Slide 1: A Leading, Low-Cost North-American Copper Producer
A Leading, Low-Cost North-American Copper Producer November 2026

Slide 2: Disclaimer
Disclaimer This presentation contains forward-looking statements and forward-looking information (collectively referred to as “forward-looking statements”) within the meaning of applicable Canadian securities legislation and the United States Private Securities Legislation Reform Act of 1995, Sectio

Slide 3: Trekor – Investment Highlights
Trekor – Investment Highlights A Leading North American Copper Producer Growing Copper Future growth Producer pipeline Two operating mines Advanced projects with delivering strong district-scale potential GIBRALTAR FLORENCE COPPER results today. for long-term growth. YELLOWHEAD ALEY Focused in North

Slide 4: Trekor – Operations and Projects
Trekor – Operations and Projects North American Asset Base Focused in North America 03 Yellowhead Project 01 Gibraltar Mine British Columbia | Arizona Thompson-Nicola, BC Cariboo-Chilcotin, BC DEVELOPMENT OPERATING Commodity: Copper (w/ Gold and Silver) LOM Avg. Annual Production: Commodity: Copper,

Slide 5: Copper Price Outlook
Copper Price Outlook Recent copper price strength driven by: Structural Demand Trends Electrification boom: electric vehicles, renewable energy, and grid upgrades require large amounts of copper Data center expansion: AI and cloud computing are increasing power infrastructure demand Growing urbaniza

Slide 6: Copper Price Outlook
Copper Price Outlook Highlights from S&P Global Copper Study (January 2026) Primary global copper production is forecast to rise from 23 million metric tons (MMT) in 2025 to a peak of 27 MMT in 2030, before falling to 22 MMT by 2040 Global demand for copper will increase by 50% over current levels b

Slide 7: Recent Results – Q3 2026
Recent Results – Q3 2026 Record Quarter Driven by Strong Copper Prices & Production $342M $164M $122M $55M $0.15/share REVENUE ADJUSTED EBITDA OPERATING CASH FLOW ADJ. NET INCOME Operational momentum $200 $500 • 41M lbs consolidated copper production • Gibraltar produced 34M lbs of copper $150 $375

Slide 8: Gibraltar Copper Mine – A foundation of stable cashflow
Gibraltar Copper Mine – British Columbia A foundation of stable cashflow MINE TYPE STAGE ANNUAL PRODUCTION Open Pit – Cu/Mo Producing 130Mlbs (~60kt Cu) CASH COSTS (LOM) MINE LIFE REPLACEMENT VALUE US$2.30/lb 18 Years +US$1 billion1 1. Calculated using US$15,000 / ton capacity multiplied by capacity

Slide 9: Gibraltar Copper Mine – Large-Scale, Steady-State Mine
Gibraltar Copper Mine – Large-Scale, Steady-State Mine Value Creation 1999 Acquired for $1 2004 Restarted operations Invested ~C$800 million to expand 2006 to 2013 and modernize the mine to 85,000 tons per day Operating steady-state at expanded 2014 to current capacity Purchased 25% of mine from JV

Slide 10: Gibraltar Mine – Cash Flow Growth from Stable Mining Operation
Gibraltar Mine – Cash Flow Growth from Stable Mining Operation Leverage to copper has resulted in strong earnings growth and cash flow generation Foundation of stable cash flow for Trekor throughout the copper price cycle Stringent cost management practices ensure positive operating cash flow mainta

Slide 11: Florence Copper – Pathway to a low-cost future
Florence Copper – Arizona Pathway to a low-cost future MINE TYPE STAGE PROCESSING In-situ Leach Producing SX/EW PRODUCTION (PER YEAR)* ESTIMATED CASH COSTS* MINE LIFE* 85Mlb (~40kt) Cu US$1.11/lb LOM 22 Years (1) Based on the Florence 43-101 Technical Report with an effective date of March 15, 2023.

Slide 12: Florence Copper – First Greenfield ISCR Operation
Florence Copper – First Greenfield ISCR Operation Construction completed on time and on-budget in Q4 2025 Development Timeline 2014 Property acquisition 2018–2020 Production Test Facility (PTF) September 2023 Final permits issued by US EPA Initiated construction of commercial January 2024 production

Slide 13: Florence Copper – First Greenfield ISCR Operation
Florence Copper – First Greenfield ISCR Operation The first new copper producer in the United States in more than a decade Project Highlights1 Mine Life 22 years 85 million pounds (~40k metric Annual production capacity tonnes) of copper cathode US$930 million @ US$3.75/lb After-tax NPV(8%) copper A

Slide 14: In-Situ Copper Recovery (“ISCR”)
In-Situ Copper Recovery (“ISCR”) Production Test Facility (“PTF”) • PTF constructed in 2018 and operated for 18 months • 24 wells in test wellfield and SX/EW plant • The PTF demonstrated successful copper production and the ability to maintain hydraulic control of fluid within the oxidized zone • Va

