  3. Slide 3: Profit & Loss

    Profit & Loss H1 FY2020 RM’000 Q1 2020 Q2 2020 H1 2020 RM55M Revenue 537,945 345,403 883,348 Cost of Sales (445,624) (276,700) (722,324) Gross Profit 92,321 68,703 161,024 Profit After Tax Other Operating Income Selling & Marketing Expenses 14,129 (8,821) 14,863 (6,208) 28,992 (15,029) Administrativ

  4. Slide 4: Balance Sheet

    RM1.56 Net Asset per share RM’000 Shareholders’ Funds Balance Sheet 30 April 2020 4,586,391 31 Oct 2019 4,538,016 NA per Share (RM) 1.56 1.54 Total Cash 382,004 600,539 shareholders’ funds & net assets per share increased Total Borrowings 3,506,587 3,779,408 Net Cash / (Debt) (3,124,583) (3,178,869)

  5. Slide 5: Sales Breakdown by Quarter

    As at 15 June 2020 Sales Breakdown by Quarter RM975M Sales Achieved 1Q 2020 304.8 RM600M 2Q 2020 28.5 Sales Pipeline 3Q 2020 642.2 600 (until 15 June) RM’mil 0 200 400 600 800 1000 1200 1400 Sales Pipeline

  6. Slide 6: Future Revenue Status as at 15 June 2020

    Future Revenue Status as at 15 June 2020 RECOGNISED FUTURE EFFECTIVE SALES SECURED PROJECT REVENUE REVENUE STAKE (%) (RMmn) (RMmn) (RMmn) Klang Valley 100% 6,319.1 5,497.4 821.7 Iskandar Malaysia 100% 5,072.9 4,405.9 667.0 Iskandar Malaysia Eco SUBSIDIARIES 100% 1,508.4 1,243.4 265.0 Business Parks

  7. Slide 7: Key Highlights

    KEY HIGHLIGHTS

  8. Slide 8: Digital Engagement

    DIGITAL ENGAGEMENT ramped up throughout MCO Active use of social media platforms to engage with customers / Webinars / video walk-throughs + wide range of digital content to promote all our projects / One-on-One zoom calls with prospects & family members / 2,000 appointments secured with new potenti

  9. Slide 9: BBCC Serviced Residence JV with Mitsui Fudosan

    Serviced Residence BBCC 2nd JV with Mitsui Fudosan Mitsui Fudosan (Asia) Malaysia Sdn Bhd and BBCC Development Sdn Bhd entered into a JV to purchase a serviced residence block in BBCC for RM242 million / To provide the units in the SR on long term and short term tenancy basis to Japanese and other f

  10. Slide 10: Eco Bloom @ Eco Meadows

    ECO BLOOM @ Eco Meadows Completed in March 2020 / Vacant possession process begun in April 2020 / Lifestyle outlets to open progressively by year end to serve the residents

  11. Slide 11: Duduk

    DUDUK a new vertical living concept has garnered a string of followers since it was unveiled in March #dudukkatrumah

  12. Slide 12: Live In Your Dream Home!

    Live In Your Dream Home! SE-RUANG HUN ECO SANCTUARY ECO ARDENCE SEMIS. %600 FURNISHED =~ MUSANG 1,000 sqft UNIT VeGbiGal:

  13. Slide 13: Duduk: What It Offers

    DUDUK what it offers Se.Ruang Huni @ Eco @ Eco Ardence Sanctuary Built up 1,000 sqft (3 room, 2 bathrooms) Semi-furnished All Light & Fan | Air Cond | Master Bedroom Wardrobe | Kitchen Cabinet | Hob | Washer Dryer | Water Heater Target selling price From RM393,000 Target launch End 2020 Target compl

  14. Slide 14: Eco Botanic 2

    ECO BOTANIC 2 dream homes for M40 group Project Eco Botanic Phase 2 Built up 1,701 sqft – 2,300 sqft Target selling price From RM500,000 Target launch End 2020 / Early 2021 Target completion End 2025

  15. Slide 15: FY2020 Outlook

    FY2020 Works at construction sites fully resumed HOC incentives & low interest rate to spur demand for properties Strong pipeline + encouraging registrations for both Duduk & Eco Botanic 2 Effective future revenue of RM4.6b provides clear earnings visibility