  1. Slide 1: Coopers Gap Wind Farm

    Coopers Gap Wind Farm Community Meeting No. 28 30 August 2018

  2. Slide 2: Project Update

    Project Update Tim Knill, AGL Coopers Gap Construction Manager

  3. Slide 3: Project Update

    Project Update Tim Knill Coopers Gap Wind Farm | 30 August 2018 3

  4. Slide 4: Construction update video

    Construction update video Coopers Gap Wind Farm | 30 August 2018 4

  5. Slide 5: Project Update: Transformer Delivery

    Project Update Transformer Delivery Coopers Gap Wind Farm | 30 August 2018 5

  6. Slide 6: Transformer Delivery

    Transformer Delivery Coopers Gap Wind Farm | 30 August 2018 6

  7. Slide 7: Transformer Delivery

    Transformer Delivery Coopers Gap Wind Farm | 30 August 2018 7

  8. Slide 8: Solar Program

    Solar Program Tim Knill, AGL Coopers Gap Construction Manager

  9. Slide 9: Construction Update

    Construction Update Andrew O’Connor, GE-CATCON Site Manager

  10. Slide 10: WTG Components

    WTG Components First Hub delivered to site The Coopers Gap Wind Farm is owned by the Powering Australian Renewables Fund (PARF). Image courtesy of PARF. Coopers Gap Wind Farm | 30 August 2018 10

  11. Slide 11: WTG Components

    WTG Components Delivery of first tower section Coopers Gap Wind Farm | 30 August 2018 11

  12. Slide 12: WTG Components

    WTG Components TBR delivered to site and placed on foundation Coopers Gap Wind Farm | 30 August 2018 12

  13. Slide 13: Civil Works Continue

    Civil Works Continue Footing preparation Coopers Gap Wind Farm | 30 August 2018 13

  14. Slide 14: Cable trenching/laying machine

    Cable trenching/laying machine Coopers Gap Wind Farm | 30 August 2018 14

  15. Slide 15: Tool Box Meetings

    Tool Box Meetings Guest safety speaker James Wood Coopers Gap Wind Farm | 30 August 2018 15

  16. Slide 16: Community Update

    Community Update Michael Yeo, AECOM Site Representative Rob Hart, Chair

  17. Slide 17: Traffic conditions

    Traffic conditions • More oversized deliveries will be happening in the coming months Please stay patient Only overtake when its safe to do so For traffic information, please go to TMR website • Most components will arrive on site before dawn or between 1pm to 4pm Coopers Gap Wind Farm | 30 August 2

  18. Slide 18: Community Fund

    Community Fund Tim Knill, Construction Project Manager

  19. Slide 19: Community Fund

    Community Fund Round 3 applications open Monday, 3rd September 2018 and close Friday, 28th September 2018 Application forms at: • Bell Bunya Community Centre • Jandowae Library and Civic Centre • Kumbia State School • www.agl.com.au/coopersgap Announcements in October Coopers Gap Wind Farm | 30 Augu

  20. Slide 20: Contact

    Contact Tim Knill Construction Project Manager (02) 9921 2276 tknill@agl.com.au