ReVolve Renewable Power Corp · CSE:REVV

ReVolve Renewable Power — Investor Presentation (December 2022)

18 slides from ReVolve Renewable Power's investor presentation, December 2022

  1. Slide 1: Corporate Presentation

    Slide 1: Corporate Presentation

    CORPORATE PRESENTATION DECEMBER 2022 TSXV:REVV

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    2 Disclaimer This corporate presentation (“CP”) does not purport to be all-inclusive or necessarily to contain all the information that a prospective investor may desire in investigating the Company and may be subject to updating, revision or amendment. Certain disclosures may constitute "forward-lo

  3. Slide 3: Investment Opportunity – What We Offer

    Slide 3: Investment Opportunity – What We Offer

    3 Investment Opportunity – What We Offer ESG focused investment opportunity – renewable energy project development and generation key driver toward ‘net zero’ emissions target. Diversified investment strategy providing investors access to higher development returns from utility scale project develop

  4. Slide 4: Company Background

    Slide 4: Company Background

    4 Company Background WHO WE ARE Revolve Renewable Power Corp. (TSXV:REVV), established in 2012 is a renewable energy company focused on the development of utility scale wind, solar, battery storage projects and distributed generation projects in the US and Mexico. WHAT WE DO The company operates a r

  5. Slide 5: Investment Highlights

    Slide 5: Investment Highlights

    5 Investment Highlights Proven track record – over 10 years of project development experience successfully achieved. Successfully developed over 300MW of projects (525,000t avoided CO2) to a fully permitted, ready to build (RTB) stage. Realized a 5X ROI (5 times Return on Investment) for shareholder

  6. Slide 6: Management Team

    Slide 6: Management Team

    6 Management Team x Steve Dalton, x Omar Bojorquez, CEO & Director President & Director Co-founder of the Company and has led the Co-founder of the Company, 12+ years experience in the development of the business since inception. Broad renewable energy industry including leading the based experience

  7. Slide 7: Market Opportunity – Underpinning Growth

    Slide 7: Market Opportunity – Underpinning Growth

    7 Market Opportunity Finance: Corporate –ofUnderpinning Growth procurement clean energy in the U.S. Transition to Net Zero Emissions is the key driver for the renewable energy Renewable RenewableEnergy contracted capacity by US contracted bycorporations corporations, Largest corporate offtakers, 202

  8. Slide 8: Business Units

    Slide 8: Business Units

    8 Business Units Project Type Development Timeline Business Model Shareholder Value ▪ Wind, Solar & Battery ▪ 3 to 4 years from ▪ Develop and sell / exit at ▪ Large milestone 1 Utility Scale Storage technology greenfield to ready to build RTB to large utilities and payments based on ▪ Utility scale

  9. Slide 9: Business Model – Utility Scale

    Slide 9: Business Model – Utility Scale

    9 Business Model – Utility Scale 3-4 year development timeline Project Origination Project Development Construction Ready Project Exit 1 2 3 4 • Identify and obtain land • Project development • All permitting requirements • The Company generally rights for greenfield wind, activities consisting of s

  10. Slide 10: Business Model – Utility Scale: Illustrative Investment Case

    Slide 10: Business Model – Utility Scale: Illustrative Investment Case

    10 Business Model – Utility Scale Illustrative Investment case – 200MW Solar Project Project Origination Project Development Construction Ready Project Exit 1 2 3 4 US$400k US$600k US$1m US$2m* total investment Project Investment Period 3 to 4 years Investment Returns $40-50k per MW* US$8-10m total

  11. Slide 11: US Development Portfolio

    Slide 11: US Development Portfolio

    Emery Solar & Storage Vernal BESS 11 US Limon Solar & Storage • Located in Emery County, Utah • Located in Uintah County, Utah • 150MW Solar & Battery Storage project • 50MW Battery Storage project • Located in Lincoln County, Colorado DEVELOPMENT • Site control secured • Site control secured • 100M

  12. Slide 12: Mexican Development Portfolio

    Slide 12: Mexican Development Portfolio

    12 MEXICAN Presa Nueva Wind Project El 24 Wind Project DEVELOPMENT • Located in Nuevo Leon • Located in Tamaulipas • 400MW Wind project across two phases • 103.4MW Wind project El Mentillo Wind, Nuevo Leon: • Mid stage of development PORTFOLIO • Advanced stage of development • Site Control establish

  13. Slide 13: Business Model - Distributed Generation

    Slide 13: Business Model - Distributed Generation

    13 Business Model - Distributed Generation Newly launched division in April 2022 targeting projects up to 5MW are installed at the customer premises (rooftop solar, CHP, battery storage). Customers are typically commercial and industrial scale, including manufacturing operations and hotel chains. Re

  14. Slide 14: Business Model - Distributed Generation: Illustrative Investment Case

    Slide 14: Business Model - Distributed Generation: Illustrative Investment Case

    14 Business Model - Distributed Generation Illustrative Investment Case – 2MWh Battery Storage System LONG TERM POWER PROJECT CONSTRUCT FINANCE PURCHASE ORIGINATION AGREEMENT 3 months 6 months 10 Years Revenue / Cashflow Project Investment Period Investment Returns: US$1m total investment financed b

  15. Slide 15: Distributed Generation - Portfolio

    Slide 15: Distributed Generation - Portfolio

    15 Distributed Generation - Portfolio Centrica Business Solutions (Mexico) – Strategic Acquisition to Fast Track Move into Distribution Generation Market: Acquisition completed in August 2022 and involved ~6MW operational / under construction distributed generation portfolio including cash & spare p

  16. Slide 16: Looking Forward – What to Expect

    Slide 16: Looking Forward – What to Expect

    16 Looking Forward – What to Expect Active Utility Scale Development Programme Combined with Fast Growing Distributed Generation Business Utility Scale 1.25GW US solar & storage projects moving to mid stage development and RTB. Ongoing interconnection and permitting work on projects in Utah, Colorad

  17. Slide 17: Share Information

    Slide 17: Share Information

    17 Share Information Market Price Information (source: TSX.com) Share Structure SHARE INFORMATION NO OF (as at September 30, SHARES 2022) Ticker Symbol TSX.V: REVV Shares issued & outstanding 54,905,547 Cash & Deposits C$2.8m Compensation Options (@ $0.50) 4,000,000 Warrants (@$0.75) expire Debt C$1

  18. Slide 18: For further information, please contact

    Slide 18: For further information, please contact

    18 For further information, please contact Email: IR@revolve-renewablepower.com Phone: +1 778 885 5550 Canada – Registered Office 2200-700 W. Georgia Street Vancouver BC V7Y 1K8 Canada Mexico Office US Office Hamburgo 70, int. 206 1 - 4550 E. Easter Avenue Juárez, C.P. 06600 Suite 200 Alcaldía Cuauh

Source: Internet Archive copy of revolve-renewablepower.com

More decks from ReVolve Renewable Power Corp

All 48 ReVolve Renewable Power decks