AGL Energy Limited · ASX:AGL
AGL Energy — Corporate Update (December 2014)
9 slides from AGL Energy's corporate update, Dec 4, 2014
Slide 1: Camden Gas Project CCC Update
Camden Gas Project CCC Update Community Consultative Committee December 2014
Slide 2: Land & Approvals
Land & Approvals 1 › The Camden North Expansion Project remains suspended. › The recent amendments to the Mining SEPP clarify that minor modifications can be made to approvals within the CSG exclusion zone. › In the next couple of months, AGL will likely apply to modify its Camden Project consents/a
Slide 3: Well Summary
2 Well Summary Production Well Number Exploration Core Number Status (as of 04/12/14) Hole Status (as of 04/12/14) Drilled (total wells) 144 Drilled, Plugged and 6 Abandoned (Camden North) Wells under 0 Drilled, Plugged and 3 construction Abandoned (remainder PEL2) Producing and 96 dewatering wells
Slide 4: Health, Safety and Environment
3 Health, Safety and Environment › EPA 2013 Compliance Audit Report » External consultants engaged to design location to handle produced water at Rosalind Park Gas Plant. › 2012-2014 Independent Environmental Audit » Draft audit report issued for AGL review. » Final report to be issued by Golder Ass
Slide 5: Field operations
4 Field operations › No CSG Drilling since September 2012. › Well workovers undertaken in the Menangle Park field. Workover rig is now operating in Gloucester until early 2015. › Ongoing monitoring of rehabilitation at EM23. › Approximately 330m of gas gathering line installed at WG04. › Spring Farm
Slide 6: Rosalind Park Gas Plant
5 Rosalind Park Gas Plant › Compressor 1 Engine overhaul » Compressor engine returned to site on 29 October. » EPL varied to include a Special Condition for Compressor 1 Start-up program over 5 weeks. » Start-up program planned to commence on 04 December 2014. › Air emissions monitoring » September
Slide 7: Rosalind Park Gas Plant
6 Rosalind Park Gas Plant › Predictive Emissions Monitoring System Trial » PEMS Trial Stage 2 planned for Compressor Engines 2 and 3 in early 2015. » PEMS to be used to predict NOx emissions. » Environment Protection Licence 12003 to be varied to incorporate PEMS trial. › Noise monitoring » 3rd quar
Slide 8: Community
Community 7 Open Day/ visits to Camden › The Society of Organic Petrologists Community & business support › Light up Camden › Lifeline Macarthur, Masquerade Ball › Christmas in Narellan AGL water portal › is a kind of one-stop-shop for info from water monitoring points across our project areas and w
Slide 9: Chief Scientist Report
Chief Scientist Report 8 AGL welcomes the report and all its recommendations, which we believe will help ensure that NSW continues to have a world-class regime for the exploration and production of natural gas › 16 recommendations for the NSW Government: » 1-4 Intent, communication, transparency and