Slide 1: Emergence of a new world-class copper and gold producer
Emergence of a new world-class copper and gold producer Kay Priestly Chief Executive Officer September 6, 2012 Bank of America/Merrill Lynch Mining Conference
Slide 2: Forward-looking statements
Forward-looking statements This presentation includes certain “forward-looking statements.” All statements, other than statements of historical fact, are forward-looking statements that involve various risks and uncertainties. There can be no assurances that such statements will prove accurate and a
Slide 3: China continues to drive global demand
China continues to drive global demand Global copper demand is being driven by Supply continues to underperform China against expectations… 2009 2010 2011 YTD 2012 Global refined copper consumption1 kt Cu -4% 30000 -3% China Rest of World 348kt -2% 451kt 25000 639kt -6% 20000 1013kt ...as disruption
Slide 4: Oyu Tolgoi well placed to meet Chinese metals requirements
Oyu Tolgoi well placed to meet Chinese metals requirements 4
Slide 5: World-class asset, experienced operator
World-class asset, experienced operator Near-term and Experienced and High grade and low cost large scale innovative operator • Initial production in H2 2012 • Ranks in top five copper projects • Track record of developing and by grade operating world-class assets • Multi decade mine life • Expected
Slide 6: Unique pure copper/gold exposure
Unique pure copper/gold exposure Top 15 producing copper mines (2020)(1) $3.00 $2.50 $2.00 2020E C1 Cash Cost ($/lb) $1.50 $1.00 Turquoise Hill Resources/ Oyu Tolgoi(2) $0.50 Bubble size reflects contained copper resources (kt) Independent copper producer and publicly traded Owned by diversified min
Slide 7: Counting down to start-up
Counting down to start-up Overall phase one construction topped 97% at end of August 2012 First delivery of ore to primary crusher in July 2012 Power infrastructure completed, fully tested and ready for commissioning First production of concentrate expected in fourth quarter of 2012 Start
Slide 8: Staged development with attractive growth profile
Staged development with attractive growth profile First Production Commercial Production First U/G Production Expand Mill to 160ktpd Phase 2 U/G Completed 2012 2013 2014 2015 2016 2017 2018 2019 2020 800 1.5 1.2 600 Gold Production (mm oz) Copper Production (kt) 0.9 400 0.6 200 0.3 0 0.0 2012 2013 2
Slide 9: Well capitalized to fund development
Well capitalized to fund development Equity Successfully completed US$1.8 billion rights offering Financing 99.2% of shares taken up in initial subscription, balance (US$1.8 Bn) taken up in secondary Bridge The bridge facility remains undrawn Loan (US$1.5 Bn) Ensures project development rema
Slide 10: Significant expansion potential and execution flexibility
Significant expansion potential and execution flexibility Potential expansion options 10
Slide 11: Conclusion
Conclusion Long-term copper outlook remains positive Overall phase one construction progressing on schedule and on budget Production start-up expected in fourth quarter of 2012 with commercial production to commence in first half of 2013 Funding plan progressing well with successful $1.8 bil
Slide 12: Appendix
Appendix 12
Slide 13: Ore delivered to the coarse-ore storage, shafts #1 and #2 in background
Ore delivered to the coarse-ore storage, shafts #1 and #2 in background 13
Slide 14: Stockpiling open-pit ore in the coarse-ore storage building
Stockpiling open-pit ore in the coarse-ore storage building 14
Slide 15: First test run of SAG mill #1
First test run of SAG mill #1 15
Slide 16: Ball mill test runs
Turquoise Hill Resources Ltd. Ball mill test runs