slide 13: Salt Demand Closely Correlated with GDP

    Salt Demand Closely Correlated with GDP Salt end uses cover all key sectors of the economy  ~335Mtpa global market; 160Mtpa Asian Market  >10,000 direct and indirect uses across many market segments  Strong correlation (r=0.97) between salt demand and Asian GDP Asia Salt Consumption vs Asia GDP (

  14. Slide 14: Positive Salt Market Outlook

    Positive Salt Market Outlook Strong demand growth in Asia and insufficient new supply CONTESTABLE1 ASIAN MARKET DEMAND/SUPPLY; 2020-2030 (Mtpa)  Strong Asian salt demand; supply 29 105 constraints in India & China 21 95 10  Demand in Mardie’s contestable market projected to grow by >35% 76 74 in n

  15. Slide 15: Salt Market Strategy

    Salt Market Strategy Strong customer interest - MOUs to be converted to offtake contracts  Typically 2-year contracts and price settlements with individual customers – no official published benchmark  16 non-binding MOUs and 1 non-binding termsheet signed across target markets covering >100% of fi

  16. Slide 16: SOP – High Quality Potassium Fertiliser

    SOP – High Quality Potassium Fertiliser Growth market driven by demand for high quality fruits and vegetables  ~70Mtpa global potash market of which ~65Mtpa is muriate of potash (MOP) and ~6.5Mtpa sulphate of SOP BENEFITS IN PLANTS potash (SOP) Encourages strong Improves Growth  SOP is a premium f

  17. Slide 17: SOP Market Strategy

    SOP Market Strategy MOUs to be converted to offtake contracts over next 18-months  Buyers include compound and bulk fertiliser producers and distributors SOP TARGET MARKETS (140KTPA) China Japan Oceania USA SE Asia Other Asia  Typically 2-5-year tonnage contracts with 1-2-year pricing – European p

  18. Slide 18: Salt and SOP Price Strength

    Salt and SOP Price Strength Salt and SOP Prices driven by strong demand and limited new supply SALT Australian Imported Salt into China1,2  15-year pricing from ~US$35/t to ~US$75/t 65 delivered1 in Asia 55  Delivered salt price in China has increased by US$/t, CFR ~30% in the first half of 20211

  19. Slide 19: Mardie Salt & Potash Project

    Mardie Salt & Potash Project 19

  20. Slide 20: Mardie Project Design

    Mardie Project Design Largest salt project in Australia – fully integrated with port SITE CONDITIONS PROJECT LAYOUT  >100km2 clay soils – ideal pond floor  High net evaporation rates (~10mm/day) PRODUCTION  9 evaporation ponds  42 salt and 20 SOP crystallisers  Salt wash plant - 5.35Mtpa >99.5%

  21. Slide 21: Positive Stakeholder & Approval Progress

    Positive Stakeholder & Approval Progress Native title agreements in place; Approvals and tenure advanced GOVERNMENT  NAIF loan of $490M approved1 – largest in WA  EFA loan of $110M approved1  Efficient WA Government facilitation across agencies ENVIRONMENT  EPA positive referral to WA Environmen

  22. Slide 22: Sustainability Focus

    Sustainability Focus Inexhaustible resources, natural energy and waste minimization 1. Inexhaustible seawater feedstock; no resource depletion – 100+ year project life; No landscape scarring, mine pits, waste dumps or large-scale dewatering 2. 99% of energy derived from solar and wind – Renewable st

  23. Slide 23: Strong Financial Metrics

    Strong Financial Metrics Annuity-style cash flow >60 years1 with material upside FINANCIALS2 Pre-tax, NPV7 Sensitivity Analysis (A$M, Real)  NPV7: A$1,561M Discount Rate: 7% +/- 1%  EBITDA: A$256Mpa (Salt ~72%; SOP ~28%) Exchange Rate:  IRR: 15.5% AUD/USD (0.70): +/- 10%  60-year Cumulative Cash

