Pivotal Metals Limited · ASX:PVT

Pivotal Metals — Investor Presentation (April 2025)

27 slides from Pivotal Metals's investor presentation, Apr 3, 2025

  1. Slide 1: Investor Presentation April 2025

    For personal use only PIVOTAL METALS LTD BUILDING A COPPER Investor Presentation BUSINESS IN THE WORLDS BEST MINING ASX:PVT JURISDICTION April 2025

  2. Slide 2: Disclaimers

    Disclaimers For personal use only The release, publication or distribution of this presentation in certain jurisdictions may be restricted by law and therefore persons in such jurisdictions into which this presentation is released, published or distributed should inform themselves about and observe

  3. Slide 3: Investment Highlights

    Investment Highlights For personal use only Quality Cu-Ni-PGM Copper Focus Horden Lake Universally Bullish Outlook for Copper Advanced Cu-Ni-PGM: +200kt Cu1 / +400kt CuEq Demand case is very robust. Big questions on supply. Majority in-pit. Substantial exploration upside. Lack of credible advanced p

  4. Slide 4: Project Highlights

    Project Highlights Quality base with exciting exploration leverage For personal use only Horden Lake 100% PVT Large metal endowment. Over 200kt Cu1 / 400kt CuEq James Bay Robust grade 28mt1 @ 0.73% Cu (1.5% CuEq) incl. in-pit 17mt @ 1.38% CuEq Low risk exploration upside. Drilling has expanded miner

  5. Slide 5: Quebec – Premier Mining Jurisdiction

    Quebec – Premier Mining Jurisdiction With tangible investment incentives For personal use only ‘Flow-through scheme’ tax incentives Quebec has the highest tax credit in Canada for critical metals exploration Up to 2x leverage on money raised, without structural overhang Access to low-cost renewable

  6. Slide 6: Copper

    Copper Strong supply / demand fundamentals set For personal use only Copper demand growth remains strong Project discovery at all-time lows Shifts to electrification builds on huge industrial demand case Geological return on exploration spend is at all-time lows from developing world Unknown supply

  7. Slide 7: Horden Lake

    For personal use only Horden Lake • Advanced Cu-Ni-PGM Project • Already 28Mt1 @ 0.73% Cu / 1.5% CuEq • Substantial Exploration Upside The Company confirms that it is not aware of any new information or data that materially affects the information included in this presentation and that all material

  8. Slide 8: Horden Lake

    Horden Lake Asset of scale with upside being unlocked For personal use only 2022 MRE1: 27.8 mt @ 1.49 % CuEq ✓ Cu 0.73%, Ni 0.22%, 0.19 g/t Pd, 0.08 g/t Au ✓ 200kt Cu contained, ~400kt CuEq Immediate Exploration Focus Area ✓ 55% indicated category (Drilling + EM) ✓ 17.4mt @ 1.38% CuEq in open pit sh

  9. Slide 9: Step-outs and DHEM delivered in 2024

    Step-outs and DHEM delivered in 2024 Substantial exploration upside defined For personal use only Step-out drilling shows continuity and in places thickening of the deposit Clear extensions of economic grade and strong resource upside potential Refer ASX announcement, 2 October 2024 9

  10. Slide 10: FLTEM Shows Major Scale Potential

    FLTEM Shows Major Scale Potential Undrilled targets, up to 1200m down-plunge extent For personal use only A 39m @ 0.97% CuEq (145m) Inc incl.19.7m @ 1.41% CuEq 32m @ 1.2% CuEq (264m) incl. 14.2m @ 1.78% CuEq Limit of 2022 MRE (320m down-plunge) Limit of 2024 DHEM plates (540m down-plunge) 2024 FLTEM

  11. Slide 11: 2025 Drilling

    2025 Drilling Priority near-term open pit extension potential For personal use only HN-24-108 H33235 HOR-13-02 Step-out Drilling Complete - ASSAYS PENDING 3.2m @ 1.06% CuEq 47.5m @ 0.59% CuEq 23.7m @ 1.24% CuEq from 180m from 145.2m (Cu+Ni only) from 33.4m ✓ 1,557m drilled in Q1 2025 ✓ Focus on shal

  12. Slide 12: Regional Potential

    Regional Potential To make additional discoveries For personal use only Magnetics demonstrate scale opportunity ✓ Clear extensions along strike ✓ Repeating of structure to the west ✓ No, or limited / misplaced, drilling of the key areas for regional growth Pivotal drilled first hole ever into Wester

  13. Slide 13: Byproduct Upside

    Byproduct Upside Valuable byproducts understated in 2022 MRE For personal use only Infill delivering missing data for metal upside ✓ Grade understated in current resource ✓ Cu and Ni only in historical drilling 37.5m @ 1.31% CuEq from 50m By-products: 0.3 g/t 3PGE, 180ppm Co, 7.2g/t Ag ✓ Proven Au,

