  1. Slide 1: Thompson Falls Hydroelectric Project No. 1869 Proposed Study Plan Meeting

    Thompson Falls Hydroelectric Project No. 1869 Proposed Study Plan Meeting January 6, 2021

  2. Slide 2: Welcome

    Welcome Thompson Falls Hydroelectric Project Relicensing Proposed Study Plan Meeting

  3. Slide 3: Guidelines for Today's Zoom Meeting

    Guidelines for Today’s Zoom Meeting • Video and Audio: Keep OFF, unless you are speaking as a presenter or called on to ask a question. • Phone controls for participants – *6 – to toggle mute/unmute. • Asking a Question: During the Q&A – click on the “Chat” icon and type your question or click on th

  4. Slide 4: Schedule

    Schedule Daytime Meeting January 6, 2021 Start Time Topic Introduction and Zoom Tips, Overview of 9:00 AM the FERC Process 9:25 AM Operations Study 10:25 AM BREAK (10 minutes) Tailrace Fish Behavior and Hydraulic 10:35 AM Conditions Studies 11:35 AM Downstream Transport of Bull Trout Study 12:05 PM

  5. Slide 5: Introductions

    Introductions • Introductions • NorthWestern representatives and consultants representing engineering, operations, legal, and hydro license compliance (including biologists, water quality experts and cultural, land, and recreation specialists) • FERC representatives • We will be recording attendance

  6. Slide 6: Thompson Falls Hydroelectric Project

    Thompson Falls Hydroelectric Project

  7. Slide 7: Licensed by the Federal Energy Regulatory Commission (FERC)

    Licensed by the Federal Energy Regulatory Commission (FERC) 1938 – Original License 1979 – License was renewed for 40 years 1990 – Major Modification to the License for additional powerhouse 2025 – License expires

  8. Slide 8: ILP Process and Opportunity for Input

    ILP Process and Opportunity for Input Date Completed Relicensing Steps Jul 1, 2020 NorthWestern filed PAD/NOI Aug 28, 2020 FERC issued notice the relicensing is commencing and SD1 Oct 27, 2020 Comments on the PAD/SD1 and study requests were due (*) Dec 9, 2020 FERC issued SD2 Dec 11, 2020 NorthWeste

  9. Slide 9: ILP Process and Opportunity for Input

    ILP Process and Opportunity for Input Date Future Relicensing Steps Mar 11, 2021 Comments on the PSP are due to FERC Apr 12, 2021 NorthWestern files Revised Study Plan (RSP) Apr 27, 2021 Comments on the RSP due to FERC May 12, 2021 FERC Study Plan Determination (*) NorthWestern conducts first season

  10. Slide 10: NorthWestern Energy's Proposed Studies

    Study Plan Meeting Purpose NorthWestern Energy’s Proposed Studies Studies will provide the information on potential effects of the project which FERC needs to complete its Environmental Assessment and to make an informed decision on the License Application.

  11. Slide 11: Proposed Study 1 – Operations Study

    Proposed Study 1 – Operations Study

  12. Slide 12: Operations Study Background

    Proposed Study 1 – Operations Study Background • Flexible Capacity • Required to maintain grid stability by balancing electrical inputs and outputs on our system. • Load (consumption) changes throughout the day and seasons. • Generation changes dynamically due to intermittent resources and plant ava

  13. Slide 13: Variable Generation

    Proposed Study 1 – Operations Study Variable Generation

  14. Slide 14: Operations Study Goals

    Proposed Study 1 – Operations Study Study Goals Operations Study Goals 1. Validate and quantify flexible capacity capability and benefits of the plant under multiple operational scenarios. 2. Evaluate the effects of flexible capacity operations and possible impacts on project resources.