Slide 15: Florence Copper – Operations / Wellfield
Florence Copper – Operations / Wellfield • Commenced wellfield operations in November 2025 with ~90 production wells • First copper cathodes produced in February • Copper Cathode Production • Q1 2026: 1.5 million pounds • Q2 2026: 5.2 million pounds • Q3 2026: 7.0 million pounds • Wellfield drilling

Slide 16: Florence Copper – Overall Performance To-Date
Florence Copper – Overall Performance To-Date Solid progress on ramp up to-date. Continuous month-over-month production improvements No significant wellfield performance issues – flow rates and leaching better than modeled Work ongoing to optimize wellfield performance (balance between solution flow

Slide 17: Benefits of ISCR
Benefits of ISCR Arizona Conventional Open-pit Mine vs. Florence Copper Project 65% 75% 78% Energy Carbon Water Use Consumption Emissions (gal/lb Cu) (kWh/lb Cu) (kg Co2/lb Cu) Other Benefits Low Cost Limited land disturbance Small environmental footprint (less than a Low dust emissions square mile)

Slide 18: Florence Copper – Strategic Partnership with Mitsui
Florence Copper Strategic Partnership with Mitsui LME vs COMEX $7.00 • Provided US$50 million of construction financing (Deal closed December 2023) $6.50 • Strong endorsement of project valuation: 50% Tariff on Copper Imports Announced o Initial US$50 million investment for 2.67% copper stream $6.00

Slide 19: Looking to the Future
Trekor Metals Looking to the Future 19

Slide 20: Yellowhead Copper Project – Advanced Staged Project
Yellowhead Copper Project – Advanced Staged Project Project Economics1 Initial capital cost C$2.0 billion After-tax NPV8 C$2.0 billion @ US$4.25/lb copper LOM strip ratio 1.4:1 Onsite operating cost C$12.89 per tonne milled • First 5 years: 206M lbs copper Annual production • LOM average: 178M lbs c

Slide 21: Yellowhead Copper Project – Value to be Unlocked
Yellowhead Copper Project – Value to be Unlocked A top tier copper project in quality jurisdiction • Ranks comparably among other North and South American copper development projects • Minimal value being ascribed for Yellowhead by analysts / zero value in Trekor equity Project Economics (After-tax)

Slide 22: Yellowhead Copper Project – Value to be Unlocked
Yellowhead Copper Project – Value to be Unlocked Recent Project Acquisition P/NAV Cactus NPV8 (C$ billions) $3.1 Hudbay’s acquisition of Arizona Sonoran (Cactus project): Acquisition Value (C$ billions) $2.0 • ~C$2.0 billion (~36% premium) P/NAV 0.63 • Highlights market appetite for de-risked, North

Slide 23: Yellowhead Copper Project – Recent Highlights
Yellowhead Copper Project Recent Highlights Provincial / Federal EA Process: Commenced Environmental Assessment review process July 2025 New technical report issued July 2025 Detailed Project Description submitted to EAO June 2026 Consent agreement signed by BC and Simpcw July 2026 EA Readiness Deci

Slide 24: Yellowhead Copper Project – Estimated Development Timeline
Yellowhead Copper Project Estimated Development Timeline Yellowhead Is Here Application Final Investment Early Engagement Process Review Phase Decision and Planning Phase Planning Phase 2024 2025 2026 2027 2028 2029 2030 Pre-Early Readiness Decision Phase / Impact Assessment Application Engagement D

Slide 25: New Prosperity Gold-Copper Project
New Prosperity Gold-Copper Project Project Highlights • One of the largest undeveloped Copper-Gold porphyries in the world • Life of mine average annual production of +400,000 gold equivalent ounces over a 33 year mine life (based on 2009 Technical Report*) Recent Development • Agreement signed with

Slide 26: Aley Niobium Project
Aley Niobium Project Project Highlights1 P&P Reserves 84M tonnes grading 0.5% Nb2O5 Mine Life 24-years Annual production Capacity 14,00 tonnes of ferroniobium Project Update • Floatation Process Development - Development of a proprietary flotation process, resulting in higher niobium recoveries and

Slide 27: Why Invest in Trekor
Why Invest in Trekor The Valuation Case Trekor Valuation Waterfall • Significant gap between asset NPV and market cap $6,000 $540 $5,360 o Base NAV for Gibraltar and Florence @ US$5.50/lb $5,000 $2,500 copper $4,000 >C$2 billion Gap o Not including Yellowhead, New Prosperity or Aley $3,400 $3,000 •

Slide 28: Appendix
Appendix

Slide 29: Capital Structure & Coverage
Capital Structure & Coverage Analyst Coverage Target Price & Recommendation Listed TSX:TKO / NYSE:TGB / LSE:TKO Buy C$16.00 Nov ’26 Share Price 52 Week High / Low Shares Outstanding* Buy C$15.00 Nov ’26 C$8.17 C$13.60 / C$5.51 367 Buy C$15.50 Nov ’26 US$5.71 US$9.82 / US$3.93 Buy C$14.00 Nov ’26 Mar

