Core Scientific, Inc. · NASDAQ:CORZ

Core Scientific — Q4 2025 Earnings Presentation

16 slides from Core Scientific's earnings presentation, Mar 2, 2026

  1. Slide 1: Fourth Quarter Fiscal 2025 Earnings Call

    Fourth Quarter Fiscal 2025 Earnings Call March 2, 2026 1

  2. Slide 2: Forward-Looking Statements

    FORWARD-LOOKING STATEMENTS This presentation includes forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, (the “Securities Act”) and Section 21E of the Securities Exchange Act of 1934, as amended, (the “Exchange Act”). Forward-looking statements ma

  3. Slide 3: Core Scientific overview

    Core Scientific overview Core Scientific is a leader in digital infrastructure for high-density colocation services. We operate dedicated, purpose-built facilities for high-density colocation services and are a premier provider of digital infrastructure, software solutions and services to our third-

  4. Slide 4: Integrated colocation platform

    Site & Infrastructure Access Delivery & Build Execution Operations & Scalable Growth Find & Secure Sites Design & Engineer Operate & Maintain 1 5 8 Identify, evaluate, and secure Translate customer requirements Operate and maintain sites with available power, strong into tailored designs that keep i

  5. Slide 5: Over 800 MW of announced leasable power capacity

    Over 800 MW of announced leasable power capacity contracted sites Customer leasable sites Denton, TX Hunt County, TX Leased power: ~260MW Leasable power: ~285MW Dalton, GA Pecos, TX Leased power: ~175MW Leasable power: ~200MW Muskogee, OK Dalton, GA Leased power: ~70MW Leasable power: ~120MW Marble,

  6. Slide 6: Total Leasable Power Pipeline

    Total Leasable Power Pipeline* Our current power pipeline has ~1.5 GW of customer leasable power potential ~700 MW ~1.5 GW ~285 MW ~520 MW UNANNOUNCED LEASABLE CUSTOMER NEW HUNT COUNTY, TX POWER OPPORTUNITIES LOCATION CURRENT LEASABLE TOTAL LEASABLE CAPACITY AT EXISTING CUSTOMER SITES POWER PIPELINE

  7. Slide 7: Investment Highlights

    Investment Highlights Established expertise Attractive business model Demand & growth visibility 150+ years of combined Colocation contracts deliver 12-year, $10B+ CoreWeave data center leadership compelling economics and contract, ~$850M average experience strong margins annual revenue run rate A l

  8. Slide 8: Expansion into Hunt County

    Expansion into Hunt County brings Texas footprint to ~485 MW* in leasable power capacity Hunt County Site Details Agreement to acquire LLC owning ~265 acres Denton Hunt ~430 MW of gross capacity Dallas ~285 MW of leasable customer power capacity Pecos Austin Begin energization in 2027, ramping to fu

  9. Slide 9: Construction Update

    Construction Update 185+ MW ~350 MW 65K+ ~1M Sq Ft ~5M $5B+ Billable Capacity Energized to Customer GPUs Of Data Center Shells Total Labor Hours Through Total Aggregate Delivered to Date Date Supported Constructed Construction Project Investments ✓ Broke ground on 5 AI factories supporting ~590 MW c

  10. Slide 10: CoreWeave Relationship Overview

    CoreWeave Relationship Overview 10

  11. Slide 11: CoreWeave is contracted for ~590 MW of leased customer power capacity

    CoreWeave is contracted for ~590 MW of leased customer power capacity across 5 of our sites Denton, TX Leased power: ~260MW Dalton, GA Leased power: ~175MW Muskogee, OK Leased power: ~70MW Marble, NC Leased power: ~65MW Austin, TX Leased power: ~20MW Total leased power ~590 MW 11

  12. Slide 12: Contract summary

    Contract summary 12-year contract No ability to unilaterally ~590MW infrastructure with two 5-year options 3 terminate, with aligned joint ~800MW gross execution risk $10B+ in revenue potential Take-or-pay contract over the contracts’ term at a fixed cost, with annual escalator ~$850M average annual

  13. Slide 13: Appendix

    Appendix 13

  14. Slide 14: Restatement Overview

    Restatement Overview • In connection with the transition to KPMG as independent auditor, we identified an accounting error related to the treatment of certain Property, Plant and Equipment (PP&E) associated with legacy mining-to-colocation site conversions going back to 2024 • Demolition costs and e

  15. Slide 15: Term library

    Term library Term Definition How management uses it Total electric utility power capacity agreements associated with our data Gross Utility Power Capacity (MW) center sites under our control as of period end, including capacity that is Used for portfolio planning and utility power allocation discuss

  16. Slide 16: Contact

    Contact ir@corescientific.com 16

Core Scientific — Q4 2025 Earnings Presentation on 6ix