The Aes Corporation · NYSE:AES

The Aes — Fact Sheet (August 2024)

23 slides from The Aes's fact sheet, Aug 1, 2024

  1. Slide 1: The AES Corporation Fact Sheet

    The AES Corporation Fact Sheet As of August 1, 2024

  2. Slide 2: AES Total: 35,632 Gross MW in Operation

    AES Total: 35,632 Gross MW in Operation Technology Segment Pet Coke & Oil 2% Energy Renewables1 Infrastructure Renewables2 Gas 26% 42% 48% 56% 16% Coal 10% Utilities 1. Includes hydro, solar, wind, energy storage and landfill gas. 2 2. Excludes renewables projects in Chile, currently reported as par

  3. Slide 3: AES Total: 24,574 Proportional MW in Operation

    AES Total: 24,574 Proportional MW in Operation Technology Segment Pet Coke & Oil 2% Energy Renewables1 Infrastructure Renewables2 Gas 27% 46% 44% 53% 18% Coal 10% Utilities 1. Includes hydro, wind, solar, energy storage and landfill gas. 3 2. Excludes renewables projects in Chile, currently reported

  4. Slide 4: Renewables Total: 17,164 Gross MW in Operation

    Renewables Total1: 17,164 Gross MW in Operation Technology Energy Storage 7% 33% Hydro Wind 30% 30% Solar 1. Excludes renewables projects in Chile, currently reported as part of the Energy Infrastructure segment. 4

  5. Slide 5: Renewables Total: 10,811 Proportional MW in Operation

    Renewables Total1: 10,811 Proportional MW in Operation Technology Energy Storage 8% 36% Hydro Wind 29% 27% Solar 1. Excludes renewables projects in Chile, currently reported as part of the Energy Infrastructure segment. 5

  6. Slide 6: Renewables

    Renewables Date of Acquisition or Commencement of Contract Expiration Business Location Fuel Gross MW AES Equity Interest Customer(s) Commercial Date Operations AES Brasil Operações (AES Brazil Hydro 2,658 47% 1999 2032 Various Tietê)1,2 Alicura Argentina Hydro 1,050 100% 2000 Chivor Colombia Hydro

  7. Slide 7: Renewables

    Renewables Date of Acquisition or Commencement of Contract Expiration Business Location Fuel Gross MW AES Equity Interest Customer(s) Commercial Date Operations ENSA, Edemet, Edechi, Bayano Panama Hydro 260 49% 1999 2030 Other Buffalo Gap II1 US-TX Wind 233 100% 2007 Solar 150 Baldy Mesa2 US-CA 75%

  8. Slide 8: Renewables

    Renewables Date of Acquisition or Commencement of Contract Expiration Business Location Fuel Gross MW AES Equity Interest Customer(s) Commercial Date Operations ENSA, Edemet, Edechi, Chiriqui – Esti Panama Hydro 120 49% 2003 2030 Other Solar 60 Kuihelani1 US-HI 100% 2023-2024 2048 HECO Energy Storag

  9. Slide 9: Renewables

    Renewables Date of Acquisition or Commencement of Contract Expiration Business Location Fuel Gross MW AES Equity Interest Customer(s) Commercial Date Operations Clover Creek (OpCo C)1 US-UT Solar 80 50% 2021 2046 UMPA Westwing 1 2 US-AZ Energy Storage 80 100% 2023-2024 2043-2044 APS AGV Solar3 Brazi

  10. Slide 10: Renewables

    Renewables Date of Acquisition or Commencement of Contract Expiration Business Location Fuel Gross MW AES Equity Interest Customer(s) Commercial Date Operations National Electric Power AM Solar Jordan Solar 48 36% 2019 2039 Company Ullum Argentina Hydro 45 100% 1996 Various Solar 20 Kaua’i Island Ut

  11. Slide 11: Renewables

    Renewables Date of Acquisition or Commencement of Contract Expiration Business Location Fuel Gross MW AES Equity Interest Customer(s) Commercial Date Operations ENSA, Edemet, Edechi, Mayorca Solar Panama Solar 10 49% 2021 2030 Other ENSA, Edemet, Edechi, Cedro Panama Solar 10 49% 2021 2030 Other ENS

