K-electric — Investor Presentation (April 2016)

22 slides from K-electric's investor presentation, April 2016

  1. Slide 1: KE Presentation April 2016

    KE Presentation April 2016

  2. Slide 2: Pakistan Country Overview

    Pakistan Country Overview Country Overview Significant Progress in Recent Months Demographics (mn) FY15 China Population 189 1  Low oil price levels are expected to save Pakistan – 15 to 64 years 63% US$5-6bn in oil imports annually Improving Labor Force 63  Current account balance (as % of GDP) i

  3. Slide 3: Pakistan Power Sector Structure

    Pakistan Power Sector Structure Government of Pakistan has restructured the sector through privatization and unbundling. 9 distribution companies and 4 generation companies are still in the privatization pipeline Key Highlights Current Electricity Sector Overview  Historically the power sector cons

  4. Slide 4: Pakistan Power Sector: Need for Investment

    Pakistan Power Sector: Need for Investment Pakistan is a power deficit market which requires significant investment to meet growing demand. An Acute Energy Shortage … … Fuelled by an Expensive Generation Mix … Chronic underutilisation of capacity leading to energy deficit of more than 6GW Pakistan’s

  5. Slide 5: Pakistan Power Sector: Reform Underway

    Pakistan Power Sector: Reform Underway Circular debt has historically clogged capacity and stifled liquidity in the power sector; given recent oil price decline, rate of circular debt is expected to decline significantly, which should help the economy. Moreover, government has also undertaken measur

  6. Slide 6: KE Overview

    KE Overview KE Background  Incorporated in 1913, K-Electric (“KE” or “Company”) (formerly known as Karachi Electric Supply Company) is a publicly listed fully integrated power utility involved in generation, transmission and distribution  KE was privatized in 2005  Abraaj acquired a controlling s

  7. Slide 7: KE: Key Value Drivers

    KE: Key Value Drivers 7 1 Commercial Proposition FavorableGovernment GovernmentPolicy Policy Strategic Importance of Favorable Karachi 6 2 Strong & Credible Management Experienced Business StrategicOverview Importance Management 5 3 Opportunity to Further Enhance Opportunity to Further Operational E

  8. Slide 8: Strategic Importance of Karachi

    1 Strategic Importance of Karachi The city of Karachi is essential to Pakistan’s economy and drives much of the country’s economic growth. As the city’s sole electricity provider, KE is of strategic importance to the municipality and the country Karachi’s Importance to Pakistan Strategic Location 

  9. Slide 9: Business Overview

    2 Business Overview KE is the only remaining vertically integrated power utility in Pakistan with exclusive licensing rights for Karachi and a customer base of 2.5mn Presence Across the Entire Power Value Chain Generation Transmission Distribution All power units and grid stations are monitored by a

  10. Slide 10: Overview of Generation Capacity

    2 Overview of Generation Capacity Total installed capacity of over 2,247 MW with nearly 45% of KE’s capacity being less than 6 years old 1 Bin Qasim Power Station 1 (BQPS 1) 2 Korangi CCPP Capacity 1,260 MW (6 units)(1) Capacity 247 MW (4 units, 2ST) GDC 920 MW (5 units)(2) GDC 215 MW Year 1983 – 19

  11. Slide 11: Operational Outperformance – Generation

    3 Operational Outperformance – Generation Installed generation capacity has been enhanced by over 1,000 MW and overall efficiency has improved from 30.4% in FY 09 to 37.3% in 1H16 – significantly contributing to the financial turnaround and outperformance Capacity Enhancement KE Capacity (MW)  c. 1

  12. Slide 12: Operational Outperformance – Transmission

    3 Operational Outperformance – Transmission Increased reliability in transmission network through the addition of 12 new grid stations and 63km of new EHT (1) lines, while also rehabilitating 189km of old EHT line, resulting in an increased transmission capacity of 768 MVA Power Transformers Reliabi

  13. Slide 13: Operational Outperformance – Distribution

    3 Operational Outperformance – Distribution FY 15 T&D losses stood at 23.7%, representing a c. 12.2 percentage point decline since 2009 Key Initiatives T&D Losses (%) – Rolling Average  Organization restructured to deliver business objectives  Built modern customer services centres and Re-organiza

  14. Slide 14: Operational Outperformance – HR Restructuring

    3 Operational Outperformance – HR Restructuring Enhanced workforce effectiveness through creation of a performance-driven culture and workforce optimization (reduction of head count by approximately 7,000) KE Initiatives: Rightsizing  Accountability  Management Change   Promotion of 3,500 Non-Ma

  15. Slide 15: Robust Financial Performance: Underpinned by a Multi Year Tariff Structure

    Robust Financial Performance: Underpinned by a 4 Multi Year Tariff Structure The current MYT structure is a performance based / efficiency driven tariff whereby KE can increase its returns by beating inherent efficiency benchmarks incorporated into the tariff structure Background and Components of C

  16. Slide 16: Robust Financial Performance

    4 Robust Financial Performance KE revenue increased at a CAGR of 9.6% between FY09 and FY15 on the back of decreasing T&D losses, increasing average revenue per unit billed and decreasing fuel price environment. KE achieved positive operating profitability in FY11 and net profitability in FY12 Reven

  17. Slide 17: Robust Financial Performance (Cont’d)

    4 Robust Financial Performance (Cont’d) Significant capital expenditures over the last 6 years have allowed KE to achieve its objective to increase generation capacity and improve T&D infrastructure. Return to profitability has accelerated KE’s deleveraging pace Total Capex (US$mn) Comments Total of

  18. Slide 18: Opportunity to Further Enhance Operational Efficiency

    5 Opportunity to Further Enhance Operational Efficiency Key Transmission & Distribution Initiatives 1  1,000 MVA transmission enhancement and rehabilitation project. Contracts finalized with Siemens Germany and Shanghai Electric, China. Estimated Cost of the project US$ 400 million 1,000 MVA transm

  19. Slide 19: Experienced Management

    6 Experienced Management Highly experienced team with deep industry knowledge and a strong track record Waqar Siddique Tayyab Tareen Dale Sinkler Syed Moonis A. Alvi Eram Hasan Chairman and Chief Executive Officer Chief G&T Officer Chief Financial Officer Chief Supply Chain Officer Director KE Board

  20. Slide 20: Favorable Government Policy

    7 Favorable Government Policy The GoP has set-forth an investor friendly policy to “build a power generation capacity that can meet Pakistan’s energy needs in a sustainable manner” Key Incentives to Invest in Pakistan’s Power Sector One-window  The Private Power & Infrastructure Board (“PPIB”)  Ty

  21. Slide 21: Recognition of KE’s Turnaround Success

    Recognition of KE’s Turnaround Success KE’s transformational turnaround success has been recognized by local and international institutions 2016: Best Presented Annual Report Award 2014 by the South Asian Federation of Accountants (SAFA) 2012 & 2013: Harvard Business School Case Studies Published 2

  22. Slide 22: Disclaimer

    Disclaimer The information contained in this presentation is given without to a potential investment in the regions described. This any liability whatsoever to K-Electric Ltd or their respective presentation does not constitute a recommendation to invest in members, directors, officers or employees