  1. Slide 1: Q3 FY25 Quarterly Results

    ASX | TSX : WGX For personal use only Westgold Resources Limited westgold.com.au Q3 FY25 Quarterly Results

  2. Slide 2: Important Notices and Disclaimer

    Important Notices and Disclaimer Investor Presentation This presentation is in summary form and does not purpose to be exhaustive. Westgold makes no representation or warranty (either expressed or implied) as to the accuracy, reliability or completeness of the information in this presentation. Westg

  3. Slide 3: Important Notices and Disclaimer

    Important Notices and Disclaimer Ore Reserves and Mineral Resources JORC CODE This presentation refers to Westgold having a combined Ore Reserve and Mineral Resource estimate of 14.1Moz and 3.6Moz It is a requirement of the ASX Listing Rules that the reporting of Ore Reserves and Mineral Resources i

  4. Slide 4: Q3 FY25 Highlights

    Q3 FY25 Highlights  80,107oz produced @ AISC of $2,829/oz  78,398oz sold at an average price of For personal use only A$4,630/oz, generating revenue of A$363M  Record operational cash build of $107M before investing $74M in growth and exploration  $232M in closing cash, bullion and liquid invest

  5. Slide 5: Sustained improvement in safety – 8% reduction in TRIFR

    Sustained improvement in safety – 8% reduction in TRIFR 12 Month rolling Injury Frequency Rate 20 18.44 (injuries/million hours worked) 15 For personal use only 10 6.85 6.27 5 0 Q1 FY23 Q2 FY23 Q3 FY23 Q4 FY23 Q1 FY24 Q2 FY24 Q3 FY24 Q4 FY24 Q1 FY25 Q2 FY25 Q3 FY25 5 55

  6. Slide 6: Rebuilding cash – record cash growth in Q3 FY25

    Rebuilding cash – record cash growth in Q3 FY25 Proven recipe in the Murchison being applied to Southern Goldfields Quarterly cash, bullion and liquid investments position ($M) Two quarters to Two quarters to stabilise the stabilise the Record quarterly Six quarters of cash, bullion & merged For per

  7. Slide 7: Production & Costs

    Production & Costs 77,369 80,886 80,107 Gold production (oz) Southern Gold Fields 24,480 34,425  Production consistent Q on Q 52,100 52,795 37,201 Murchison  Temporary increase in AISC due to 52,889 46,461 increased stockpile consumption, 42,906 For personal use only haulage and sustaining capital

  8. Slide 8: FY25 Guidance maintained

    FY25 Guidance maintained Production guidance to be achieved with increased Q4 FY25 output Q3 FY25 YTD FY25 FY25 Guidance Actual Actual For personal use only Production (oz) 330,000 – 350,000 80,107 238,362 AISC (A$/oz) 2,400 – 2,600 2,829 2,659 Growth Capital (A$M) 200 46 160 Exploration (A$M) 50 11

  9. Slide 9: Operational Results

    For personal use only Operational Results Record cash generated from operations 9

  10. Slide 10: Consistent group gold production Q on Q

    Consistent group gold production Q on Q Higher mined grades offset by lower mined tonnes Ore Mined (Mt) Mined Grade (g/t) Ore Processed (Mt) Milled Grade (g/t) Gold Produced (koz) 1.30 2.1 80.1 1.12 1.00 2.7 2.4 2.5 1.29 1.34 2.1 2.1 2.1 77.4 80.9 For personal use only 0.94 2.3 0.86 52.8 0.64 Q4 Q1

  11. Slide 11: Murchison

    Murchison  Lower gold production due to lower output Change in Mill gold production quarter on quarter (oz) from Fortnum 46,461  Lower outputs from Big Bell, offset by (797) 253 increased grade at Fender For personal use only  Bluebird-South Junction tonnage up Q on Q but offset by lower grade (3

  12. Slide 12: Substantial opportunity to leverage milling capacity

    Substantial opportunity to leverage milling capacity Annualised Mill throughput rates achieved in Q3  Bluebird-South Junction achieved 450ktpa Capacity: 1,800 ktpa annualised in Q3  Ground conditions in the footwall have reduced footwall development rates, limiting access to For personal use only

