Bci Minerals Ltd · ASX:BCI

Bci Minerals — BC Iron — Non-Deal Roadshow (October 2010)

27 slides from Bci Minerals's roadshow presentation, Oct 25, 2010

  1. Slide 1: ASX cover letter for East Coast road show presentation

    25 October 2010 For personal use only The Manager Company Announcements Office Australian Securities Exchange BC Iron Limited (ASX:BCI) Please find attached a copy of the presentation that BC Iron will be presenting to investors during its East Coast road show beginning on Wednesday, 27 October 2010

  2. Slide 2: BC Iron Limited Project Update

    BC IRON LIMITED Project Update For personal use only October 2010 Mike Young - MD Morgan Ball - CFO

  3. Slide 3: A Unique Investment Opportunity

    For personal use only A UNIQUE INVESTMENT OPPORTUNITY Points of difference:  Production & revenue imminent  Mining commenced  First ore on ship in Dec 2010  Start up at 3Mtpa moving to 5Mtpa  1Mt shipped by 30 June 2011  Infrastructure secured – rail and port allocation  Nullagine Joint Ventu

  4. Slide 4: History of BC Iron

    For personal use only HISTORY OF BC IRON Staying Focused  Dec 2006 BC Iron lists on Australian Securities Exchange (ASX)  May 2007 Resource drilling identifies iron ore at Nullagine  Jul 2007 Memo of understanding with FMG  2007-09 Drilling to Feasibility & Ore Reserves  Jul 2009 Capital raisin

  5. Slide 5: BC Iron Limited – Company Snapshot: Board of Directors

    For personal use only BC IRON LIMITED – COMPANY SNAPSHOT Board of Directors BC Iron at the Nullagine JV The ore stockpile from the Trial Mining carried out in 2H 2009 can be seen in the background. Trial mining was a main recommendation of the Feasibility Study and served to de-risk the project by c

  6. Slide 6: BC Iron Limited – Company Snapshot: Senior Management Team

    For personal use only BC IRON LIMITED – COMPANY SNAPSHOT Senior Management Team Blair Duncan - Chief Operations Officer Morgan Ball - Chief Financial Officer John McCarthy – Resident Manager, NIOJV Greg Hudson - Chief Geologist Gerry Bradley – Sustainability Manager Donna Neill – HR and OH&S The BC

  7. Slide 7: Iron Ore Joint Venture – Pilbara Projects

    For personal use only NULLAGINE IRON ORE JOINT VENTURE BC Iron Limited – Pilbara Projects  Bungaroo near RIO Tinto’s Bungaroo Creek & IOH Buckland Hills  Exploration in 2011 field season Nullagine Project  Directly north of FMG Chichester Operations  Ore Reserves of 36Mt @ 57% Fe (65% CaFe)  Ta

  8. Slide 8: Nullagine Iron Ore Joint Venture

    For personal use only NULLAGINE IRON ORE PROJECT Nullagine Iron Ore Joint Venture  Joint Venture with FMG (50:50)  BC Iron operators of the Project Bonnie Creek  BCI manages all facets of mining and trucking Shaw River  BCI contracts TPI to provide rail & port services on a fixed price per tonne

  9. Slide 9: Iron Ore Project – Project Metrics

    For personal use only NULLAGINE IRON ORE PROJECT Project Metrics (BCI 50%)  Production: 1mt shipped in FY10/11 3mt shipped in FY11/12  Mine Life: 8.5 years + growth  Mining: Wirtgen surface miners & front-end loaders  Crush/screen: Striker 2o and 3o only  Haulage: 361t Power Trans road haul via

  10. Slide 10: Iron Ore Project – Production Profile

    For personal use only NULLAGINE IRON ORE PROJECT Production Profile NIOJV Production Profile  1Mtpa shipped by 30 June 2011 5 4  3Mtpa to 5Mtpa when FMG expands its Chichester Millions Hub – expected by 2H 2012 3 2 TPA  20Mt committed to Henghou Industries (HK) 1 West Australian CID 0 June 11 Jun

  11. Slide 11: Nullagine Iron Ore Joint Venture – Project Schedule

    For personal use only NULLAGINE IRON ORE PROJECT Nullagine Iron Ore Joint Venture – Project Schedule Construction & mining schedule as of October 22 2010 Schedule is general in nature and changes may occur 10

