  1. Slide 1: Silverton Wind Farm Community Consultative Committee Meeting CCC-026

    Silverton Wind Farm Community Consultative Committee Meeting No.CCC-026 Tuesday, 23 January 2018

  2. Slide 2: Agenda

    Agenda 1 2 3 4 5 6 Welcome Previous Project update Community Topics of interest Other minutes • Overview relations • Visual impact business assessment • Wind Farm Works update • Connection Works Silverton Wind Farm | 23 January 2018 2

  3. Slide 3: 1. Welcome

    1. Welcome

  4. Slide 4: 2. Previous minutes

    2. Previous minutes

  5. Slide 5: Previous minutes: Action items

    2. Previous minutes Action items Item Action Status Who 5.19.01 AGL to arrange site tour for interested Silverton community members and the Broken Hill City Open AGL – 1/18 Council. 4.22.05 Naomi Schmidt to forward copy of email from Mark Coulton on telecommunication upgrade Open NS – 1/18 options t

  6. Slide 6: Previous minutes: Action items

    2. Previous minutes Action items Item Action Status Who 4.24.05 Community member asked if AGL would partner with Silverton to apply for blackspot funding, and Closed could the $15,000 from the community fund go towards the mobile reception program. 4.24.06 AGL to meet with Helen Murray to discuss vi

  7. Slide 7: 3. Project update

    • Overview • Wind Farm Works • Connection Works 3. Project update

  8. Slide 8: Silverton Wind Farm

    3. Project update Silverton Wind Farm Silverton Wind Farm • Located in the Barrier Ranges approximately 5km north of the Silverton township • Generation capacity of 200 MW • Wind turbines: 58 x GE 3.43-130 • Annual Energy Production (AEP) - ~780,000 MWh (capacity factor of 44.5%) - Powering more tha

  9. Slide 9: Scope of works

    3. Project update Silverton Wind Farm Scope of works • Silverton Wind Farm consists of two main scope of work: - Wind Farm Works (GE-CATCON) - Connection Works (TransGrid) • AGL has prepared an Overview Environmental Management Strategy (OEMS) in accordance with the project approval • Overview activ

  10. Slide 10: Wind farm works by GE-CATCON

    3. Project update Silverton Wind Farm Wind Farm Works • GE-CATCON (joint venture) has been engaged to deliver the wind farm works - Engineer, Procure, Construct (EPC) Contract • Scope of works, includes - 58 x GE 3.43-130 wind turbines - 33kV electrical reticulation (underground and overhead) and 33

  11. Slide 11: Connection Works

    3. Project update Silverton Wind Farm Connection Works • TransGrid (Network Services Provider) has been engaged to deliver the connection works for the wind farm - Project Agreement (construction) • Scope of works, includes - Wind farm 220kV substation - ~25km of 220kV transmission line - New circui

  12. Slide 12: Construction works

    3. Project update Wind Farm Works Construction works • Civil works progress: - Access road clearance: 55/61km (~91%) - Access road capping: 49/61km (~80%) • Structural works progress: - WTG foundations excavated: 50/58 (~86%) - WTG foundations poured: 45/58 (~78%) • Electrical works progress: - 33kV

  13. Slide 13: Construction works – Progress photos

    3. Project update Wind Farm Works Construction works – Progress photos Silverton Wind Farm | 23 January 2018 13

  14. Slide 14: Delivery of Wind Turbine Components

    3. Project update Wind Farm Works Delivery of Wind Turbine Components • Delivery of components commenced on 27 Nov 2017: - Over dimensional and over weight deliveries require coordination between SA and NSW Police with a change over at Cockburn on the border. • Largest wind turbine blades ever deliv

  15. Slide 15: Largest Wind Turbine Blades in Australia negotiate Silverton Rd

    3. Project update Wind Farm Works Largest Wind Turbine Blades in Australia negotiate Silverton Rd / Daydream Rd Photos provide courtesy of Helen Murray Silverton Wind Farm | 23 January 2018 15

  16. Slide 16: Largest Wind Turbine Blades delivered in Australia

    3. Project update Wind Farm Works Largest Wind Turbine Blades delivered in Australia • Local media – ABC Broken Hill, Barrier Daily Truth and Southern Cross TV (Broken Hill) • Adelaide Metro – Channel 7, 9 and 10 • National – Channel 10 (The Project) Silverton Wind Farm | 23 January 2018 16

  17. Slide 17: Assembly of Cranes

    3. Project update Wind Farm Works Assembly of Cranes • Two main cranes are currently being used for the installation of wind turbines. These cranes have been certified and registered with SafeWork NSW. - LR1450 (450 tonne crane) - LR1650 (650 tonne crane) Silverton Wind Farm | 23 January 2018 17

  18. Slide 18: Erection of Wind Turbine Components

    3. Project update Wind Farm Works Erection of Wind Turbine Components • Installation steps for erection are shown below: - Down tower assembly (DTA) + door section installed - Tower section C + B - Tower section A + Top section + nacelle - Hub + 3 blades • Blades are lifted into position using a sin