  24. Slide 24: Capital Cost Estimate

    Capital Cost Estimate Estimates de-risked through independent reviews and value engineering  Estimates re-confirmed as AACE1 Class 3 with A$M A$M Area Description an accuracy range of ±10-15%. Real Nominal Salt2 282.5 294.4  Project capital cost estimate $954M ($ real) - SOP3 119.9 127.4 applied f

  25. Slide 25: Contracting Strategy

    Contracting Strategy 60%+ of Capital Cost to be delivered via fixed price contracting model1 NORTHERN EMBANKMENT TRIAL  Experienced BCI owner’s team assembled2  Engenium engaged as integrated Project Management Contractor (PMC) service provider  Pond wall construction trial successfully completed

  26. Slide 26: Mardie Will Have an Integrated Port Facility

    Mardie Will Have an Integrated Port Facility Marine structure is single largest contract  Marine structure package value >$180M  Contract award targeted for Q4 20211  Design, procurement and port access (causeway and road) construction scheduled to commence Q1 20221  Jetty construction scheduled

  27. Slide 27: Operating Cost Estimates

    Operating Cost Estimates Estimates de-risked through independent reviews and value engineering  AACE1 Class 3 estimate with an accuracy range of ±10-15% SALT OPEX ESTIMATES ($ real)  Estimates recognise equipment and labour cost increases during 1.8 FY21 Cash costs (Ex-works)  Base Case All In Su

  28. Slide 28: Salt Cost Curve – Contestable Market

    Salt Cost Curve – Contestable Market Mardie will be a low-cost supplier of salt into contestable1 Asian market 60 Mardie Salt 50 Only  Mexican solar salt and Chinese rock salt the marginal cost suppliers Chinese Rock 3rd Tier to most Asian markets Other Mardie with Chile 40 CIF eq. Cost (US$/t) SOP

  29. Slide 29: SOP Cost Curve

    SOP Cost Curve1 Mardie is expected to be the lowest cost supplier of SOP globally 500 Mardie SOP Only  Marginal cost is USA Primary 400 ~US$350/t FOB/ex works China Tier 2 Secondary Europe 1 Primary MARGINAL COST Middle East 2 Secondary  The majority of high Middle East 1 Secondary Other East Asia

  30. Slide 30: Final Investment Decision Made

    Final Investment Decision Made Followed significant project de-risking over several years  Definitive Feasibility Study (DFS) July 20201; Optimised Feasibility Study (OFS) April 20212  Confirmation from independent expert reviews that Project development strategies, operating plans, revenue and co

  31. Slide 31: Indicative Project Schedule

    Indicative Project Schedule 2021 2022 2023 2024 2025 2026 Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4 Q1 | Q2 | Q3 | Q4 H1 | H2 H1 | H2 Early Works; Approvals1 OFFTAKE CONTRACTS NEGOTIATED Funding EQUITY CONTRIBUTION DEBT PERIOD PONDS FID2 CRYSTALLISERS GROW SALT INVENTORY MAIN CONSTRUCTIO

  32. Slide 32: Equity Funding For Main Construction

    Equity Funding For Main Construction 32

  33. Slide 33: Construction Funding Sources and Uses

    Construction Funding Sources and Uses1 $460M equity contribution required prior to first drawdown of project debt  $460M to cover financing costs and significantly advance: Jetty – Accommodation village – Primary seawater intake structure and pumps – Evaporation ponds construction – Crystalliser co

  34. Slide 34: Funding Provided By Iron Valley Royalty

    Funding Provided By Iron Valley Royalty Royalty payments provide funding support for Mardie construction  Quarterly royalty earnings from operating agreement with IRON VALLEY MINE Mineral Resources Ltd (ASX: MIN)  Iron Valley royalty earnings forecast to provide additional funding to first Project

