Slide 4: Production, sales and financing update
Increasing Overall Resilience of the Business PRODUCTION: • 2Q25 Production Volumes Expected to Meet Target ▪ New Crusher Plant Installed with On-site Capacity of 7,500t/day SALES: • Lower Spot Prices May Result in Temporary Inventory Buildup in Q2 • Sales Expected to Recover in 3Q-4Q 1Q25 AISC at $
Slide 5: Sigma Lithium Delivered on the Challenge
Sigma Lithium Delivered on the Challenge Achieved Low-Cost Production, Without Sacrificing Sustainability and Ethical Sourcing Hard-Rock C3 cost-curve 1,400 1,200 CIF China U$/t Cost of Lithium Concentrate 1,000 800 600 400 200 - - 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500 5,000 5,500 Spod
Slide 6: Production Levels Increase of 28% YoY Achieved in 1Q25
Production Levels Increase of 28% YoY Achieved in 1Q25 Reinforces FY2025 Production Guidance Production & Sales Volumes Unlocking Financing 100% Production Not Tied to Production Sales Annualized Production Offtakes = 308kt Potential Cash Generation From Prepayments, Lower Cost of Debt 273kt 270kt 3
Slide 7: Commercial
Commercial
Slide 8: 12-Month Lithium Price Overview
12-Month Lithium Price Overview Spodumene 6% of Li2O, Asia, $/Tonne $1,400 $1,200 $1,000 $800 $600 $400 $200 $- Jun-24 Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25
Slide 9: Race to the Bottom…ZERO Ethical Standards
Race to the Bottom…ZERO Ethical Standards page 9
Slide 10: Prepayment Offtake Options
Prepayment Offtake Options Potential Value of Agreement: Counterparties: Trading & Corporate Quantity Duration Counterparty to Secure Prepayment 1. 40kt per company 3 years: 1. Western Trading Companies $50 million each 2. 40kt per company 2H25 to 2H28 3 years: 2. Asian Trading Companies 80kt $100 m
Slide 11: Decrease in Trade Finance Short-Term Debt
Decrease in Trade Finance Short-Term Debt As a Result of Continuous Working Capital Efficiency (1) Decreased Short-Term Trade Finance Facilities Decrease in Interest per Ton in 1Q25 $ 120 25.00% $ 2,500 $ 80 Interest (Accrued) and Average Interest Rates (US$ M) -42% Export Prepayment Trade Finance B
Slide 12: Further Decreased Interest Expenses Towards Achieving 2025 Targets
Further Decreased Interest Expenses Towards Achieving 2025 Targets Production Expansion to be Financed with Lower-Cost Subsidized Debt from BNDES Financial Guidance Statements Provided Reported Guidance Provided FY 2025 E FY 2026 E Short-Term Debt $1 20/t Long-Term Debt $ 200,000 Interest/ton Non-Di
Slide 13: Update on Expansion
Update on Expansion
Slide 14: Existing Infrastructure Will Expedite Construction of Plant 2
Existing Infrastructure and Mining Operations of Plant 1 will Expedite the Construction of Plant 2 Construction Progress P1 P2 Water Pipelines In Place Power Substation In Place Moving High Voltage Power Lines In Place Sewage Water Treatment Plant In Place Greentech Plant Support Infrastructure In P
Slide 15: Plant 2 Fully Financed by BNDES Loan
Plant 2 Fully Financed by BNDES Loan Highly Attractive Development Loan for Project Financing Financial Commitment: BRL 487 mm First loan disbursement pending bank guarantee. Will reimburse capex spent 99% Capex since 1Q24 Terms: Maturity: 16 Years Grace Period: 18 Months % Fixed Interest Rate: USD
Slide 16: Sigma Built a Resilient Company Thriving Throughout Lithium Price Cycles
Sigma Built a Resilient Company Thriving Throughout Lithium Price Cycles Large Scale Production 1. Speed of Execution 2. Low Capex: Developed Mining & Industrialized State in Brazil 3. Low-Cost Operating Country Traceability: Zero Accidents & Low Production Cost Highest Environmental Standards
Slide 17: Q&A
Q&A
Slide 18: Social Development Engine of the Entire Region
Social Development Engine of the Entire Region 21,000 1,700 18,000 Job Openings Direct Jobs Indirect Jobs (Microcredit & Small Scale Agriculture) 18,000 85% 50% People With Access to Regional Workforce Economically Active Drinking Water Population Beenfited 200 6.8% 3 Million NEW Construction Jobs G
Slide 19: We Successfully Solved The Puzzle of Competitive Advantage
We Successfully Solved The “Puzzle of Competitive Advantage” Scale + Low Costs Traceability + Low Costs Scale + Traceability = = = Price Cycle Resilience Competitive Sells to Largest Supply Advantage to Africa Chains Low Construction Capex Management Speed of Location in Developed = Execution Mining
Slide 20: Among the Lowest Capex-Intensive Projects in the World
Among the Lowest Capex-Intensive Projects in the World Sigma is the incremental supplier to meet growing demand Project Capex Intensity Comparison Sigma’s P2 Leads in Capex Intensity Bubble size = capex efficiency ratio (USD millions) / production capacity Capex intensity ratio = capex (USD millions
Slide 21: Operational Excellence Driven by a Culture of Safety and Processes
Operational Excellence Driven by a Culture of Safety and Processes One of ICMM’s Best Safety Records ▪ Strengthening Health, Safety & Environment Strategy ▪ Employee Engagement & Safety Leadership ▪ Workshops & Safety Culture Development 700+ Consecutive Days Without a Lost Time Injury (LTI) 1.23 (1