Slide 1: Duralie Coal CCC Meeting Presentation – Company Report & Overview of Activities
Duralie Coal CCC Meeting Presentation – Company Report & Overview of Activities February 2020 Alarna Bristow Environment & Community Superintendent
Slide 2: Table of Contents
Table of Contents 1. Agenda Item 7a - Progress at the Mine 2. Agenda Item 7b - Environmental Reporting 3. Agenda Item 7c - Environmental Management Plans & Monitoring 4. Agenda Item 7d - Community Complaints 5. Agenda Item 7e - Community Programs 2 19 February 2020 2
Slide 3: 1. Progress at the Mine
1. Progress at the Mine Mining 2nd Half 2019 No mining operations were undertaken at Duralie during the second half of 2019. Rehabilitation works continued with bulk shaping of the waste emplacement and Rogers road. AD1 Decommissioning 1st Half of 2020 PAF re-handling works is currently out
Slide 4: 2. Environmental Reporting & Regulators
2. Environmental Reporting & Regulators Management Project Status Area Reporting • Duralie Coal Mine Annual Review • The Duralie Coal Mine 2019/20 Annual Review is due August 2020. The Annual Review 2019/20 will be made available to the CCC and on the Duralie Coal website. Regulator • Mining Operati
Slide 5: 3. Environmental Management Plans & Monitoring
3. Environmental Management Plans & Monitoring a) Air Quality Management b) Blast Management c) Noise Management d) Water Management e) Rehabilitation Management f) Biodiversity Management g) Mine Closure Planning 5 19 February 2020 5
Slide 6: 3a. Air Quality Management – Dust Deposition
3a. Air Quality Management Duralie Dust Deposition - Annual Rolling Average 12 Months to January 2020 8.0 Dust (g/m2/month) 6.0 4.0 2.0 0.0 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 D3 D4 D5 D5A D7 D8 D9 D10 D12 D13 DP&E limit Feb-19 Heavy - 40% Dirt, 60% Po
Slide 7: 3a. Air Quality Management – PM10 Monitoring
3a. Air Quality Management Duralie HVAS Monitoring (PM10) 200 12 Months to January 2020 150 PM10 (µg/m3) 100 50 0 6-Dec-18 4-Feb-19 5-Apr-19 4-Jun-19 3-Aug-19 2-Oct-19 1-Dec-19 30-Jan-20 -50 High Noon Twin Houses Hattam Edwards DP&E Limit Duralie HVAS Monitoring (PM10) • All sites below DP&E limit.
Slide 8: 3b. Blast Management
3b. Blast Management Management Project Status Area Blasting • Blast monitoring • Blast activities at the DCM were completed on 17 August 2018. No further blasting is proposed until further notice. • Note: Blast Compliance: No more than 5% of total blasts for annual monitoring period to exceed an ov
Slide 9: 3c. Noise Management
3c. Noise Management Management Project Status Area Noise • Routine Monitoring • Routine quarterly monitoring of operations recommenced in Q4. Monitoring • Noise reports are made available on the Duralie Coal website. Noise • Real-Time Noise Management • During Q4 2018 operations at the Duralie Mine
Slide 10: 3d. Water Management
3d. Water Management Management Project Status Area Site Water • Annual water balance review. • The 2019 annual site water balance review is currently being prepared. A summary will Management be included in the Annual Review. Surface Water • Routine monitoring • Sporadic and low rainfall conditions
Slide 11: 3d. Water Management – Rainfall and Surface Water
3d. Water Management Duralie Mine Site - Monthly Rainfall Duralie Surface Water Monitoring - pH 6 months to January 2020 10 300 9 200 8 7 Rainfall (mm) 100 6 5 05-May-1904-Jun-19 04-Jul-19 03-Aug-1902-Sep-1902-Oct-1901-Nov-1901-Dec-1931-Dec-1930-Jan-20 0 2019 SW2 - DCPL (CSC) SW2 RC - Rail Culvert D
Slide 12: 3e. Rehabilitation Management
3e. Rehabilitation Management Management Area Project Status Rehabilitated Waste • Rehabilitation Works • Rehabilitation of 20ha was commenced during H2 2019, including topsoil spreading, emplacements ground preparation and seeding. 20ha of native will be planted in February 2020. • Rehabilitation m
Slide 13: 3e. Rehabilitation Management – Dam Decommissioning
3e. Rehabilitation Management Management Area Project Status Dam • Auxiliary Dam 1 • Decommissioning and rehabilitation of AD1 is proposed to commenced in October Decommissioning 2019 • Clay has been recovered and is being stockpiled for use for the clay lining in the Coal Shaft Creek Reconstruction
Slide 14: 3f. Biodiversity Management
3f. Biodiversity Management Management Project Status Area BMP • Biodiversity • A revision of the Biodiversity Management Plan has been prepared following the first 5 years of Management Plan implementation. A summary of the biodiversity offset works completed and the changes to the revision BMP is
Slide 15: 3f. Biodiversity Management
3f. Biodiversity Management Management Project Status Area Flora/Fauna • Nest Box Program • Annual monitoring of nest boxes is scheduled to be undertaken in February 2020. A summary of the nest box progress will be included in the next Annual Review. Pest Control • Wild Dog control • Wild dog and fo
Slide 16: 3g. Mine Closure Planning
3g. Mine Closure Planning Note: *Refer to Duralie Mining Operations Plan & Rehabilitation Management Plan Table 14 Mine Closure Planning Schedule. *Further detail on mine closure planning progress is included in the Annual Review 2018. Management Project Status Area Mine Closure • Stakeholder • Comm
Slide 17: 4. Community Complaints
4. Community Complaints Duralie Complaint Summary Period: 31/06/2019 - 31/01/2020 Period: 6 Months Total No. of Complaints: 0 (0 noise, 0 blast, 0 air quality, 0 other) Total No. of Complainants: 0 Date/Time of Method of Nature of Complaint Complainant Location Complaint Complaint Investigation/Outc
Slide 18: 5. Community Programs
5. Community Programs Management Area Project Status Support Programs Stratford Coal • The application period for the 2020 Stratford Coal Community Support Program is closed. Community Support • Applications have been reviewed with the outcomes announced in February 2020. Program Stratford Coal • Th