Slide 1: Stakeholder Consultation Meeting
Stakeholder Consultation Meeting Oakdale West Estate December 2019 1
Slide 2: Overview
Overview • Welcome and Introductions • Project Outcomes – Previous Month • Project Program • Safety Update • Environmental Performance Update • Community Interactions Update • Proposed Modifications & Stage 2 • Stakeholder Feedback & Questions 2
Slide 3: Welcome and Introductions
Welcome and Introductions Project Team: Organisation Goodman AT&L Burton Robson Civil SLR Ersed Contractors Projects Consulting Role Proponent Project Manager & Oakdale West – Western North Stakeholder Environmental Contract Stage 1 Internal South Link Engagement Representative Superintendents Infra
Slide 4: Project Outcomes – Previous Month
Project Outcomes – Previous Month • Site establishment commenced 5 December 2019 • Pre construction activities underway to enable construction to commence in the new year. 4
Slide 5: Project Program
Project Program Oakdale West Estate – Burton Contractors – Site establishment work occurring, with mobilisation of plant to site out of hours to limit impacts on the surrounds – December 2019 – Fencing areas of biodiversity and services to avoid encroachment impacts – December 2019 – Demolition and
Slide 6: Site Plan
Site Plan global environmental and advisory solutions S LR®
Slide 7: Master Plan
SSDA Estate Masterplan 7 = , WY) Y4 a Master Plan global environmental and advisory solutions
Slide 8: Safety
Safety • No safety incidents • Due to current environmental conditions caused by smoke haze, the health and safety of workers is being monitored closely. • The previous structures on site contained low levels of asbestos, which is in the process of being removed in accordance with EPA and Council gu
Slide 9: Environmental Performance (Dec 2019)
Environmental Performance (Dec 2019) 1. No incidents or Non- Compliances reported in preceding month 2. Environmental Management Activities in preparation for works • Compliance Monitoring Program submitted (Per Condition D 139) • CEMP and Sub Plans submitted to DPIE for approval (15/11/19 ) & with
Slide 10: Community Interactions
Community Interactions 1. No complaints received during the preceding month 2. Dilapidation Assessments undertaken at all properties required by the development consent 3. Notification of Stage 2 SSD and Modifications 1, 2 and 3 to SSD 7348 4. Notification of works commencing to stakeholders issued
Slide 11: Stage 2 SSD and Proposed Modifications
Stage 2 SSD and Proposed Modifications • SSD7348 included speculative warehousing units approved under SSD7348 in Precinct 1 (1A, 1B, 1C) • Two major tenants subsequently secured for the Estate, one for a warehouse in Precinct 1, the other in Precinct 2 • Modifications proposed to the original SSD73
Slide 12: Modifications – Precinct 1
Modifications – Precinct 1 12
Slide 13: Modifications – Precinct 2
Modifications – Precinct 2 13
Slide 14: Stakeholder Feedback & Questions
Stakeholder Feedback & Questions 14