  15. Slide 15: Summary of 2019 Operations Test

    Proposed Study 1 – Operations Study Summary of 2019 Operations Test • Operations Test was conducted in October of 2019. • Test was a single operation event increasing generation to maximum plant output and maintaining maximum plant output until the top 4 feet of reservoir volume was utilized. • Test

  16. Slide 16: Study Objectives and Description

    Proposed Study 1 – Operations Study Study Objectives and Description • Study Objectives • To simulate operational scenarios of flexible capacity at the project to determine plant generation outputs, rate, and degree of reservoir elevation changes. • Study Description • This study will simulate opera

  17. Slide 17: Methods

    Proposed Study 1 – Operations Study Methods • Test will be conducted in three separate phases • Phase 1 – low flexible capacity (20 MW) • Phase 2 – moderate flexible capacity (40 MW) • Phase 3 – maximum flexible capacity (max available) • Each phase will be 7 days long. • Minimum of 2 weeks break wi

  18. Slide 18: Example Reservoir Elevations

    Proposed Study 1 – Operations Study Example Reservoir Elevations Example of potential reservoir elevations during Phase 1

  19. Slide 19: Resources to be Evaluated

    Proposed Study 1 – Operations Study Resources to be Evaluated • Resource areas to be evaluated • Operations • Shoreline Stability • Fisheries • Recreation & Aesthetics • Public Safety • Water Quality • Wetland/Riparian Habitats • Cultural Resources

  20. Slide 20: Objectives

    Proposed Study 1 – Operations Study Objectives • Operations • Simulate flexible capacity scenarios to determine plant generation outputs, rate, and degree of reservoir elevation changes. • Shoreline Stability • Determine effects of operations on shoreline stability around the reservoir. • Fisheries

  21. Slide 21: Objectives (cont.)

    Proposed Study 1 – Operations Study Objectives (cont.) • Public Safety • Determine potential effects of project operations on public safety including changing water levels in the reservoir and below the powerhouse. • Water Quality • Evaluate any potential changes in water quality related to the proj

  22. Slide 22: Shoreline Stability Study Area

    Proposed Study 1 – Operations Study Shoreline Stability Study Area • Study includes shorelines extending from the dams upstream to the mouth of the Thompson River. • Includes the majority of developed lands in the project boundary. • Shorelines and embankments upstream of Thompson River and downstre

  23. Slide 23: Shoreline Stability Study Methods

    Proposed Study 1 – Operations Study Shoreline Stability Study Methods • Nine established reference points representing a diversity of soil types, slope, aspect, vegetation, and land use. • Visual observations made on a 300-foot reach at each reference point during each site visit during the study. •

  24. Slide 24: Fisheries Study Area

    Proposed Study 1 – Operations Study Fisheries Study Area • Fish Stranding: Exposed islands and shoreline habitats in Thompson Falls Reservoir below Cherry Creek and near the islands above Thompson River. • Habitat condition observations at the mouth of the Thompson River and Cherry Creek. • Conditio

  25. Slide 25: Fisheries Study Methods

    Proposed Study 1 – Operations Study Fisheries Study Methods • Establish 200-foot transects in shallow habitats less than 2.5 feet deep at full pool (fluctuation zone). • Three transects on exposed mid-channel island areas and three transects along exposed shoreline habitats below Cherry Creek and ne

  26. Slide 26: Recreation & Aesthetics Study Area

    Proposed Study 1 – Operations Study Recreation & Aesthetics Study Area Focus on shoreline facilities from the dam upstream to the mouth of the Thompson River and Sandy Beach dispersed recreation site.

  27. Slide 27: Recreation & Aesthetics Study Methods

    Proposed Study 1 – Operations Study Recreation & Aesthetics Study Methods • Reference points established at boat launches, docks, and public viewing areas. • Reservoir divided into four sections to identify subset of 40 representative docks: • Boat barrier upstream to Steamboat Island • Steamboat Is

  28. Slide 28: Public Safety

    Proposed Study 1 – Operations Study Public Safety • Study Area • Sandy Beach dispersed recreation site below original powerhouse. • High traffic areas in Thompson Falls Reservoir. • Methods • Monitoring and observation of shallow water areas during static hold times for each Phase. • Assess the publ

