Slide 1: Environmental Management – Engineering to prevent LOPC
Environmental Management – Engineering to prevent LOPC By Ian Pannett, BP AGT Regional Engineering Authority
Slide 2: Engineering to avoid Loss of Primary Containment
Engineering to avoid Loss of Primary Containment No accidents, no harm to people, no damage to the environment Integrity Management & Process Safety activities deliver the policy and assure our facilities are managed safely with maintained integrity Achieved by: Application of a continuous ass
Slide 3: OMS and Systematic Management
OMS and Systematic Management 3.1 Risk assessment and management 3.3 Process Safety
Slide 4: Risk Assessment and Ranking
Risk Assessment and Ranking High RISK EVENT Consequence Severity Risk reduction activity implemented Event Likelihood High 4
Slide 5: Typical Bow Tie Model and Risk Barriers
Typical Bow Tie Model and Risk Barriers PREVENTION MITIGATION BARRIER CONSEQUENCE CAUSE EVENT BARRIER Hazard Loss of Process Process Blast Fire, Relief Contain Ignition Integrity control SIS Resistant Explosion System ment prevention system buildings LOPC Environmental External impact Physical Contr
Slide 6: OMS and Risk Management Cycle
OMS and Risk Management Cycle Risk Assessment Planning & Controls & Prioritisation Barriers Planned Risk Study Mitigations MOC Inspection Un-planned Routine Non-routine Incident Assurance Operating Annual Plan Procedures Mobilise Risk Update Resources Management Review Implementation & & Improvement