Northam Platinum — FY2013 Earnings Presentation

27 slides from Northam Platinum's earnings presentation, June 2013

  1. Slide 1: Northam Platinum

    NORTHAM PLATIN UM tLtmMtitTteo

  2. Slide 2: Key features from the results

    Key features from the results • Zondereinde production marginally higher at 9 041kg (290 675oz) • Metal sales 7.3% higher at 10 704kg (344 128oz) • Basket price received up 8.9% to R365 217/kg • Operating profit up 79.4% to R607.7 million • Earnings per share up 62.6% up at 132.0 cps • Net debt of R

  3. Slide 3: Zondereinde safety

    Zondereinde safety Injury incidence rates per 200 000 man hours 6 5.0 5 4.1 4 3 2.5 2.3 2.3 2.3 2.1 1.9 2 1.5 1.5 1.3 1.0 1 0.8 1.2 1.3 1.2 1.3 1.0 1.0 1.0 1.0 0.9 0.8 0.6 0.7 0.5 0 F2001 F2002 F2003 F2004 F2005 F2006 F2007 F2008 F2009 F2010 F2011 F2012 F2013 LTIIR RIIR 3 PRELIMINARY RESULTS FOR THE

  4. Slide 4: Zondereinde production

    Zondereinde production F2013 F2012 Change (%) Merensky tonnes milled 958 211 884 660 8.3 Merensky head grade (g/t) 5.8 5.9 (1.7) UG2 tonnes milled 1 157 501 1 049 017 10.3 UG2 head grade (g/t) 4.2 4.4 (4.5) Total tonnes milled 2 115 712 1 933 677 9.4 Average combined head grade 4.9 5.1 (3.9) PGMs in

  5. Slide 5: Zondereinde unit costs

    Zondereinde unit costs 2013 2012 Change (%) Operating costs - Rand per tonne milled 1 447 1 447 0.0 Cash costs - Rand per tonne milled 1 322 1 318 0.3 Operating costs - Rand per kilogram (3PGE+Au) 334 899 311 645 7.5 Cash costs - Rand per kilogram (3PGE+Au) 309 421 283 934 9.0 Operating costs - US$

  6. Slide 6: Zondereinde mine plan

    Zondereinde mine plan 6 PRELIMINARY RESULTS FOR THE YEAR ENDED 30 JUNE 2013

  7. Slide 7: Zondereinde mining ratios

    Zondereinde mining ratios 100% 7.0 90% 6.0 80% UG2 55% PERCENTAGE CONTRIBUTION 70% 5.0 MILL HEAD GRADE (g/t) 60% 4.0 50% 3.0 40% MR 30% 45% 2.0 20% 1.0 10% 0% 0.0 F2000 F2001 F2002 F2003 F2004 F2005 F2006 F2007 F2008 F2009 F2010 F2011 F2012 F2013 UG2 Merensky Head Grade 7 PRELIMINARY RESULTS FOR THE

  8. Slide 8: Zondereinde Merensky reef facies ratios

    Zondereinde Merensky reef facies ratios 100% 90% 22%NR PERCENTAGE MERENSKY FACIES 80% 4%NP2 70% 60% 50% 59%P2 40% 30% 20% 10% 9%FWP 6%Waste 0% F2000 F2001 F2002 F2003 F2004 F2005 F2006 F2007 F2008 F2009 F2010 F2011 F2012 F2013 8 PRELIMINARY RESULTS FOR THE YEAR ENDED 30 JUNE 2013

  9. Slide 9: Booysendal

    BOOYSENDAL 9 PRELIMINARY RESULTS FOR THE YEAR ENDED 30 JUNE 2013

  10. Slide 10: Booysendal update

    Booysendal update • Total workforce at Booysendal reduced to 1 915 people • LTIIR – 0.53, RIIR 0.33 (per 200 000 man hours) • 1 million fatality free shifts achieved on 9 March 2013 • Eskom power conductor commissioned in March 2013 • Concentrator plant commissioned • Tailings storage facility compl

  11. Slide 11: Booysendal operating performance

    Booysendal operating performance F2013 F2012 Square metres stoped 41 639 - Tonnes mined 747 586 - Tonnes milled 242 602 - Head grade (g/t 3PGE+Au) 2.40 - PGMs in concentrate produced (kg 3PGE+Au) 473 - PGMs sold (kg 3PGE+Au) 109 - Reef stockpile (tonnes) 400 000 102 900 11 PRELIMINARY RESULTS FOR TH

  12. Slide 12: Booysendal mine plan

    Booysendal mine plan 12 PRELIMINARY RESULTS FOR THE YEAR ENDED 30 JUNE 2013

  13. Slide 13: Financial performance

    FINANCIAL PERFORMANCE 13 PRELIMINARY RESULTS FOR THE YEAR ENDED 30 JUNE 2013

  14. Slide 14: Income statement

    Income statement F2013 F2012 Change (%) R000s R000s Sales revenue 4 420 977 3 684 000 20.0 Cost of sales 3 813 301 3 345 311 14.0 Operating profit 607 676 338 689 79.4 Share of earnings from associate 13 783 16 602 (17.0) Investment revenue 33 434 53 951 (38.0) Finance charges (17 946) - - Net sundr