  29. Slide 29: Water Quality Study Area

    Proposed Study 1 – Operations Study Water Quality Study Area • Water Quality Instruments • Water level (stage) recorders • Upstream of Dry Channel Dam • Islands above Thompson River • Birdland Bay Bridge • Mouth of Thompson River • Downstream of Powerhouses

  30. Slide 30: Water Quality Study Methods

    Proposed Study 1 – Operations Study Water Quality Study Methods • Water level recorders will be set to record water stage on 5-minute intervals to evaluate reservoir elevation change throughout the project. • Instruments will be deployed and programed to record water quality parameters every 15 minu

  31. Slide 31: Wetland/Riparian Habitats Study Area

    Proposed Study 1 – Operations Study Wetland/Riparian Habitats Study Area • In Thompson Falls Reservoir focusing on known wetland habitats near Steamboat Island and upstream of the Thompson River. • Wetlands identified using Montana Spatial Data Infrastructure Wetlands Framework.

  32. Slide 32: Wetland/Riparian Habitats Study Methods

    Proposed Study 1 – Operations Study Wetland/Riparian Habitats Study Methods • Measurement of changes in water level with level loggers and/or piezometers. • Visual observations of identified Wetland and Riparian areas. • Risk to each wetland and riparian area ranked as high, medium, or low by evalua

  33. Slide 33: Cultural

    Proposed Study 1 – Operations Study Cultural • Study area consists of the locations of known archaeological properties at or near the reservoir high water line. • 3 known properties • Salish House • Prehistoric and historic artifact scatter • Chinese railroad encampment • Methods • Effects of reserv

  34. Slide 34: Schedule

    Proposed Study 1 – Operations Study Schedule • Preparatory work prior to the FERC Study Plan Determination • Identifying baseline conditions • Establishing reference points • Identifying sampling sites • Preparing maps • First Study Season • All three phases will be scheduled when inflows are below

  35. Slide 35: Reporting

    Proposed Study 1 – Operations Study Reporting • NorthWestern will develop a Final Study Report which will include • Data summaries • Assessments of observations • Photo documentation • Conclusions from resource evaluations • Data compilation, analysis, and drafting of report will take place after Ph

  36. Slide 36: Any Questions?

    Any Questions? • Guidelines for Asking a Question • Click on the “Chat” icon and type your question; once recognized, please unmute yourself, introduce yourself, and ask your question. • Click on the “Raise Your Hand” icon to be recognized; once recognized, please unmute yourself, introduce yourself

  37. Slide 37: Proposed Study 4 – Hydraulic Conditions

    Proposed Study 4 – Hydraulic Conditions

  38. Slide 38: Study Description

    Proposed Study 4 – Hydraulic Conditions Study Description • Result of 2008 Biological Opinion requirement to conduct a scientific review of the passage facility. • The scientific review panel recommended a hydraulics study in the near field downstream of the project and a fish behavior study. • Flow

  39. Slide 39: Study Area

    Proposed Study 4 – Hydraulic Conditions Study Area • Combine a bathymetric survey and available LiDAR data to develop a digital elevation model from the Main Channel Dam downstream to the High Bridge.

  40. Slide 40: Methods – Two-Phased Approach

    Proposed Study 4 – Hydraulic Conditions Methods – Two-Phased Approach Phase 1: 2D simulation to provide overview of hydraulics and a wider range of flow rates. • Overview of river channel hydraulics to identify areas to focus and refine modeling • Up to 4 flow rate simulations • Flow depth and depth

  41. Slide 41: Methods - Two-Phased Approach (cont.)

    Proposed Study 4 – Hydraulic Conditions Methods - Two-Phased Approach (cont.) Phase 2: 3D simulation at key identified flow rates and locations based on 2D findings. • Further refine model in key areas such as fish passage entrance and falls area. • 2 flow rate simulations. • Flow depth, vertical ve

  42. Slide 42: Schedule

    Proposed Study 4 – Hydraulic Conditions Schedule 42

  43. Slide 43: Proposed Study 5 – Fish Behavior

    Proposed Study 5 – Fish Behavior

  44. Slide 44: Goals & Objectives

    Proposed Study 5 – Fish Behavior Goals & Objectives • Evaluate fish movement through the Zone of Passage (ZOP). • Assess the effectiveness of upstream fish passage and residual project influences. • The scientific review panel recommended a fish behavior study using radio telemetry to evaluate fish

