Turquoise Hill Resources — Non-Deal Roadshow (June 2016)
19 slides from Turquoise Hill Resources's roadshow presentation, Jun 30, 2016
Slide 1: The future of Oyu Tolgoi is underground
Investor Meetings JUNE 30, 2016 The future of Oyu Tolgoi is underground Developing the third-largest copper mine
Slide 2: Forward-looking statements
Forward-looking statements This presentation includes certain “forward-looking information” within the meaning of applicable Canadian securities legislation and “forward-looking statements” within the meaning of the “safe harbour” provisions of the United States Private Securities Litigation Reform
Slide 3: Investment summary
Investment summary Re-starting underground development • 2015 –Underground Development Plan approved (May), pre-start activities began (Aug) and project finance signed (Dec) • May 2016 – Notice to proceed approved and 2016 feasibility study completed • June 2016 – EPCM contract awarded to Jacobs Eng
Slide 4: Multi-generational copper asset
Multi-generational copper asset* Southern Oyu Open Pit ~1,000Mt (reserve) 0.45% copper; 0.31 g/t gold Hugo North Lift 1 ~500Mt (reserve) Hugo South 1.66% copper; 0.35 g/t gold ~300Mt (resource) 1.07% copper Heruga 0.06 g/t gold ~700Mt (resource) 0.42% copper 0.43 g/t gold; >100Mlb moly Plant Hugo No
Slide 5: Hugo North Lift 1 development timeline
Hugo North Lift 1 development timeline Sustainable underground production Complete convey to surface Project 1st draw Complete concentrator Complete re-start bell firing upgrade ramp-up 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Pre-start Excavation (lateral / mass / vertical)
Slide 6: Key underground components
Key underground components Not on critical path Shaft 1 Shaft 2 Shaft 5 Shaft 3 Shaft 4 (early development (production and (ventilation) (ventilation) (ventilation) and ventilation) ventilation) Total Depth 1,385 metres 1,284 metres 1,195 metres 1,148 metres 1,220 metres Diameter 6.7 metres 10 metre
Slide 7: Medium-term timeline
Medium-term timeline 2015 – 2016 2016 – 2020 2021 – 2026 2027 + • Project finance • Hugo North Lift 1 • Sustainable • Hugo North Lift 2 signed construction underground production • Hugo South • Completed • Additional $1.6 billion • Ramp-up to full feasibility study project financing debt production
Slide 8: Multiple development options
Multiple development options Source: 2014 Oyu Tolgoi Technical Report Production creep targeted along with expansion Actual operating performance will inform choice of expansion path A decision to expand the concentrator is not required for a couple years 8
Slide 9: Project financing – flow of funds
Project financing – flow of funds At March 31, 20161 At project financing drawdown Payable to Turquoise Hill* Receivable from Oyu Tolgoi* Proceeds: $4.4 billion2 $4.1 billion3,4 $4.1 billion4 Shareholder loan: $7.0 billion Shareholder loan: $7.0 billion Payable to Turquoise Hill* Receivable from Oyu
Slide 10: Production highlights
Production highlights Concentrator throughput Concentrate production ('000 tonnes) (‘000 tonnes) 788.5 34,537 27,872 563.6 215.5 210.3 231.8 229.5 9,025 8,632 9,369 9,662 7,512 130.9 Q1'15 Q2'15 Q3'15 Q4'15 Q1'16 2014 2015 Q1'15 Q2'15 Q3'15 Q4'15 Q1'16 2014 2015 Q1’16 throughput averaging above name
Slide 11: Financial highlights
Financial highlights Cash position Operating cash flow ($'000,000) ($'000,000) $1,482.2 $718.5 $1,310.4 $1,343.9 $650.5 $1,200.0 $954.2 $862.8 $239.2 $171.7 $195.9 $138.1 $101.5 Cu:$2.66* Cu:$2.77 Cu:$2.39 Cu:$2.20 Cu:$2.11 Cu:$3.10 Cu:$2.51 Au:$1,219* Au:$1,194 Au:$1,124 Au:$1,106 Au:$1,183 Au:$1,2
Slide 12: Phases of open-pit production
Phases of open-pit production In Q2’16, mining bottom of phase 2 as well as phases 3 and 6 Phase 2 mining expected to complete in Q2’16 Deferred stripping of phase 4 underway, expected until late 2018 2 2 Material by select pit phases Phase Ore (Mt) Waste (Mt) Strip Ratio Cu (%) Au (g/t) Phase 3 41
Slide 13: Copper industry overview
Copper industry overview 2025 copper mine C1 + sustaining normal cost curve C/lb, 2016$ 400 In top three largest copper mines after Oyu Tolgoi planned expansion1 Other Mines 300 2025-2030 expected average annual copper production of ~560kt2 200 Top 10 copper deposit by contained reserves 100 and res
Slide 14: Copper supply/demand (Mt)
Long-term copper fundamentals strong Copper mine supply/demand outlook Copper market likely to see Base Highly Probable Primary Demand Annual Avg Cu Price small surplus in coming years. Forecast 30 $4 Ongoing attrition at existing mines driven by declining Annual average LME copper price (US$/lb) 25
Slide 15: Turquoise Hill – a long-term growth opportunity
Turquoise Hill – a long-term growth opportunity Pure copper and gold exposure Positive operating cash flow with focused asset optimization Agreed path forward for development of the high-grade underground mine Significant growth, development and expansion opportunities Resources located near China w
Slide 16: Appendix
Appendix
Slide 17: Ore flow
Ore flow APEX LEVEL Lateral Development lg UNDERCUT LEVEL ~-@ > eC Lateral Development Undercutting Undercut Mucking & Ground Support EXTRACTION LEVEL \vaa"/ «>t PB paid: Lateral Development & Ground Support Drawpoint / Drawbell Production Construction Secondary Breaking \ rere Foe: DUMP AT Fill Tru
Slide 18: Oyu Tolgoi at China's doorstep
Oyu Tolgoi at China’s doorstep 18
Slide 19: Made in Mongolia
Made in Mongolia Mongolians occupy 95% of Oyu Tolgoi roles Since 2010, in-country spend of $5.5 billion (Mongolian suppliers, salaries, taxes and other Government payments) Partnered with more than 800 local suppliers in 2015, accounting for over 50% of procurement spend In April 2015, Oyu Tolgoi si