Slide 30: Operating Costs
Operating Costs Breakdown of Key Operating Costs Gibraltar Florence Copper Other 9% Other Labour 20% Labour 26% 22% Maintenance 24% Consumables Diesel 22% 10% Sulphuric Acid 36% Consumables 31% Sensitivity: Sensitivity: Diesel – C$0.10/litre price = Sulphuric Acid – US$100/ton US$0.025/pound copper

Slide 31: Florence Copper Project – Two Phase Development Approach
Florence Copper Project – Two Phase Development Approach • PTF development and construction • Issued updated 43-101 Technical Report starts (~US$25M) (March) 2018 • Final UIC permit issued from US EPA • Wellfield & SX/EW plant commissioned (Q3), operations commenced in (Q4) (September) 2023 • Site p

Slide 32: Gibraltar Mine – Acquisition of Gibraltar Minority Interest
Gibraltar Mine – Acquisition of Gibraltar Minority Interest Variable payments self-funded with incremental cashflow from Gibraltar Illustrative Payment Schedule • Trekor acquired the remaining 25% interest in Gibraltar in @ US$4.25/lb Copper two separate transactions: $50 • Sojitz (12.5% interest ac

Slide 33: Credit Profile
Credit Profile Substantial improvement in leverage metrics expected with increasing EBITDA and Florence construction capex complete • Trekor maintains reasonable leverage levels and balances capital LTM Adjusted EBITDA needs through a combination of debt, equity and internally generated cash flow •

Slide 34: Proactively Reducing Impact of Cu Price Volatility
Proactively Reducing Impact of Cu Price Volatility Hedging policy in place to reduce the short-term impact of a decline in the price of copper Defensive Hedging Strategy • Trekor’s hedging strategy is designed to secure a Historical Copper Hedging and Cu Production (Mlbs) minimum price for a signifi

Slide 35: 2025 Sustainability Highlights: Growth with Purpose
2025 Sustainability Highlights: Growth with Purpose 35

Slide 36: A Proven Team of Mine Builders and Value Creators
A Proven Team of Mine Builders and Value Creators Senior Management Board of Directors Ron Thiessen – Chairman Rita Maguire • President, CEO and Director of Northern • Lawyer based in Arizona and focused on Dynasty Minerals. water, environmental, mining and • Chartered Professional Accountant with a

Slide 37: Appendix – Reserves & Resources
Appendix – Reserves & Resources Gibraltar Florence Copper Short Grade Contained Metal Short Tons Grade Contained Metal Category Tons Category Cu (%) Mo (%) Cu (billions lbs) (millions) Cu (%) Cu (billions lbs) (millions) Sulphide Mineral Reserves as of December 31, 2025 at a 0.15% Cu cut-off Mineral

Slide 38: Appendix – Reserves & Resources
Appendix – Reserves & Resources Yellowhead Aley Contained Contained Grade Tonnes Grade Tonnes Metal Category Metal Category (millions) (millions) Cu Nb205 (%) Nb (million kg) Cu (%) Au (g/t) Ag (g/t) (billion lbs) Mineral Reserves Effective September 15, 2014 at a 0.30% Nb2O5 cut-off Mineral Reserve

Slide 39: Appendix – Reserves & Resources
Appendix – Reserves & Resources New Prosperity Tonnes Grade Contained Metal Category (millions) Au (g/t) Cu (%) Au (M oz) Cu (B lb) Mineral Reserves Effective November 2, 2009 at a C$5.50 NSR/t cut-off Proven 481 0.46 0.26 7.1 2.8 Probable 350 0.35 0.18 3.9 1.4 Total P&P Reserves 831 0.41 0.23 11.0

Slide 40: Appendix – NI 43-101 Compliance
Appendix – NI 43-101 Compliance • Unless stated otherwise, Trekor Metals Limited (the “Company”) has prepared the technical information in this presentation including Mineral Reserve and Mineral Resource estimates (“Technical Information”) based on information contained in the technical reports, new

Slide 41: Investor Relations
TSX: TKO NYSE: TGB LSE: TKO Investor Relations Brian Bergot, Vice President, Investor Relations Office: 778.373.4554 Email: bbergot@trekormetals.com Keep up with the latest news and project updates from Trekor @TrekorMetals Scan to Subscribe

Slide 42: Thank You!
> oO > = c ie] < =
Source: company website
More decks from Taseko Mines Limited
Trekor Metals — Technical Presentation (October 2026)54 slides · Oct 8, 2026
Trekor Metals — Investor Presentation (October 2026)42 slides · October 2026
Trekor Metals — Investor Presentation (September 2026)40 slides · September 2026
Investor Presentation (April 2026)40 slides · April 2026
Investor Presentation (January 2026)41 slides · January 2026
Investor Presentation (November 2025)39 slides · November 2025