  1. Slide 1: Intimation of Investor Meet / Site Visit

    Se vedanta ca HZL/ 2019-Secy August 07,2019 BSE Limited National Stock Exchange of India Limited Phiroze Jeejeebhoy Towers Exchange Plaza Dalal Street, Plot No.C/1, G Block Mumbai 400 001 Bandra — Kurla Complex Bandra (East) Mumbai 400 051 Scrip Code: 500188 Trading Symbol: “HINDZINC” Sub:- Intimati

  2. Slide 2: Hindustan Zinc Limited Investor Presentation August 2019

    Hindustan Zinc Limited I N V E S T O R P R E S E N TAT I O N AUGUST 2019

  3. Slide 3: Cautionary Statement and Disclaimer

    Cautionary Statement and Disclaimer The views expressed here may contain information derived from publicly available sources that have not been independently verified. No representation or warranty is made as to the accuracy, completeness, reasonableness or reliability of this information. Any forwa

  4. Slide 4: A premium zinc-lead and silver company

    A premium zinc-lead and silver company Vedanta set to become the largest Zinc-Lead miner globally in the next 2 years 2 nd L A R G E S T Z I N C - L E A D M I N E R G L O B A L LY 2000 2019 Mined metal in kt 1500 4 th 1000 HZL L A R G E S T Z I N C - L E A D S M E LT E R G L O B A L LY 500 Largest 0

  5. Slide 5: Hindustan Zinc – A sustainable enterprise

    Hindustan Zinc – A sustainable enterprise Sustainability efforts are centred around safe mining and optimizing waste, water, land & carbon footprint Safe Mining – Setting right Culture • 60% of tailings to be used for void filling in UG mines Paste fill plant back fill, Reduce land required for tail

  6. Slide 6: Social Licence to Operate - Impactful projects target key areas of need & development

    Social Licence to Operate - Impactful projects target key areas of need & development 5

  7. Slide 7: Strong foundation driving growth and transformation

    Strong foundation driving growth and transformation R&R ZINC – LEAD SILVER COSTS 1.35 mT 1,000 t 600 mT 1.2mT 800 t $900 /t 400 mT 1.0 mT 679 t $1000 /t • Expanding R&R across the mines • Completion of 1.2 mtpa capacity in H2 • Focus on silver rich deposits Key structural initiatives on • Digital tr

  8. Slide 8: Confident of delivering FY2020 guidance

    Confident of delivering FY2020 guidance Production ramp up to 1.0 million tonne mined metal H2 – Completing 1.2 mtpa project activities 1200 YOY +7% 1,200 1000 1,000 Mined metal , H1 vs H2 Mined Metal in kt 800 800 600 52% 53% 54% UG CAGR 600 65% 400 39% 400 200 200 0 - FY2014 FY2015 FY2016 FY2017 F

  9. Slide 9: Setting Business for 1.35 mtpa and beyond – concurrent mining

    Setting Business for 1.35 mtpa and beyond – concurrent mining Rampura Agucha (3.3 → 4.5 → 5) Sindesar Khurd (5.3 → 6 → 8) Zawar ( 2.8→ 4.0 → 8 ) Safe Transition Fully Digitised Mine Integrating Mines Kayad (1.2, extending mine life) Rajpura Dariba (0.9 → 2 → 4) Sindesar Khurd and Rampura Agucha are

  10. Slide 10: On track to become top silver producers globally

    On track to become top 3 silver producers globally Fastest growing silver company with a CAGR of 18% Ranked 9th globally in primary silver production 1000 2500 Hindustan Zinc 750-800 2000 679 Silver in tonnes 558 1500 425 453 328 1000 500 0 FY2015 FY2016 FY2017 FY2018 FY2019 FY2020 E Target E* 1 2 3

  11. Slide 11: Reserve & Resource upgrade – World class technology adopted

    Reserve & Resource upgrade – World class technology adopted Opportunities across mines ( 400 → 600 mT ) Motorised Motorised Directional Drilling technology creates Directional multiple branches from a parent hole resulting in Drilling saving cost and time Mine Technical program • Galena & Main orebo

  12. Slide 12: Time bound cost optimization programs in place

    Time bound cost optimization programs in place Structural cost optimization Zinc COP: $1000 per MT 1 Technology Ore to metal index Advanced Process Controls $ 17 2 Productivity Autonomous machines Digitalisation of mines Current efficiency $ 15 Higher development factor $7 3 Mining Techniques Narrow

  13. Slide 13: Zinc supply shortfall and low stocks expected to support price

    Zinc supply shortfall and low stocks expected to support price Mine supply increasing at slower then expected rate Underperformance of smelters keeping stocks at all time lows and • Slower start at key projects and some smaller mines market in deficit • Reduction in production at some existing mines

  14. Slide 14: Hindustan Zinc - Strong Value Proposition

    Hindustan Zinc - Strong Value Proposition Strong Financial Profile Proven Execution Clear Growth Path Sustainable Enterprise Derisked Business • Net Cash of $2.65bn • ~35% 5-yr CAGR of UG • 1.2 mtpa MIC capacity • Globally 1st in • Low cost producer • Strong FCF ~$1BN in FY19, mines to 936kt MIC in

  15. Slide 15: Thank You

    Thank You HINDUSTAN ZINC LIMITED ZINC | LEAD | SILVER |