  14. Slide 14: Metallurgical Testwork

    Metallurgical Testwork Shows attractive NSR potential from conventional flowsheet For personal use only Conventional Floatation Flowsheet Copper is the dominant economic driver ✓ 87-94% Cu total recovery shown in open and closed tests ✓ Low cost and complexity ✓ High grade concentrate, with substant

  15. Slide 15: Development Considerations

    Development Considerations Conventional project with realistic development hurdles For personal use only 17mt1 @ 1.39% CuEq is pit constrained Paved highway within 10km ✓ Low-cost open pit front-end starter, and growing ✓ Simplifies exploration ✓ Significant underground upside potential ✓ Reduces de

  16. Slide 16: Case Study: Foran Mining

    Case Study: Foran Mining Traded at ‘option value’ at market nadir. Outsized returns without a “new discovery”. For personal use only 58x Peak-to-Trough C$/share C$0.08/sh Equity Return C$4.61/sh US$/lb Cu $5.00 C$10.5m C$1.8B 5.00 $4.00 4.40 $3.00 3.80 $2.00 3.20 $1.00 2.60 Foran (TSX:FOM) Cu Price

  17. Slide 17: BAGB

    For personal use only BAGB • Belleterre-Angliers Greenstone Belt • Exploration stage • Advanced prospects with bonanza grades evident LORRAINE • Targeting anomalies of scale 17

  18. Slide 18: BAGB: Ultra high-grade mineralisation defined

    BAGB Ultra high-grade mineralisation defined For personal use only • 157km2 greenstone belt package with prospective suite of gabbroic intrusives in southern Quebec • Multiple deposits with bonanza grade Cu-Ni-PGE and Au intersections • Historical mining of one deposit • BUT, previous operators kept

  19. Slide 19: BAGB: Midrim and Alotta

    BAGB Midrim and Alotta – smoke from a very a big fire? For personal use only Alotta 9.2m @ 2.6% Ni, 2.8% Cu, 3.6 g/t 3E from 85.2m in ZA-18-08 Midrim 4.3m @ 6.5% Ni, 5.2% Cu, 7.2g/t 3E from 57.2m in MR-00-05 9.4m @ 3.5% Ni, 4.3% Cu, 4.6 g/t 3E from 56.6m in MR-17-01 • Mafic contact deposit model • E

  20. Slide 20: Consistent News-Flow

    Consistent News-Flow To continue through 2025 For personal use only Building Resources • Step-out results building tonnes. Assays pending. 0-6 • Infill building grade and increasing confidence months • Resource update Expanding Footprint • Drilling EM targets showing growth potential ` 3-9 • BAGB ta

  21. Slide 21: Investment Highlights

    Investment Highlights For personal use only Copper Value is Exploration Premier Near term leverage underpinned engine jurisdiction re-rate catalysts Clear deficits Large Cu and Ni Clear path to Quebec is skills and HL drilling, resource forecast, driven by endowment in improve and grow infrastructur

  22. Slide 22: Appendix

    For personal use only Appendix

  23. Slide 23: Corporate Overview

    Corporate Overview Committed board, management and shareholders Vol (m) For personal use only Ivan Fairhall, Managing Director $0.03 10 ▪ Chartered engineer, finance and capital markets professional with 20 years of mining experience. 9 ▪ Previously CEO of a TSX listed Mawson Gold, which spun out So

  24. Slide 24: Geological Setting – Horden Lake Deposit

    Geological Setting – Horden Lake Deposit Strong structural control for mineralisation For personal use only ✓ Mineralisation style supports good potential for resource extension ✓ Magmatic sulphide deposit associated with mafic and ultramafic rocks ✓ Mineralisation occurs along the contact of the ga

  25. Slide 25: 2022 JORC Compliant Minerals Resource Estimate

    Appendix 2022 JORC Compliant Minerals Resource Estimate For personal use only Grade Contained Metal Category Tonnes CuEq (%) Cu (%) Ni (%) Au (g/t) Pd (g/t) CuEq (kt) Cu (kt) Ni (kt) Au (koz) Pd (koz) Indicated 15.2 1.50 0.77 0.20 0.13 0.19 228.6 117.6 30.5 59.4 91.3 Inferred 12.5 1.47 0.67 0.25 0.0

  26. Slide 26: Supporting information: Foran Mining

    Appendix Supporting information For personal use only Foran Mining 2019 Resource - Filed 10 July 2019 2021 Resource - Filed 25 October 2021 Resource Mt Cu (%) Zn (%) Pb (%) Au (g/t) Ag (g/t) Resource Mt Cu (%) Zn (%) Pb (%) Au (g/t) Ag (g/t) M&I 22.3 1.2 3 0.2 0.44 17 M&I 39 1.2 2.2 0.15 0.4 14 Infe