Slide 1: Empire Pipeline Spring 2021 NGA Presentation
Empire Pipeline Spring 2021 NGA Presentation
Slide 2: System Overview
System Overview
Slide 3: Spring 2021 Empire System Overview: Weather and Throughput Statistics
Spring 2021 Empire System Overview Weather and Throughput Statistics • Winter Operations 10/1/20-3/31/21 • Peak Day Throughput 12/17/20 727 mmcf Total 176 mmcf Power Gen • Peak Day Degree Day 12/17/20 43 • Average Degree Day 2020-2021 30 • Average Degree Day 2019-2020 30 • Normal Degree Day 34 • Thr
Slide 10: 2021 Construction and Maintenance Schedule