  12. Slide 12: Utilities Total: 3,693 Gross MW in Operation

    Utilities Total: 3,693 Gross MW in Operation Technology Renewables1 1% Oil 13% 53% Coal Gas 33% 1. Includes solar, wind, energy storage and landfill gas. 12

  13. Slide 13: Utilities Total: 2,573 Proportional MW in Operation

    Utilities Total: 2,573 Proportional MW in Operation Technology 2% Oil Renewables1 12% 53% Gas Coal 33% 1. Includes solar, wind, energy storage and landfill gas. 13

  14. Slide 14: Utilities

    Utilities Date of Acquisition or Commencement of Contract Expiration Business Location Fuel Gross MW AES Equity Interest Customer(s) Commercial Date Operations CAESS, EEO, CLESA, Bosforo El Salvador Solar 100 50% 2018-2019 2043-2044 DEUSEM CLESA, Cemento Holcim Metapan El Salvador Solar 15 100% 2023

  15. Slide 15: Energy Infrastructure Total: 14,774 Gross MW in Operation

    Energy Infrastructure Total: 14,774 Gross MW in Operation Technology 4% Pet Coke Renewables1 15% 51% Gas Coal 30% 1. Includes hydro, solar, wind and energy storage. 15

  16. Slide 16: Energy Infrastructure Total: 11,190 Proportional MW in Operation

    Energy Infrastructure Total: 11,190 Proportional MW in Operation Technology 5% Pet Coke Renewables1 17% 46% Gas Coal 32% 1. Includes hydro, solar, energy storage and wind. 16

  17. Slide 17: Energy Infrastructure

    Energy Infrastructure Date of Acquisition or Commencement of Contract Expiration Business Location Fuel Gross MW AES Equity Interest Customer(s) Commercial Date Operations Mong Duong 21 Vietnam Coal 1,242 51% 2015 2040 EVN California Department of Southland – Alamitos US-CA Gas 1,200 100% 1998 2026

  18. Slide 18: Energy Infrastructure

    Energy Infrastructure Date of Acquisition or Commencement of Contract Expiration Business Location Fuel Gross MW AES Equity Interest Customer(s) Commercial Date Operations Ede Este, Ede Norte, Ede DPP (Los Mina) Dominican Republic Gas 358 65% 1996 2025 Sur, Non-Regulated Users Ede Este, Ede Norte, E

  19. Slide 19: Energy Infrastructure

    Energy Infrastructure Date of Acquisition or Commencement of Contract Expiration Business Location Fuel Gross MW AES Equity Interest Customer(s) Commercial Date Operations Andes Solar 1 Chile Solar 22 99% 2016 2036 Quebrada Blanca Cochrane ES Chile Energy Storage 20 57% 2016 Angamos ES Chile Energy

  20. Slide 20: 5,064 Gross MW Under Construction

    5,064 Gross MW Under Construction Technology Segment Gas Renewables1 Energy Infrastructure Renewables2 13% 21% Utilities 10% 69% 87% 1. Includes solar, energy storage and wind. 20 2. Excludes renewables projects in Chile, currently reported as part of the Energy Infrastructure segment.

  21. Slide 21: 3,604 Proportional MW Under Construction

    3,604 Proportional MW Under Construction Technology Segment 4% Gas Energy Renewables1 Infrastructure Renewables2 15% Utilities 10% 75% 96% 1. Includes solar, energy storage, and wind. 21 2. Excludes renewables projects in Chile, currently reported as part of the Energy Infrastructure segment.

  22. Slide 22: 5,064 Gross MW of Generation Under Construction

    5,064 Gross MW of Generation Under Construction Business Location Fuel Gross MW AES Equity Interest Expected Commercial Operations Date Mirasol 1&2 Dominican Republic Solar 100 65% 2H 2024 Solar 10 1 High Mesa US-CO 75% 2H 2024 Energy Storage 10 2 Cajuína 2 Brazil Wind 74 47% 2H 2024 Los Santos Sola

  23. Slide 23: 5,064 Gross MW of Generation Under Construction

    5,064 Gross MW of Generation Under Construction Expected Commercial Business Location Fuel Gross MW AES Equity Interest Operations Date Pike County (AES Indiana) US-IN Energy Storage 200 70% 2H 2024 Solar 250 Petersburg Energy Center (AES Indiana) US-IN 70% 2H 2025 Energy Storage 45 Generation – Uti

The AES — Fact Sheet (August 2024) on 6ix