  45. Slide 45: Study Description

    Proposed Study 5 – Fish Behavior Study Description • The telemetry monitoring efforts will focus on assessing fish movement, including • Travel time from the far field to the near field. • Movement patterns (e.g., left bank, right bank) in the near field (Main Channel Dam area). • Travel time from t

  46. Slide 46: Study Area

    Proposed Study 5 – Fish Behavior Study Area

  47. Slide 47: Study Area (ZOP)

    Proposed Study 5 – Fish Behavior Study Area (ZOP)

  48. Slide 48: Methods

    Proposed Study 5 – Fish Behavior Methods • Related to Bull Trout, surrogates are needed to make inferences where appropriate. • Size. • Swimming capability. • Migration timing. • Radio and PIT tag 50 Brown Trout and 50 Rainbow Trout captured from Thompson River. • Depth and activity tag sensors. • A

  49. Slide 49: Methods (cont.)

    Proposed Study 5 – Fish Behavior Methods (cont.) Release radio tagged fish at Flat Iron boat launch (4 miles downstream).

  50. Slide 50: Methods – Fixed Receiver System

    Proposed Study 5 – Fish Behavior Methods – Fixed Receiver System 50

  51. Slide 51: Methods

    Proposed Study 5 – Fish Behavior Methods • Combining the behavioral data and hydraulic modeling data to help identify potential project influences (e.g., velocity fields) in the near field that may affect conditions for upstream fish passage. • Complete a literature review of the relative swimming c

  52. Slide 52: Schedule

    Proposed Study 5 – Fish Behavior Schedule Brown Trout movement Rainbow Trout movement

  53. Slide 53: Any Questions?

    Any Questions? • Guidelines for Asking a Question: • Click on the “Chat” icon and type your question; once recognized, please unmute yourself, introduce yourself, and ask your question. • Click on the “Raise Your Hand” icon to be recognized; once recognized, please unmute yourself, introduce yoursel

  54. Slide 54: Proposed Study 6 – Downstream Transport of Bull Trout

    Proposed Study 6 – Downstream Transport of Bull Trout

  55. Slide 55: Goals & Objectives

    Proposed Study 6 – Downstream Transport of Bull Trout Goals & Objectives • Evaluate the feasibility of collecting and transporting juvenile Bull Trout from Thompson River tributaries to Lake Pend Oreille. • Determine the most efficient and effective capture methods, location, and seasonal timing of

  56. Slide 56: Study Description

    Proposed Study 6 – Downstream Transport of Bull Trout Study Description • Out-migrating juvenile Bull Trout from Thompson River may reside in Noxon Rapids Reservoir. As adults, they can migrate upstream to their natal stream using the fish passage facility at Thompson Falls Dam. • Alternatively, the

  57. Slide 57: Study Area

    Proposed Study 6 – Downstream Transport of Bull Trout Study Area 57

  58. Slide 58: Study Description

    Proposed Study 6 – Downstream Transport of Bull Trout Study Description • 3 PIT antenna arrays. • Weir operation near PIT arrays in West Fork Thompson River and Fishtrap Creek.

  59. Slide 59: Methods

    Proposed Study 6 – Downstream Transport of Bull Trout Methods • Electrofish and picket weir traps operated during October and November. • Lower sections of Fishtrap and West Fork Thompson River. • PIT tag up to 200 Bull Trout, 120-250mm and transport 75% downstream to Lake Pend Oreille, release 25%

  60. Slide 60: Schedule

    Proposed Study 6 – Downstream Transport of Bull Trout Schedule

  61. Slide 61: Any Questions?

    Any Questions? • Guidelines for Asking a Question • Click on the “Chat” icon and type your question; once recognized, please unmute yourself, introduce yourself, and ask your question. • Click on the “Raise Your Hand” icon to be recognized; once recognized, please unmute yourself, introduce yourself

