Slide 1: Southern Natural Gas Company 2021 Outage Review
Southern Natural Gas Company 2021 Outage Review March 17, 2021
Slide 2: Welcome
Southern Natural Gas Company, L.L.C. Welcome
Slide 3: Agenda
Agenda • Review of current and upcoming notable Outages – March/April/May/June • Unscheduled outages • North System • South System • South Louisiana System • EEC 2021 • The next outage meeting will be on April 21, at 1:30 CST • Contacts 3
Slide 4: Disclaimers
Disclaimers • Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. • Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas
Slide 5: Color Key for Maps
Color Key for Maps • Yellow – Restrictions are possible – With extended duration, restrictions could be necessary from time to time – Lower than normal pressures may be experienced – Meter(s) affected are noted with (PIN #) • Red – Restrictions are probable 5
Slide 6: Southern Natural Gas Pipeline
Southern Natural Gas Pipeline Chattanooga Rome Hartwell SC Muldon North System GA MS McConnells Tarrant Bell Mills Atlanta Aiken Pell City DeArmanville Louisville Wrens Providence Ocmulgee Pickens Reform Ellerslie Hall Gate Bear Creek Onward Auburn Thomaston Elba Rankin Selma Elmore Holy Trinity Bie
Slide 7: Southern Natural Gas Pipeline Unscheduled Outage Update
Southern Natural Gas Pipeline Unscheduled Outage Update Chattanooga Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Logansport Elba
Slide 8: SNG North System Pigging Review March/April/May/June
SNG North System Pigging Review March/April/May/June Chattanooga Pigging on NML 6-22-21 to 6-24-21 Pigging on TCI loop line Huntsville Pro. 6316 east of Pell City Pigging on NMLL 6-15-21 to 7-1-21 4-27-21 to 4-29-21 Pigging on NMLL Rome Pro. 4581-East of Providence Pro. 9951 west of Pickens 4-30-21
Slide 9: SNG North System Maint. Review March/April/May/June
SNG North System Maint. Review March/April/May/June NMLL Pipeline maintenance NML Pipeline maintenance Chattanooga NML Pipeline maintenance NMLL Pipeline maintenance 6-14-21 to 6-23-21 6-1-21 to 6-9-21 4-7-21 to 5-8-21 6-28-21 to 9-30-21 Seg.120 Cap. of 652 Mdth/d Seg.120 Cap. ofHuntsville 652 Mdth/
Slide 10: SNG South System Pigging Review March/April/May/June
SNG South System Pigging Review March/April/May/June Pigging on SM3rdLL Pigging on Thomaston Griffin 6-29-21 to 7-1-21 Pigging on SM2ndLL MS 3rdLL 3-30-21 to 3-31-21 Pro. 6130 east of 4-20-21 to 4-22-21 Ocmulgee Pro.11265 -East of Ocmulgee Pro. 5724-North of Thomaston Hartwell Pigging on SMLL Aiken
Slide 11: SNG South System Maint. Review March/April/May/June
SNG South System Maint. Review March/April/May/June Unit maintenance at Wrens MS 3-15-21 to 3-19-21 Seg. 560Hartwell capacity of 724 Hydro-test on SML Mdth/d impacted 60 Mdth/d SESH outage will reduce 4-5-21 to 4-23-21 Aiken capacity at 606400-EGT-SNG East of Ellerslie Atlanta SESH RICHLAND to zero
Slide 12: SNG South Louisiana System Pigging Review March/April/May/June
SNG South Louisiana System Pigging Review March/April/May/June Gwinville Pearl River MS LAPigging on WCFLL Franklinton 4-6-21 to 4-8-21 Pro. 4605-North of White Castle West Leg White Castle Toca East Leg Shadyside Compressor Station Southern will be conducting other general Storage Field maintenance
Slide 13: SNG South Louisiana System Maint. Review March/April/May/June
SNG South Louisiana System Maint. Review March/April/May/June Gwinville Pearl River Pipeline maintenance on The MPF2ndLL MS 5-13-21 to 5-24-21 LA Franklinton Seg. 330 capacity of 1,010 Mdth/d impacted as much as 700 Mdth/d Proj. 13543 West Leg White Castle Toca East Leg White Castle and Shadyside Sh
Slide 14: EEC line March/April/May/June
EEC line March/April/May/June Chattanooga Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Logansport Elba Rankin Bay Springs Selma
Slide 15: SNG North System Pigging Review remainder of year
SNG North System Pigging Review remainder of year Chattanooga Pigging on NML Pigging on NMLL 9-14-21 to 9-15-21 8-16-21 to 8-17-21 Pro. 9065 west of Reform Pro. 9051 east ofHuntsville Tarrant Rome AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Lou
Slide 16: SNG North System Maint. Review remainder of year
SNG North System Maint. Review remainder of year Chattanooga Huntsville Rome Muldon Shut-in test AL 10-5-21 to 10-11-21 Muldon Storage DIQ and DWQ allocated 36% Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville Pickens GA Onward Bear Creek Storage AL Logans
Slide 17: SNG South System Pigging Review Remainder of the year
SNG South System Pigging Review Remainder of the year MS Pigging on SML 7-27-21 to 7-28-21 Hartwell Pro. 9054 east of Auburn Aiken Atlanta Pigging on SML Wrens 7-20-21 to 7-22-21 GA Pro. 4637 east of Auburn Ocmulgee Hallgate AL Ellerslie Pigging on Plant Pigging on SML Auburn Thomaston McDonough lin
Slide 18: SNG South System Maint. Review Remainder of the year
SNG South System Maint. Review Remainder of the year MS Unit maint. at Auburn 10-1-21 to 10-31-21 Hartwell Seg. 460 capacity of 1943 Aiken Mdth/d reduced Atlantaby 143 Mdth/d Wrens GA Ocmulgee Hallgate AL Ellerslie Auburn Thomaston Pressure test on Moultrie L-1 Elba Gallion Selma Elmore 7-26-21 to 8
Slide 19: SNG South Louisiana System Maint. review Remainder of year
SNG South Louisiana System Maint. review Remainder of year Gwinville Pearl River MS LA Franklinton West Leg White Castle Toca East Leg White Castle and Shadyside Shadyside unit maintenance 9-1-21 to 10-31-21 Segment 340 capacity of 701 Mdth/d impacted as much as 100 Mdth/d Compressor Station Souther
Slide 20: EEC line 2021
EEC line 2021 Chattanooga Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Logansport Elba Rankin Bay Springs Selma Elmore Gallion H
Slide 21: Gas Control Contacts
Gas Control Contacts Reese Hart – Manager – (713) – 420 – 4774 (office) – (832) – 248-2937 (cell) – Maurice_hartIII@kindermorgan.com Kal Dankovich – Outage Coordinator – (713) – 420 – 7522 (office) – kalman_dankovich@kindermorgan.com Jimmy Reese – Lead Controller – (713) – 420 – 7310 (office) – jimm
Slide 22: Questions?
Southern Natural Gas Company, L.L.C. Questions? 22