Cleanaway Waste Management Ltd. · ASX:CWY

Cleanaway Waste Management — Corporate Update (November 2018)

5 slides from Cleanaway Waste Management's corporate update, Nov 29, 2018

  1. Slide 1: MRL CRG – Cleanaway Update

    MRL CRG – Cleanaway Update 29 November 2018

  2. Slide 2: Cell Construction

    Cell Construction • Cell 4A construction completed and added to the license. • Key environmental improvements: – Litter management – Re-design of leachate sumps • Sub grade works have commenced for Cell 4B-1

  3. Slide 3: Operations Update

    Operations Update • Screening soil bunds left by Boral • Will begin transition into Cell 4A late this week / early next week. • New haul constructed. • Have begun placing intermediate capping on Cell 3B.

  4. Slide 4: Environment Update

    Environment Update • November groundwater monitoring event completed. • Update to the Landfill Operations Risk Assessment & Landfill Environmental Monitoring Plan. Conditional auditor approval. • Environmental Audit commenced. • New set of horizontals being installed in Cell 3B • Wheel wash repairs

  5. Slide 5: Major Projects Update

    Major Projects Update Major works scheduled in the next 12 months • 12 m Litter Nets: Geotechincal works commencing once suitable permits have been issues for drilling (approval required from Department of Mining). Current expected completion July 2019. • LFG Upgrades: Design of new LFG ring main go