Northland Power Inc. · TSX:NPI

Northland Power — Q1 2025 Earnings Presentation

24 slides from Northland Power's earnings presentation, May 14, 2025

  1. Slide 1: Investor Presentation

    Investor Presentation May 2025 Baltic Power, Poland

  2. Slide 2: Northland Overview

    Investor Relations: Public Northland Overview Northland Overview 37+ >1,200 ~15yrs Years of success Employees1 Weighted average contracted revenue life2 Onshore Renewables 2.2 GW Under 3.4 GW 90%+ Contracted revenue construction3 In operations3 Natural Gas & Utilities 722 MW of natural gas across fo

  3. Slide 3: Global Footprint

    Investor Relations: Public Global Footprint Canada Northern Europe (offshore wind) Operating Operating 1,511 MW 1,192 MW In Construction 1,140 MW United States Operating Colombia Spain Taiwan 220 MW Operating Utility Operating In Construction 500,000+ customers 559 MW 1,022 MW Operating 16 MW Operat

  4. Slide 4: Significant Construction Pipeline Secured Financial Growth

    Investor Relations: Public Significant Construction Pipeline Secured Financial Growth 2.4 GW of growth Investment grade balance sheet with fully funded secured through 2027 Including construction program Construction 1,140 MW Projects ~6.0 GW1 1,022 MW 2 Adjusted EBITDA Baltic 250 MW Power 7-10% $1.

  5. Slide 5: Growth Markets

    Investor Relations: Public Growth Markets Priority Markets Canada Offshore Taiwan Wind South Poland Scotland Korea Scotland 10 GW (Excl. 2.2 GW of projects under construction) Development Onshore Renewables Pipeline Ontario New York Alberta US South Korea EBSA rate growth Poland Ne w Natural Gas bas

  6. Slide 6: Construction Progress Milestones

    Investor Relations: Public Construction Progress Milestones Hai Long Baltic Power Oneida 1GW Offshore Wind, Taiwan 1.1GW Offshore Wind, Poland 250MW Battery Storage, Canada Executed Revenue Contract Executed EPC Construction Contracts Executed Financing Starts In-water Construction N/A Battery Deliv

  7. Slide 7: Hai Long & Baltic Power Construction Milestones & Status

    Investor Relations: Public Hai Long & Baltic Power Construction Milestones & Status Fully-funded1 construction program with first power expected for Hai Long in H2 2025 and H1 2026 for Baltic Power Hai Long • First turbine installation • First foundation installation • Offshore substation • Offshore

  8. Slide 8: Adjusted EBITDA Diversification by Technology & Geography

    Investor Relations: Public Adjusted EBITDA1 Diversification by Technology & Geography By 2027, cash flow growth will diversify across more regions providing higher quality and stability 2024A Adjusted EBITDA 2027F Adjusted EBITDA Utility ~9% Efficient Natural Gas North Sea Utility ~11% ~11% ~30% Off

  9. Slide 9: Forward Looking Statements

    Investor Relations: Public Forward Looking Statements This written and accompanying oral presentation contains certain forward-looking statements and information within the meaning of Canadian securities laws concerning the business and operations of Northland Power Inc. and are provided for the pur

  10. Slide 10: Northland Power Investor Relations Contact

    Northland Power Adam Beaumont, Senior Vice 30 St. Clair Avenue West, Email: investorrelations@northlandpower.com President of Capital Markets 3rd Floor 647.288.1019 Website: northlandpower.com Toronto, ON Canada M4V 3A1

  11. Slide 11: Appendix

    NORTHLAND 4 ee POWER Appendix

  12. Slide 12: Leadership Team

    Investor Relations: Public Leadership Team Christine Healy - President & CEO • Christine most recently served as President of AMEA (Asia, Middle East, Australia) for AtkinsRealis. • Previous experience at TotalEnergies includes Senior Vice President for Carbon Neutrality and Continental Europe, Pres

  13. Slide 13: Hai Long (1.0 GW)

    Investor Relations: Public Hai Long (1.0 GW)1 • Stable revenue through 20-year FIT and 30-year Corporate Power Purchase Agreement with S&P AA- rated counterparty • Construction is fully funded, with long-term non-recourse project financing secured • Material contribution to Northland’s Adjusted EBIT

  14. Slide 14: Hai Long

    Investor Relations: Public Hai Long Installation of Offshore Substation Topside (2 of 2) - March 2025 14

  15. Slide 15: Hai Long

    Hai Long First turbine installed

  16. Slide 16: Hai Long

    Hai Long Delivery of the 219 Project's Pin Piles. March 2025

  17. Slide 17: Baltic Power (1.1 GW)

    Investor Relations: Public Baltic Power (1.1 GW)1 • Construction is fully funded and long-term project financing with 25 financial Baltic Power institutions is secured • Stable cash flow from 25-year Contract for Differences (CfD) revenue contract that has indexation based on the Polish CPI commenci

  18. Slide 18: Baltic Power

    Baltic Power Transition pieces sail out of Newcastle, England. March 2025

  19. Slide 19: Baltic Power

    Baltic Power O&M Base Grand Opening May 2025 and Turbine towers at the Pre-Assembly Harbour

  20. Slide 20: Baltic Power

    Investor Relations: Public Baltic Power Baltic Power Baltic Power Onshore Substation, Offshore September Substation 2024 Topside Sail Out March Monopile Foundation Install February 2025 2025 20

  21. Slide 21: Oneida (250 MW)

    Investor Relations: Public Oneida (250 MW)1 • 250 MW (4-hour duration) Lithium-Ion Battery Storage in Oneida Southwestern Ontario Battery • One of the largest battery storage project in Canada and North Storage America • 20-year capacity contract with the IESO • Strong group of equity partners with

  22. Slide 22: Oneida

    Oneida Main substation area completed with high voltage switches, breakers and transformers April 2025

  23. Slide 23: Oneida

    Oneida Megapacks on Foundations, April 2025

  24. Slide 24: Partners and Contractors

    Investor Relations: Public Partners and Contractors Partner(s) High Quality Contractors Hai Long Baltic Power Oneida 24

Northland Power — Q1 2025 Earnings Presentation on 6ix