  19. Slide 19: First Wind Turbine Installed – WTG12

    3. Project update Wind Farm Works First Wind Turbine Installed – WTG12 Silverton Wind Farm | 23 January 2018 19

  20. Slide 20: Local Industry Participation

    3. Project update Wind Farm Works Local Industry Participation • Currently ~150 construction workers with approximately 40% from the local area. - Planned increase of workers for commissioning of wind turbines. • High involvement of local suppliers. - Concrete supply, plant and equipment maintenance

  21. Slide 21: Local suppliers

    3. Project update Wind Farm Works Local suppliers • Delivery of the Silverton Wind Farm to date has involved the following local suppliers / contractors - Attards Transport - Interhealth Broken Hill - Barrier Daily Truth - Judd Plumbing - Boss Construction - Lawrence Engineering - Broken Hill City C

  22. Slide 22: Turbine Manufacturing

    3. Project update Wind Farm Works Turbine Manufacturing • Wind Turbine - Manufactured in Germany - Consists of the Nacelle, Hub and electrical equipment which forms the Down Tower Assembly - Nacelles manufactured: 58/58 (100%) - Hubs manufactured: 38/58 (100%) • Towers - Manufactured in Vietnam - Se

  23. Slide 23: Connection Works – TransGrid presentation

    3. Project update Connection Works TransGrid presentation 23

  24. Slide 24: TransGrid's existing 220kV Broken Hill Substation

    3. Project update Connection Works TransGrid’s existing 220kV Broken Hill Substation Silverton Wind Farm | 23 January 2017 24

  25. Slide 25: 220kV Transmission Line

    3. Project update Connection Works 220kV Transmission Line Silverton Wind Farm | 23 January 2017 25

  26. Slide 26: Wind Farm 220kV Substation

    3. Project update Connection Works Wind Farm 220kV Substation Silverton Wind Farm | 23 January 2017 26

  27. Slide 27: 4. Community relations update

    4. Community relations update

  28. Slide 28: Community enhancement program

    4. Community relations update Community enhancement program Community Enhancement Program AGL has finalised the Community Enhancement Program for the Silverton Wind Farm, in accordance with condition 18 (schedule 2) of the project approval and will implement the program in order to give effect to th

  29. Slide 29: Solar Silverton Program

    4. Community relations update Community enhancement program Solar Silverton Program • AGL Solar commenced the property inspections with the accredited contractor on Monday, 15 January 2018, which involved assessment of: - Structural  condition of roof - Hazardous materials  No asbestos - Electrica

  30. Slide 30: Water Tank Program

    4. Community relations update Community enhancement program Water Tank Program • AGL has progressed quotes for water tanks with potential supplier and installers (plumbers) • AGL will need to arrange for property inspections to assess the following: - Structural  ground condition - Connection  roo

  31. Slide 31: Mobile Reception Program

    4. Community relations update Community enhancement program Mobile Reception Program • Mobile Black Spot Program - Silverton has been identified as a “community reported black spot”. • Black Spot Funding – Rounds 1 and 2 - Together rounds 1 and 2 are delivering almost $600 million in new investment

  32. Slide 32: Mobile Reception Program

    4. Community relations update Community enhancement program Mobile Reception Program • AGL is progressing the previous 4GX solution developed with Telstra for the mobile reception program - Installation of a 20m monopole at Telstra’s Silverton Exchange site with a 4GX small cell which will provide 4

  33. Slide 33: Mobile Reception Program

    4. Community relations update Community enhancement program Mobile Reception Program • The coverage predications below provide and indicative view of the coverage the proposed 4GX small cell would provide - Proposed 4GX solution would require a 4G 700 MHz compatible device to benefit from the improv

  34. Slide 34: Visual Impact Mitigation

    4. Community relations update Visual impact mitigation Visual Impact Mitigation AGL issued notification to the Silverton residents in accordance with condition 2 (schedule 3) of the project approval in relation to the visual impact mitigation measures outlined in condition 1 (schedule 3). • Owners w

  35. Slide 35: Community engagement

    4. Community relations update Community engagement Silverton Information Centre • AGL will be utilising the old butchers shop in Silverton during the construction of the wind farm to provide project information and updates Community information AGL contact details for community and project informati

  36. Slide 36: 5. Topics of interest

    • Visual impact assessment 5. Topics of interest

  37. Slide 37: Visual impact assessment

    5. Topics of interest Visual impact assessment Silverton Wind Farm • Green Bean Design has prepared photomontages from the following six locations (developed with the community): - Silverton township - Mundi Mundi lookout - Umberumberka House - Desert Sculpture (Living Desert) - North Silverton - Th

  38. Slide 38: Photomontage – view NW to ENE from Layard Street

    5. Topics of interest Visual impact assessment Photomontage – view NW to ENE from Layard Street 120 degree view 60 degree view Silverton Wind Farm | 23 January 2018 38

  39. Slide 39: 6. Other business

    6. Other business

  40. Slide 40: Next meeting

    Silverton Wind Farm Community Consultative Committee (CCC) • Next meeting (TBC) - Thursday, 22 March 2018 - Time: 6-8pm - Silverton Municipal Chambers, Silverton Next meeting

  41. Slide 41: Contact

    Contact AGL Energy Silverton Wind Farm 1800-039-600 AGLcommunity@agl.com.au