  35. Slide 35: BCI’s Other Assets

    BCI’s Other Assets BCI’s strengthening salt and potash portfolio and further iron ore upside OTHER SALT AND POTASH INTERESTS  BCI to become a ~7% shareholder in HFR and a ~15% shareholder in AMN1, subject to shareholder approval – HFR owns the 100% of the Muga Potash and Salt Project in northern Sp

  36. Slide 36: Pro Forma Balance Sheet

    Pro Forma Balance Sheet Assumptions  Placement proceeds of approximately $256.2M 30 Sep-21 Net 30 Sep-21 Pro Forma Balance Sheet after expenses of approximately $3.8M Unaudited Proceeds Pro-forma $M $M $M  Convertible Note Series 1 value of $29.1M reflects Cash 87.4 256.21 343.6 market value of AM

  37. Slide 37: AustralianSuper Convertible Notes

    AustralianSuper Convertible Notes Convertible notes provide BCI with funding optionality  Series 2 & 3 Convertible Notes provide BCI with up to $100M cash  Subject to shareholder approval and conditions to drawdown and issue including BCI and AustralianSuper agreeing to any additional conditions t

  38. Slide 38: Mardie will become a Tier 1 Project

    Mardie will become a Tier 1 Project Large scale, low cost and long operating life STRONG STAKEHOLDER LARGE SCALE, 3. QUALITY ROBUST MARKETS; 5. LOWSTRONG COST; 2. SUSTAINABLE SUSTAINABLE 4. LOW COST STRONG CASHFLOWS SUPPORT MULTI-GENERATIONAL PRODUCTS QUALITY PRODUCTS CASHFLOWS  Strong support from

  39. Slide 39: Why Invest in BCI?

    Why Invest in BCI? Significant Mardie upside potential CURRENT VALUATION MARDIE POTENTIAL  Low enterprise value of  Salt & SOP growth markets ~$183M (pre-raise) 1  Tier 1 – sustainable, large  ~$106M cash (pre-raise)1; scale, low cost & long life no debt  ~$250M/annum EBITDA for 100 years2 1As

  40. Slide 40: Appendices

    = BCI minees's Appendices

  41. Slide 41: Mardie Production Process

    Mardie Production Process1 99% Sun and Wind Energy 4. Salt Wash Plant 5. Salt Stockpiles C. SOP Storage Shed 7. Transhipper 6. 2.4km (12,000t) Jetty B. SOP Process Plant 8. Ocean Going Vessel A. KTMS2 (up to Capesize) Crystallisers (5km2) 9. Export 3b. Secondary Salt Crystallisers (6km2) 3a. Primary

  42. Slide 42: BCI Board of Directors

    BCI Board of Directors Brian O’Donnell Alwyn Vorster Michael Blakiston NON-EXECUTIVE CHAIRMAN MANAGING DIRECTOR NON-EXECUTIVE DIRECTOR  Banking and investment background  Geology, Mineral Economics, MBA  Legal and mining business background  Director, Finance and Investments -  Kumba; Rio Tinto

  43. Slide 43: BCI Executive Team / Key Project Personnel

    BCI Executive Team / Key Project Personnel Alwyn Vorster Sam Bennett Stephanie Majteles MANAGING DIRECTOR PROJECT DIRECTOR GENERAL COUNSEL/JOINT COMPANY SECRETARY  Geology, Mining and MBA degrees  Civil engineering degree  Law degree  Kumba; Rio Tinto; Iron Ore Holdings  Fortescue; Roy Hill; WS

  44. Slide 44: Potential Impact on Voting Power

    Potential Impact on Voting Power  The impact of passing Resolutions on AustralianSuper and Wroxby’s maximum voting power in the Company in various scenarios. The table below assumes that all Convertible Notes are fully drawn and converted at their maturity, all interest and fees are capitalised to

