Arcelormittal South Africa Limited · JSE:ACL
Arcelormittal South Africa — Technical Presentation (June 2011)
17 slides from Arcelormittal South Africa's technical presentation, Jun 8, 2011
Slide 1: ArcelorMittal South Africa Vanderbijlpark Works
ArcelorMittal South Africa Vanderbijlpark Works Heinrich Kriel 2011
Slide 2: Agenda
Agenda • ArcelorMittal South Africa’s standing • Process • Main Industries • Sales • Corporate Responsibility 1
Slide 3: ArcelorMittal South Africa at a glance
ArcelorMittal South Africa at a glance •Largest steel producer on the African continent •Relationship with ArcelorMittal facilitates world- with capacity of 8.0 mt of liquid steel per annum of class R & D, best practice processes, aggressive which 65% is flat and 35% is long procurement contracts, a
Slide 4: A Committed South African Citizen
A Committed South African Citizen • ArcelorMittal South Africa’s long standing commitment to South Africa will continue – Approximately ZAR15bn invested since 2001/2 including the payment of R2,8 billion for the undivided share of the mining right over Sishen and R8bn in capex over last five years •
Slide 5: ArcelorMittal in South Africa
ArcelorMittal in South Africa Flat Steel Products shipped* HR issues* • Vanderbijlpark Works – 2 575 kt • Full time employees 9 145 for the year • Saldanha Works – 904 kt • Employees per million tons prod = 1 612 Long Steel Products shipped* • Revenue per head R3.3m (US$0.5m) • Newcastle Works – 1 3
Slide 6: Flat carbon steel - Vanderbijlpark Works
Flat carbon steel - Vanderbijlpark Works 2010 • Liquid steel production (‘000 tons) 3 108 • Sales tons 2 611 • Domestic percentage of total sales 78 % • Domestic percentage (excl SS) 73% • Manpower 4 450 • Area of site 2 300 Ha • Perimeter 20 km • Rail networks 256 km and 34 locomotives • Electricit
Slide 7: Company Structure
Company Structure ArcelorMittal ArcelorMittal South Africa Limited Flat steel products Long steel products Vanderbijlpark Works Saldanha Steel (Pty) Ltd Newcastle Works Vereeniging Works Hot rolled Hot rolled coil Rolled profiles Rolled profiles (Vereeniging) Heavy Plates - thin and ultra thin Speci
Slide 8: Vanderbijlpark Works Management Team
Vanderbijlpark Works Management Team Heinrich Kriel General Manager Vanderbijlpark Works Gerhard Moolman Erwee Lourens Albert Swanepoel Alvin Govender Chris van Dijk Dirk Lourens Werner Venter Works Manager Plant/Works Works Manager Works Manager Works Manager Works Manager Manager Manager Central Q
Slide 9: Vanderbijlpark Works Process Configuration
Vanderbijlpark Works Process Configuration 8
Slide 10: Production and sales history (000t)
Production and sales history 1000 Export sales Local sales Liquid steel production 800 600 (000t) 400 200 0 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 2006 2007 2008 2009 2010 2011 9
Slide 11: Domestic Sales: Prime Volume
Domestic Sales: Prime Volume 2010 Tin DWI Cold Rolled Tin 6% Q & T Plate 14% Colour Appliance 0% 6% 1% Plate Normal Colour Normal 6% 4% Hot Rolled to DSP Electro 3% 4% Hot Rolled P&O 6% Hot Dipped 17% Hot Rolled Coils <= 1.5 mm Hot Rolled Dry 0% 33% 10
Slide 12: Domestic sales: Prime Volume per segment
Domestic sales: Prime Volume per segment 2010 Automotive Primary Transformation 8% 19% Building Exterior - Roofing & Cladding 14% Pressure Vessel 3% Packaging 14% Other Transport 0% Civil Engineering Machinery and 33% equipment Converters & Re- 3% rollers 3% Domestic Appliances Distribution-Traders
Slide 13: Export Sales: Prime Volume per Segment
Export Sales: Prime Volume per Segment 2010 Tin Cold Rolled Plate Normal 0% 19% 3% Hot Rolled P&O Colour Normal 21% 1% Hot Dipped 5% Hot Rolled Coils <= 1.5 mm 0% Hot Rolled Dry 51% 12
Slide 14: Export: Volumes per Region
Export: Volumes per Region 2010 Asia 30% Africa 70% 13
Slide 15: Financial history
Financial history (milj) R 7,000 Revenue 50% Operating profit R 6,000 Margin 40% R 5,000 30% R 4,000 20% R 3,000 10% R 2,000 0% R 1,000 R0 -10% Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 -R 1,000 -20% 2006 2007 2008 2009 2010 2011 14
Slide 16: Implementing a Corporate Responsibility strategy
Implementing a Corporate Responsibility strategy Human Resources Environment Communities Shareholders Social Environmental Communities Corporate Commitments Commitments Commitments Governance and sustainability reporting • Health & Safety • Waste disposal • Local economic • Board development indepen
Slide 17: Questions
a“ ArcelorMittal
ArcelorMittal South Africa — Technical Presentation (June 2011) on 6ix