  15. Slide 15: Cost of sales

    Cost of sales F2013 F2012 Change (%) R000s R000s Sales revenue 4 420 977 3 684 000 20.0 Cost of sales 3 813 301 3 345 311 14.0 operating costs 2 826 094 2 632 926 7.3 concentrates purchased 657 540 624 774 5.2 refining costs 161 591 100 612 60.6 depreciation 234 690 190 287 23.3 change in metal inve

  16. Slide 16: Cash flow

    Cash flow • R1.25 billion financing secured in domestic capital market during the period • Available debt facilities at 30 June 2013 of R2.25 billion (including the above) • Net debt at 30 June 2013 amounted to R1 201.4 million • Undrawn facilities (RCF) at 30 June 2013 amounted to R750 million F201

  17. Slide 17: Revenue vs cost of sales

    Revenue vs cost of sales R000s 4 500 000 4 000 000 3 500 000 3 000 000 2 500 000 2 000 000 1 500 000 1 000 000 500 000 0 2007 2008 2009 2010 2011 2012 2013 Platinum Palladium Rhodium Gold Nickel Other Operating costs Cost of sales 17 PRELIMINARY RESULTS FOR THE YEAR ENDED 30 JUNE 2013

  18. Slide 18: Markets

    Markets 18 PRELIMINARY RESULTS FOR THE YEAR ENDED 30 JUNE 2013

  19. Slide 19: Market review

    Market review • PGM prices declined sharply in first half of 2013 • Platinum declined 13%; palladium 6%; rhodium 7% • Pt demand • autocatalyst and industrial sectors remain subdued • growth in jewellery and investment sectors • Pd demand • more robust than Pt • growth in gasoline vehicle production

  20. Slide 20: Market outlook

    Market outlook • Demand • Pt and Rh likely to continue subdued • Pd outlook more positive • Supply • higher volumes of recycled material • cutbacks in primary mine supplies • potential for production disruptions • Market balances • metal deficits expected to deepen in Pt and Pd; surplus in Rh • abov

  21. Slide 21: Business outlook

    Business outlook • Operations • Zondereinde production remains challenging especially in the NW quadrant however, the deepening project should help maintain ore ratios • Booysendal equipping and production ramp-up • furnace rebuild and toll refining • power availability and costs • Markets • Pt and

  22. Slide 22: Northam Platinum

    NORTHAM PLATIN UM tLtmMtitTteo

  23. Slide 23: Sales volumes (kg)

    Sales volumes (kg) F2013 F2012 Change % Platinum 6 606 6 088 8.5 Palladium 3 133 2 861 9.5 Rhodium 786 843 (6.8) Gold 179 188 (4.8) Total (3PGE+Au) 10 704 9 980 7.3 Ruthenium 1 315 1 091 20.5 Iridium 261 218 19.7 Copper (tonnes) 678 660 2.7 Nickel (tonnes) 1 313 1 180 11.3 23 PRELIMINARY RESULTS FOR

  24. Slide 24: Sales volumes (oz)

    Sales volumes (oz) F2013 F2012 Change % Platinum 212 375 195 737 8.5 Palladium 100 715 91 999 9.5 Rhodium 25 280 27 093 (6.8) Gold 5 758 6 032 (4.8) Total (3PGE+Au) 344 128 320 861 7.3 Ruthenium 42 268 35 080 20.5 Iridium 8 382 6 999 19.7 Copper (tonnes) 678 660 2.7 Nickel (tonnes) 1 313 1 180 11.3

  25. Slide 25: Sales prices realised (R/kg)

    Sales prices realised (R/kg) F2013 F2012 Change % Platinum 448 077 404 431 10.8 Palladium 196 059 169 152 15.9 Rhodium 322 097 381 187 15.5 Gold 455 340 421 375 8.1 Total (3PGE+Au) 365 217 335 326 8.9 Ruthenium 23 390 27 222 (14.1) Iridium 284 864 269 196 5.8 Copper (R/tonne) 65 171 59 671 9.2 Nicke

  26. Slide 26: Sales prices realised (US$/oz)

    Sales prices realised (US$/oz) F2013 F2012 Change % Platinum 1 567 1 622 (3.4) Palladium 684 679 0.7 Rhodium 1 117 1 523 (26.7) Gold 1 583 1 686 (6.1) Total (3PGE+Au) 1 276 1 345 (5.1) Ruthenium 82 106 (22.6) Iridium 985 1 054 (6.5) Copper ($/t) 7 398 7 820 (5.4) Nickel ($/t) 16 045 18 919 (15.1) 26

  27. Slide 27: Contact details and shareholder information

    Contact details Shareholder information 1st Floor, 1A Albury Park Name Northam Platinum Limited Magalieszicht Avenue Dunkeld West Sharecode NHM Johannesburg 2196 South Africa JSE sector Platinum Tel: +27 11 759 6000 ADR programme Yes Fax: +27 11 325 4795 Email: rene.rautenbach@norplats.co.za; Sponso