  13. Slide 13: Southern Goldfields

    Southern Goldfields Change in Mill gold production quarter on quarter (oz)  Beta Hunt & Two Boys head grade improvement drives Q on Q production increase at 37,201 Higginsville For personal use only  Lakewood performed to expectation prior to shutdown ahead of divestment 4,275 34,425  Total AISC

  14. Slide 14: Beta Hunt – expansion to >2Mtpa

    Beta Hunt – expansion to >2Mtpa Infrastructure upgrades progressing  Primary vent upgrades  Adding two new primary fans to almost double For personal use only primary vent capacity  Completion due in June 2025  Clean water supply  Construction of pipework and pumping from Formidable Pit well pr

  15. Slide 15: Balancing mine and mill capacity, reducing costs

    Balancing mine and mill capacity, reducing costs Stockpiles used ~30% Higginsville capacity - only produced 10% of the gold Annualised Mill throughput rates Gold production in Q3 by ore  On strategy sale of high-cost achieved in Q3 source & mill (oz) Lakewood mill for $70M cash and For personal use

  16. Slide 16: Projects & Resource Development

    For personal use only Projects & Resource Development Continued focus on growth 16

  17. Slide 17: Great Fingall production in sight

    Great Fingall production in sight  Decline development progressing  Primary ventilation installation completed in For personal use only Q3 FY25  Dewatering of historical workings continued  First ore from virgin stopes expected in H1 FY26  Fingall Flats early mining opportunity progressed with

  18. Slide 18: Murchison resource development highlights

    Murchison resource development highlights  Nightfall lode in Starlight UG  25m at 17.66g/t Au from 169m in NF1090GC14  15.47m at 23.53g/t Au from 82m in NF1120GC100 For personal use only  9.47m at 25.56g/t Au from 68m in NF1120GC89  Bluebird-South Junction  8.11m at 12.66 g/t Au from 166m in 2

  19. Slide 19: Southern Goldfields resource development highlights

    Southern Goldfields resource development highlights  Fletcher resource definition program nearing completion  45.50m at 2.23g/t Au from 746m in WF440DD-37AE For personal use only  63.00m at 3.62g/t Au from 324m in WF490DD-51AE  Fletcher Mineral Resource estimate on track for end of FY25  Wester

  20. Slide 20: Financial results

    For personal use only Financial results Balance sheet supports growth strategy 20

  21. Slide 21: Record quarterly cash generation from operations

    Record quarterly cash generation from operations Higher mined grades offset by lower mined tonnes Gold sold (koz) Realised gold price (g/t) AISC ($/oz) Net mine cash flow Closing Cash, Bullion & ($M) Investments ($M) 4,630 2,829 87 263 86.9 78.4 2,703 232 For personal use only 4,066 2,422 72.2 3,723

  22. Slide 22: Record quarterly operational cash build

    Record quarterly operational cash build Cash, Bullion, and Liquid Investments Movement (A$M) (14)  $63M growth capital 6 (31) cash expenditure 73 (11) 232 For personal use only (31) 25  Paying down working capital balance 28 (32) (3) 179 85 25 152 $107M cash build (11) 157  $25M of the $70M in 17

  23. Slide 23: Monthly cost performance

    Monthly cost performance 120 4,000 110 Karora Transaction 3,148 3,500 2,796 2,791 2,754 3,000 2,619 2,490 2,643 2,542 2,561 100 2,309 2,209 2,342 2,370 2,198 2,622 2,500 For personal use only 1,983 90 2,230 2,000 1,842 80 80 75 75 76 74 0 70 69 71 70 -500 60 -1,000 48 50 -1,500 50 45 42 43 40 -2,000

