Scana ASA · OSL:SCANA
Scana ASA — Investor Presentation (November 2010)
27 slides from Scana ASA's investor presentation, Nov 4, 2010

Slide 1: Scana Offshore
> Scana SCANA CREATES PROGRESS Scana Offshore

Slide 2: Scana in brief
Scana in brief Vision: World-class companies recognize Scana as their most reliable supplier. ● Scana is an industrial group with approx. 1,900 employees (of which approx. 800 are located in China) ● Established in 1987, starting off as a company primarily providing products and services to the oil

Slide 3: Oil & Gas Group Structure
Oil & Oil Gas Group & Gas Structure Group Structure Company Location Core competence Scana Offshore Vestby AS Norway Engineering, Fabrication, Assembly, Repair & Service, Welding, HVOF Coating Scana Offshore Technology AS Norway Repair & Service, Welding Scana Materials Technology Centre AS Norway M

Slide 4: Scana Companies Worldwide
Scana Companies Worldwide HQ / Scana rep. office Steel Marine Oil and gas

Slide 5: Facilities
Facilities Jørpeland Vestby • Machine shop (1.800 sq.m) • Engineering/Project Management • Welding facilities department • Mechanical workshop (800 sq.m) • Machine shop (1600 sq.m) • Sandblasting facilities (200 sq.m) • Welding facilities • Heat treatment facilities • Mechanical Workshop (900 sq.m)

Slide 6: Engineering tool box
Engineering tool box • Inventor Professional Suit • ANSYS - Design Modeller - Fatigue • DnV STIPLA – Buckling • AutoCad • ePLAN • AX data (business and project management)

Slide 7: Engineering Concept
Engineering Concept Realising customers ideas trough detail design to finished product.

Slide 8: Engineering qualifications and experience
Engineering qualifications and experience -Manufacturing -Mechanical design -Hydraulics -Automation -Material technology.

Slide 9: Typical project work flow
Typical project work flow Envelope sketch Detail design

Slide 10: Typical project work flow
Typical project work flow Manufacturing Assembly and testing

Slide 11: Typical project work flow
Typical project work flow. Ready for delivery Preparing installation

Slide 12: Typical project work flow
Typical project work flow. Installation

Slide 13: Passive Heave Compensator
Passive Heave Compensator Scana offshore scope of work •Project management •Conceptual design •Detail design •Fabrication •Assembly and testing. •Class approval (DNV) •Installation and MC Purpose •Soft pull in of riser production and loading buoy Equipment features •Pull in load 150-350 ton. •Accele

Slide 14: Production swivel stack
Production swivel stack. Scana offshore scope of work •Project management •Conceptual design •Detail design •Fabrication •Assembly and testing. •Class approval (DNV) •Installation and MC Equipment features •5 x 8” 5000 psi production lines. Duplex •Torque monitoring system •Seal fluid monitoring sys

Slide 15: Riser buoy turning device
Riser bouy turning device. Scana offshore scope of work •Project management •Conceptual design •Detail design •Fabrication •Assembly and testing. •Class approval (DNV) •Installation and MC Purpose •Active turning of riser production buoy Equipment features •Rated for Torque upto 6000kNm at 110kW hyd

Slide 16: Building and servicing Intervention Systems
Building and servicing Intervention Systems • Scana provide a unique opportunity by building seabed intervention tools, ROV tools and various pull in & connection features, by in-house material supply, machining, assembly and testing. The capabilities are flexible for customer prototype and single d

Slide 17: Maintenance and Repair
Maintenance and Repair Services: • Maintenance, repair, 5 year major surveys and re- certification of heavy drilling and production equipment • BOPs • Handling tools • Drilling equipment • Marine risers • Drilling and Workover risers • Riser tensioners / Guideline tensioners • Gate valves (API) and

Slide 18: Re-certification and Repair of BOP's and BOP equipment
Re-certification and Repair of BOP´s and BOP equipment • Ram BOP´s • Annulars • Connectors • Flex loops • Coflexip hoses • Wireline BOP´s

Slide 19: Re-certification and repairs of Riser and Guideline Tensioners
Re-certification and repairs of Riser and Guideline Tensioners Scana Riser Program • Workover Risers • Drilling Risers • Riser Tensioners • Guideline Tensioners • Strip cladding (Inconell 625) • Laser welding (Inconell 625 or Ultimet) • Thermal spraying (Inconell 625, Tungsten Carbide, etc.) Done ac

Slide 20: Welding and Machining
Welding and Machining Scana has the competence and machines to perform advanced welding and machining of heavy drilling, process equipment and components

Slide 21: Thermal Coating
Thermal Coating Product examples: Facilities: • Piston rods • Coating of up to 25m lengths • Gates & Seats • 3 HVOF systems. • Ram shafts for BOP´s • 1 Plasma transfer arc machine • Pin and Box ends • Arc Spray,Flame Spray systems. • Seal areas • Spray and fuse systems. • PVD / CVD possibilities. Ma

Slide 22: Production and Repair of Gates & Seats for Christmas trees
Production and Repair of Gates & Seats for Christmas trees Scana provides high expertise and continues developement within the productarea Gates & Seats: • High pressure gates in Inconell 718 • High pressure gates in 17.4.PH • Coated with with different Tungsten Carbides • Service and repair on all

Slide 23: Mobile Machining
Mobile Machining • Mobile Milling Unit • Mobile Turning Unit • Machining of APL Buoy • Turning of 200mm seal area performed offshore

Slide 24: Material Technology
Material Technology Laboratory and Consulting Services Scana has very strong competence within material technology, through its separate laboratory and capabilities within: • Mechanical testing • Chemical analysis • Structural analysis • Corrosion testing • Re-certification (also on-site) • Analysis

Slide 25: Certification
SCANA CREATES PROGRESS ¥e Scana Certification D rentes 205 eee queaneavon Sytem io * — * * — iNe iit for wipers othe OF Mery Korey ont Denar Certificate of Qualification _____DeT NORSKE VERITAS | Aearded _ MANAGEMENT SYSTEM CERTIFICATE CERTIFICATE ‘SCANA OFFSHORE TECHNOLOGY Condione Ne 1.08 A088 PR

Slide 26: Reasons for choosing Scana Offshore Vestby AS
Reasons for choosing Scana Offshore Vestby AS • A partner with competence and capability of doing “Development Projects” • A partner with Engineering and in-house fabrication with FAT possibilities • A partner with competence in material technology • A partner with Lifecycle serviceprogram • A repai

Slide 27: Thank you for your attention.
Thank you for your attention. Scana Offshore
Source: Internet Archive copy of scana.no
More decks from Scana ASA
Pareto Securities' Annual Energy Conference 202521 slides · Sep 10, 2025
Investor Presentation (November 2024)23 slides · Nov 12, 2024
Pareto Energy Conference 202413 slides · Sep 11, 2024
Q2 2023 Earnings Presentation25 slides · Aug 31, 2023
Q2 2022 Earnings Presentation24 slides · Aug 24, 2022
Q1 2022 Earnings Presentation23 slides · May 13, 2022