  62. Slide 62: Proposed Study 9 – Westslope Cutthroat Trout Genetics Study

    Proposed Study 9- Westslope Cutthroat Trout Genetics Study

  63. Slide 63: Goals & Objectives

    Proposed Study 9 – Westslope Cutthroat Trout Genetics Study Goals & Objectives • Standardize approach to phenotypically identify Westslope Cutthroat Trout (WCT) and hybrids captured at passage facility. • Take a genetic sample for WCT and hybrids to determine level of purity or hybridization of indi

  64. Slide 64: Study Description

    Proposed Study 9 – Westslope Cutthroat Trout Genetics Study Study Description • Main stem dams have fragmented habitats and WCT populations. • Since 2011 over 2,000 WCT, Rainbow Trout, and hybrids have been passed at upstream fish passage facility. • Can we correctly identify WCT or hybrids captured

  65. Slide 65: Study Area

    Proposed Study 9 – Westslope Cutthroat Trout Genetics Study Study Area

  66. Slide 66: Methods

    Proposed Study 9 – Westslope Cutthroat Trout Genetics Study Methods • Develop standardized phenotypic approach to identify WCT at the upstream passage facility. • Use photographs of pure WCT as guides. • Slash intensity, body spotting, anal fin spotting, and coloration as key characteristics.

  67. Slide 67: Methods

    Proposed Study 9 – Westslope Cutthroat Trout Genetics Study Methods • Genetic sample from WCT and hybrids to determine levels of hybridization and accuracy of observer identification. • Range of 14 - 48 visually identified WCT captured at the facility per year.

  68. Slide 68: Study Schedule

    Proposed Study 9 – Westslope Cutthroat Trout Genetics Study Study Schedule • March-October 2021 - Collections at upstream fish passageway • October 2021 - February 2022 - Laboratory analysis • May 2022 - Final report

  69. Slide 69: Any Questions?

    Any Questions? • Guidelines for Asking a Question • Click on the “Chat” icon and type your question; once recognized, please unmute yourself, introduce yourself, and ask your question. • Click on the “Raise Your Hand” icon to be recognized; once recognized, please unmute yourself, introduce yourself

  70. Slide 70: Proposed Study 2 – Total Dissolved Gas

    Proposed Study 2 – Total Dissolved Gas

  71. Slide 71: Total Dissolved Gas (TDG) Purpose

    Proposed Study 2 – Total Dissolved Gas (TDG) Purpose • Purpose of the Study: • Collect background (incoming) TDG concentrations in the Clark Fork River upstream of the dams. • Collect downstream (outgoing) TDG concentrations in the Clark Fork River below the main dam and at Birdland Bay Bridge. • TD

  72. Slide 72: Slide 72

  73. Slide 73: Slide 73

  74. Slide 74: Slide 74

  75. Slide 75: Study Area & Description

    Proposed Study 2 – Total Dissolved Gas (TDG) Study Area & Description • TDG is measured in three locations • Above the powerhouse • Below the main dam • Birdland Bay Bridge • Hydrolab instruments provide TDG readings at 30-minute intervals.

  76. Slide 76: Birdland Bay Bridge

    Birdland Bay Bridge

  77. Slide 77: Thompson Falls Total Dissolved Gas Concentrations (TDG)

    Total Dissolved Gas Concentration % Thompson Falls Total Dissolved Gas Concentrations (TDG) 140% 100000 130% 120% 110% 100% ® Below Main Dam @ Birdland Bay Brdge @ Above Dam 70% Total Flow (cfs) 30% 20% 10% 0% “—__— — ——— —e¢—_—— —_e—__s#—__—- 4/15/2020 0:00 —- ———10 4/30/2020 0:00 5/15/2020 0:00 5/

  78. Slide 78: Methods

    Proposed Study 2 – Total Dissolved Gas (TDG) Methods • This study will use monitoring methodologies similar to past monitoring efforts. • Data will be collected throughout the spill season in the spring to capture TDG concentrations at different river flows and gate configurations.