  45. Slide 45: Underwriting Agreement: Key Terms

    Underwriting Agreement: Key Terms Overview Canaccord Genuity (Australia) Limited (ABN 19 075 071 466) ('Underwriter') is appointed as the exclusive underwriter, bookrunner and lead manager to the Placement and SPP (together, the 'Offer'). The Company has entered in an underwriting agreement with the

  46. Slide 46: Underwriting Agreement: Key Terms

    Underwriting Agreement: Key Terms • (Contravention of constitution or Act): a contravention by a member of the Group of any provision of its constitution, the Corporations Act, the Listing Rules or any other applicable legislation or any policy or requirement of ASIC or ASX; • (Adverse change): an e

  47. Slide 47: Placement Agreement: Key Terms

    Placement Agreement: Key Terms Overview Company has entered into a Placement Agreement ('Placement Agreement') with AustralianSuper. Under the terms of the Placement Agreement, AustralianSuper has agreed to subscribe for, up to 174,418,605 New Shares at an issue price of $0.43 per New Share to raise

  48. Slide 48: Key Risks (1)

    Key Risks (1) Development of the Mardie Salt and Potash Project The Company’s ability to successfully develop and commercialise the Mardie Salt and SOP project ('Mardie' or 'Project') may be affected by numerous factors including but not limited to: macro-economic conditions, obtaining required appr

  49. Slide 49: Key Risks (2)

    Key Risks (2) Offtake Risk There is no certainty that BCI will be able to enter into binding offtake agreements in a timely manner, with acceptable parties, for sufficient volumes or on reasonable terms to satisfy the debt funding requirements. Offtake contracts could be entered into at a lower pric

  50. Slide 50: Key Risks (3)

    Key Risks (3) Control risk Upon completion of the Placement and SPP (assuming full subscription and shareholder approvals), the number of Shares in the Company will increase from 599,957,864 to approximately 1,204,609,027. Further, if the Series 1, 2 and 3 Convertible Notes are converted to shares,

  51. Slide 51: Key Risks (4)

    Key Risks (4) Climate Change Risk There are a number of climate-related factors that may affect the proposed operations and financial position of the Company. The climate change risks particularly attributable to the Company include the risk of increased frequency of severe weather events which may

  52. Slide 52: Key Risks (5)

    Key Risks (5) Data Security Risk It is possible that the Company’s procedures and systems may not stop or detect cyberattacks, data theft and hacking. Cyber security breaches may result in business interruption and loss of commercially sensitive data, which could have an adverse impact on the Compan

  53. Slide 53: Key Risks (6)

    Key Risks (6) Securities Investments and Share Market Conditions Generally There are risks associated with any securities investment. The prices at which the securities trade may fluctuate in response to a number of factors. Furthermore, the stock market, and in particular the market for exploration

  54. Slide 54: International Offer Restrictions

    International Offer Restrictions This document does not constitute an offer of new ordinary shares ("New Shares") of the Company in any jurisdiction in which it would be unlawful. In particular, this document may not be distributed to any person, and the New Shares may not be offered or sold, in any

  55. Slide 55: International Offer Restrictions

    International Offer Restrictions Indonesia A registration statement with respect to the New Shares has not been, and will not be, filed with Otoritas Jasa Keuangan in the Republic of Indonesia. Therefore, the New Shares may not be offered or sold to the public in Indonesia. Neither this document nor

  56. Slide 56: International Offer Restrictions

    International Offer Restrictions Switzerland The New Shares may not be publicly offered in Switzerland and will not be listed on the SIX Swiss Exchange or on any other stock exchange or regulated trading facility in Switzerland. Neither this document nor any other offering or marketing material rela

  57. Slide 57: Contact details

    T +61 8 6311 3400 Level 1, 1 Altona St GPO Box 2811 E info@bciminerals.com.au West Perth West Perth W www.bciminerals.com.au WA 6005 WA 6872

BCI Minerals — Investor Presentation (November 2021) on 6ix