  12. Slide 12: Mine to Market

    For personal use only NULLAGINE JV – MINE TO MARKET •Wirtgen 2500SM Surface Miner x 2 •CAT 777D Dump Trucks x 3 •CAT 992 FEL’s x 2 Mining •Striker Crushing & Screening Plant •TL 2000 Apron Feeder •Three stage screening plant •CM 500 Cone Crushers x 2 •Sampling Station •600 tonnes per hour Crushing &

  13. Slide 13: Mine to Mill

    For personal use only NULLAGINE JV – MINE TO MILL

  14. Slide 14: Iron Ore Project – Geology

    For personal use only NULLAGINE IRON ORE PROJECT – GEOLOGY 801,000E 802,000E 803,000E 804,000E 805,000E 7,562,000N 7,561,000N Scale 500 m Outcamp-Warrigal deposit  Outcropping mesa (Spanish for ‘table’)  Above water table  No pit – mining off the top of mesa 13

  15. Slide 15: Outcamp

    For personal use only NULLAGINE JV – OUTCAMP

  16. Slide 16: Outcamp

    For personal use only NULLAGINE JV – OUTCAMP Initial Mining Area Bottom of Orebody Water Table  Shallow “pits” mainly above surrounding plains - mining ore from day 1  Above water table - lower environmental impact  Low OpEx - low strip ratio, use of surface miners, efficient crushing and screeni

  17. Slide 17: Reserves & Resources

    For personal use only NULLAGINE JV – RESERVES & RESOURCES June 2010 – Reserves and Resources Statement Probable Ore Reserves Pit Mt Fe% CaFe% SiO2% Al2O3% P% S% LOI1000 Outcamp 19.2 56.8 64.8 3.21 1.92 0.01 0.01 12.2 Warrigal 10.3 57.0 64.5 3.67 2.13 0.02 0.01 11.7 Coongan 6.0 57.0 65.1 2.52 1.82 0.

  18. Slide 18: Project Pipeline

    For personal use only PROJECT PIPELINE Targeted M & A  Experienced Pilbara iron ore junior  Use in-house experience and IP  Use developed relationships (FMG, Henghou) Commodity and geography  Realistic targeting of sufficient quantity, quality and technical & commercial thresholds  Active in bu

  19. Slide 19: BC Iron Limited – Catalysts

    For personal use only BC IRON LIMITED – CATALYSTS BCI is poised for value re-rating: Infrastructure solution secured Approvals from mine to port secured Key long-lead items ordered (Powertrans, Wirtgen SM) Mining commenced Q3 2010 Iron ore exports commence Q4 2010 Data: BCI and ASX Revenue str

  20. Slide 20: Mine to Mill

    For personal use only NULLAGINE JV – MINE TO MILL Project stockpile at Outcamp, looking south along haul road corridor

  21. Slide 21: Mine to Mill

    For personal use only NULLAGINE JV – MINE TO MILL Graders clearing on haul road alignment.

  22. Slide 22: Mine to Mill

    For personal use only NULLAGINE JV – MINE TO MILL Aerial view of Stage 1 haul road alignment clearing looking north towards Outcamp (right). Haul road alignment clearing (above).

  23. Slide 23: Mine to Mill

    For personal use only NULLAGINE JV – MINE TO MILL Aerial views of Stage 1 haul road alignment clearings.

  24. Slide 24: Mine to Mill

    For personal use only NULLAGINE JV – MINE TO MILL Aerial view looking northwest of Christmas Creek OPF rail loop. BC Iron haul road will enter from top right of photo.

  25. Slide 25: Mine to Mill

    For personal use only NULLAGINE JV – MINE TO MILL Aerial view looking southeast of Christmas Creek OPF rail loop. BC Iron stockyard area will be in the cleared area in the middle right of the photo.

  26. Slide 26: Mine to Mill

    For personal use only NULLAGINE JV – MINE TO MILL Aerial view of BC Iron first stage, 60-man camp. Expansion underway to final camp which will be 180-man.

  27. Slide 27: Supporting Statement

    For personal use only SUPPORTING STATEMENT This release may include forward-looking statements. These forward-looking statements are based on management’s expectations and beliefs concerning future events. Forward-looking statements are necessarily subject to risks, uncertainties and other factors,