  79. Slide 79: Schedule

    Proposed Study 2 – Total Dissolved Gas (TDG) Schedule • Deploy monitoring equipment in April 2021. • Conduct monitoring and bi-weekly maintenance on equipment through July 2021. • Analyze data collected and prepare summary report for May 2022. • Conduct additional monitoring in 2022 for a final repo

  80. Slide 80: Any Questions?

    Any Questions? • Guidelines for Asking a Question • Click on the “Chat” icon and type your question; once recognized, please unmute yourself, introduce yourself, and ask your question. • Click on the “Raise Your Hand” icon to be recognized; once recognized, please unmute yourself, introduce yourself

  81. Slide 81: Proposed Study 3 – Water Quality

    Proposed Study 3 – Water Quality

  82. Slide 82: Goals & Objectives

    Proposed Study 3 – Water Quality Goals & Objectives • The purpose of this study is to collect water quality data to characterize the existing water quality conditions at the Thompson Falls Hydroelectric Project. • Data from this study will supplement water quality data collected in 2019 and 2020. •

  83. Slide 83: Study Area

    Proposed Study 3 – Water Quality Study Area

  84. Slide 84: Methods

    Proposed Study 3 – Water Quality Methods • Water quality samples consist of a depth-integrated sample, and where possible, width-integrated sample. • Several samples are collected at each site and composited into one representative sample for the site. • Each sample is analyzed for nutrients, metals

  85. Slide 85: ; s e s i ; be A ‘ . ‘ x A .

    ; s e 5 s i ; be A ‘ . ‘ x A . xe TENGE .

  86. Slide 86: Slide 86

  87. Slide 87: Methods

    Proposed Study 3 – Water Quality Methods • Data collected will be compared to Montana’s water quality standards. • Numeric nutrient standards have not been developed for the Clark Fork River downstream of Missoula. • Numeric metals standards are based on a potential harm to either aquatic life or hu

  88. Slide 88: Schedule

    Proposed Study 3 – Water Quality Schedule • Conduct quarterly water chemistry monitoring in March, June, September, and December 2021. • Analyze data collected and prepare summary report for May 2022. • Conduct additional quarterly monitoring in 2022 for a final report in May 2023.

  89. Slide 89: Any Questions?

    Any Questions? • Guidelines for Asking a Question • Click on the “Chat” icon and type your question; once recognized, please unmute yourself, introduce yourself, and ask your question. • Click on the “Raise Your Hand” icon to be recognized; once recognized, please unmute yourself, introduce yourself

  90. Slide 90: Proposed Study 7 – Visitor Survey

    Proposed Study 7 – Visitor Survey

  91. Slide 91: Goals & Objectives

    Proposed Study 7 – Visitor Survey Goals & Objectives • A recreation visitor survey is proposed in the Project area from Memorial Day weekend through Labor Day weekend 2021 to obtain current information from recreationists about their use of recreation sites, facilities, and opportunities during the

  92. Slide 92: Study Description

    Proposed Study 7 – Visitor Survey Study Description Information will be sought regarding: Previous Site Use Recreation Activities at Site Current Site Use Problems Encountered at Site (if any) Reasons for Visiting Site Use of Trails and Satisfaction Opinions about Site Facilities Visitor Geographic