  24. Slide 24: $32M of $49M targeted annual synergies realised – so far

    $32M of $49M targeted annual synergies realised – so far Work ongoing with further opportunities identified Realised savings  Further opportunities identified in Q4 Pre-tax Synergies For personal use only ($M/annum)  Accommodation services Corporate Management 21  Flights  Supply chain commoditi

  25. Slide 25: What's ahead?

    For personal use only What's ahead? 25

  26. Slide 26: Focus is the two growth engines – and cost reduction

    Focus is the two growth engines – and cost reduction Murchison Southern Goldfields Portfolio For personal use only Bluebird-South Junction Beta Hunt Strategic Review  Increase mine scale to 1.2Mtpa  Expansion to >2Mtpa  Rank assets across 3,200km2 land  Reduce haulage  Define Fletcher Zone hold

  27. Slide 27: Westgold – the value proposition

    Westgold – the value proposition Top 5 ASX / Top Financial Unhedged 10 TSX Producer Strength For personal use only One of Australia’s Robust balance sheet $2.9B market largest fully unhedged with $300M debt capitalisation[1] gold producers facility Investing in Shareholder Portfolio has Diversificat

  28. Slide 28: Thank You

    Investor Relations & Media For personal use only Kasun Liyanaarachchi Group Manager Investor Relations & Communications Kasun.Liyanaarachchi@westgold.com.au +61 458 564 483 Thank You www.westgold.com.au 28

  29. Slide 29: Mineral Resource Statement: Operating Mines

    Mineral Resource Statement: Operating Mines At 30 June 2024 [1],[2] Murchison Gold Operations (Rounded for reporting) Measured Indicated Measured and Indicated Inferred Total Tonnes Ounces Tonnes Ounces Tonnes Ounces Tonnes Ounces Tonnes Ounces Project Grade Grade Grade Grade Grade ('000s) Au ('000s

  30. Slide 30: Mineral Resource Statement: Non-Operating Projects

    Mineral Resource Statement: Non-Operating Projects At 30 June 2024 [1],[2] Murchison Gold Operations (Rounded for reporting) Measured Indicated Measured and Indicated Inferred Total Tonnes Ounces Tonnes Ounces Tonnes Ounces Tonnes Ounces Tonnes Ounces Project Grade Grade Grade Grade Grade ('000s) Au

  31. Slide 31: Ore Reserves Statement: Operating Mines

    Ore Reserves Statement: Operating Mines At 30 June 2024 [1],[2] Murchison Gold Operations (Rounded for reporting) Proven Probable Total Project Tonnes ('000s) Grade Ounces Au ('000s) Tonnes ('000s) Grade Ounces Au ('000s) Tonnes ('000s) Grade Ounces Au ('000s) Big Bell UG 9,808 1.48 467 4,898 3.10 4

  32. Slide 32: Ore Reserves Statement: Non-Operating Projects

    Ore Reserves Statement: Non-Operating Projects At 30 June 2024 [1],[2] Murchison Gold Operations (Rounded for reporting) Proven Probable Total Project Tonnes ('000s) Grade Ounces Au ('000s) Tonnes ('000s) Grade Ounces Au ('000s) Tonnes ('000s) Grade Ounces Au ('000s) Big Bell District 0 0.00 0 59 2.

  33. Slide 33: Mineral Resource Updates

    Mineral Resource Updates Bluebird-South Junction MRE at end of Q1 FY25[1] Grade Tonnes Ounces Classification (g/t Au) Measured 321,000 4.0 41,000 For personal use only Indicated 8,410,000 2.9 773,000 Inferred 6,238,000 2.8 556,000 Total 14,969,000 2.9 1,370,000 Starlight Open Pit & Underground MRE a

  34. Slide 34: Ore Reserves Update: Bluebird-South Junction

    Ore Reserves Update: Bluebird-South Junction At end of Q1 FY25 [1] Grade Classification Tonnes Ounces For personal use only (g/t Au) Proven 105,000 4.0 13,600 Probable 7,141,000 2.4 559,000 Total 7,246,000 2.5 573,000 1. See Westgold ASX Announcement 4 December 2024 – Westgold Doubles Bluebird - Sou