  93. Slide 93: Cherry Creek Boat Launch

    Proposed Study 7 – Visitor Survey Cherry Creek Boat Launch

  94. Slide 94: North Shore Dispersed Use Area

    Proposed Study 7 – Visitor Survey North Shore Dispersed Use Area

  95. Slide 95: Wild Goose Landing Park

    Proposed Study 7 – Visitor Survey Wild Goose Landing Park

  96. Slide 96: North Shore Boat Restraint

    Proposed Study 7 – Visitor Survey North Shore Boat Restraint

  97. Slide 97: Island Park

    Proposed Study 7 – Visitor Survey Island Park

  98. Slide 98: South Shore Dispersed Recreation Area

    Proposed Study 7 – Visitor Survey South Shore Dispersed Recreation Area

  99. Slide 99: Power Park

    Proposed Study 7 – Visitor Survey Power Park

  100. Slide 100: Sandy Beach

    Proposed Study 7 – Visitor Survey Sandy Beach

  101. Slide 101: Powerhouse Loop Trail

    Proposed Study 7 – Visitor Survey Powerhouse Loop Trail

  102. Slide 102: Study Area

    Proposed Study 7 – Visitor Survey Study Area Recreation sites associated with the Thompson Falls Project offer facilities and opportunities to participate in a variety of activities: •Picnic facilities •Boat ramps and launching docks •Facilities for visitor conveniences •Shoreline access •Trail-base

  103. Slide 103: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  104. Slide 104: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  105. Slide 105: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  106. Slide 106: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  107. Slide 107: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  108. Slide 108: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  109. Slide 109: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  110. Slide 110: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  111. Slide 111: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  112. Slide 112: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  113. Slide 113: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  114. Slide 114: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  115. Slide 115: Proposed Study Plan 7 – Visitor Use Survey

    Proposed Study Plan 7 – Visitor Use Survey

  116. Slide 116: Methods & Schedule

    Proposed Study 7 – Visitor Survey Methods & Schedule • 60 sampling days will be randomly selected during the sampling timeframe between May 28 and September 6, 2021. Sampling will be dispersed throughout the days of the week and hours of the day to arrive at a sampling schedule that is representativ

  117. Slide 117: Any Questions?

    Any Questions? • Guidelines for Asking a Question • Click on the “Chat” icon and type your question; once recognized, please unmute yourself, introduce yourself, and ask your question. • Click on the “Raise Your Hand” icon to be recognized; once recognized, please unmute yourself, introduce yourself

  118. Slide 118: Proposed Study 8 – Cultural Resources Inventory, Evaluation, and Examination of Potential Effects

    Proposed Study 8 – Cultural Resources Inventory, Evaluation, and Examination of Potential Effects

  119. Slide 119: Cultural Resources Inventory and National Register Evaluation

    Proposed Study 8 – Cultural Resources Cultural Resources Inventory and National Register Evaluation • Update inventory of Historic Architectural and Engineering Properties. • Develop high probability model for Prehistoric and Historic Archaeological Properties. • Field inventory identified high prob

  120. Slide 120: Goals & Objectives

    Proposed Study 8 – Cultural Resources Goals & Objectives • Collect and analyze baseline resource data to gauge any current and anticipated Project effects on cultural properties. • Develop Historic Properties Management Plan under new License.

  121. Slide 121: Study Description

    Proposed Study 8 – Cultural Resources Study Description • Update inventory and evaluation of historic architectural and engineering elements of Thompson Falls Hydroelectric Dam Historic District. • Expand record of known prehistoric and historic archaeological properties through systematic inventory

  122. Slide 122: Methods

    Proposed Study 8 – Cultural Resources Methods For Historic Architectural and Engineering Properties • Re-Inventory Thompson Falls Hydroelectric Dam Historic District and update 1986 National Register of Historic Places listing.

  123. Slide 123: Methods

    Proposed Study 8 – Cultural Resources Methods For Previously-unknown Prehistoric and Historic Archaeological Properties • Develop and field test high probability model to predict where previously-unknown prehistoric and historic archaeological properties mostly likely exist within project. • Invento

  124. Slide 124: Schedule

    Proposed Study 8 – Cultural Resources Schedule Timing Activity May 2021–Feb 2022 Update inventory of Thompson Falls Hydroelectric Dam Historic District May–Sept 2021 Develop and refine high prehistoric and historic archaeological properties probability model; submit to reviewers Oct 2021 Review peri

  125. Slide 125: Any Questions?

    Any Questions? • Guidelines for Asking a Question • Click on the “Chat” icon and type your question; once recognized, please unmute yourself, introduce yourself, and ask your question. • Click on the “Raise Your Hand” icon to be recognized; once recognized, please unmute yourself, introduce yourself

  126. Slide 126: Delivering a bright future

    U belivering a bright future NorthWesternEnergy.com