American Electric Power Company, Inc. · NASDAQ:AEP

American Electric Power — Non-Deal Roadshow (May 2019)

53 slides from American Electric Power's roadshow presentation, May 2019

  1. Slide 1: Investor Meetings May 2019

    Investor Meetings May 2019 May Investor Meetings | aep.com 0

  2. Slide 2: Safe Harbor Statement

    “Safe Harbor” Statement under the Private Securities Litigation Reform Act of 1995 This presentation contains forward-looking statements within the meaning of Section 21E of the Securities Exchange Act of 1934. Although AEP and each of its Registrant Subsidiaries believe that their expectations are

  3. Slide 3: The Premier Regulated Energy Company

    The Premier Regulated Energy Company 40,000 $42B Miles of Transmission Rate Base 5.4M Customers in 11 States 26GW Owned Generation $42B Current Market Capitalization 18,000 Employees $69B Total Assets Statistics as of December 31, 2018 except for market capitalization as of May 10, 2019 May Investor

  4. Slide 4: Leading the Way

    Leading the Way Strong Execution Track Record Delivered Successful Superior Balance Sale of Earnings & Regulatory Capital Sheet Non-Core Dividend Outcomes Allocation Strength Assets Growth AEP Leading the Way Forward Confidence in Commitment to Compelling Portfolio Steady and Well Positioned Growing

  5. Slide 5: Execute Strategy

    Strategic Vision 2023 Initiative Themes Improve customer experience Invest in infrastructure and renewables Invest in transmission and distribution networks Pilot technologies and business models Execute Strategy Mitigate generation exposure Invest in regulated and contracted renewables Manage custo

  6. Slide 6: Operating Earnings Guidance

    Operating Earnings Guidance Organic Investment Opportunity + Manageable Execution Risk = Growth $5.00 $4.75 $4.50 $4.25 $4.00 $3.85 $3.75 $3.50 2018 2019 2020 Future Operating Earnings $3.75 - $3.95 $4.00 - $4.20 $4.25 - $4.45 Guidance Actual $3.95 May Investor Meetings | aep.com 5

  7. Slide 7: Strong Dividend Growth

    Strong Dividend Growth $2.80 Targeted payout ratio 60-70% of $2.60 $2.68 operating $2.53 earnings $2.40 $2.39 $2.20 $2.27 Over 108 $2.15 years of $2.00 $2.03 consecutive $1.95 quarterly $1.80 $1.88 dividends $1.85 $1.71 $1.60 $1.40 Dividend growth in line with earnings $1.20 2010 2011 2012 2013 2014

  8. Slide 8: Positioning for the Future: Capital Investment Opportunities

    POSITIONING FOR THE FUTURE CAPITAL INVESTMENT OPPORTUNITIES May Investor Meetings | aep.com 7

  9. Slide 9: Robust Organic Capital Opportunities

    Robust Organic Capital Opportunities Grid modernization, aging infrastructure, physical/cyber Transmission security, reliability, market efficiency and economic development projects Grid modernization, reliability improvement projects Distribution and distribution station refurbishment Regulated ren

  10. Slide 10: 2019-2023 Capital Forecast of $33B and Net Plant

    2019-2023 Capital Forecast of $33B and Net Plant 2019-2023 Capital Forecast Historical Net Plant Profiles Regulated Regulated Renewables Environmental $0.5B | 1% Generation Regulated Fossil/Hydro $1.1B | 3% Generation Contracted Renewables $1.0B | 3% $2.2B | 7% Nuclear Generation $0.5B | 2% Corporat

  11. Slide 11: 2019-2023 Capital Forecast by Subsidiary

    2019-2023 Capital Forecast by Subsidiary $ in millions (excluding AFUDC) 2019E 2020E 2021E 2022E 2023E Total Appalachian Power Company $821 $786 $847 $939 $875 $4,267 Wheeling Power Company $42 $43 $52 $56 $33 $226 Kingsport Power Company $17 $15 $21 $19 $25 $97 Indiana Michigan Power Company $647 $

  12. Slide 12: Cash Flows and Financial Metrics

    Cash Flows and Financial Metrics $ in millions 2019E 2020E 2021E 2022E Cash from Operations $ 4,700 $ 4,900 $ 5,300 $ 5,800 Capital & JV Equity Contributions * (7,300) (5,800) (6,100) (6,500) Other Investing Activities (300) (400) (100) (100) Common Dividends ** (1,300) (1,300) (1,300) (1,400) Exces

  13. Slide 13: 7.8% CAGR in Rate Base Growth

    7.8% CAGR in Rate Base Growth Cumulative Change from 2017 Base 2017 Rate Base Proxy Vertically Integrated Utilities $23.0B T&D Utilities $9.7B Transcos/Transource $5.7B $21.6B Total $38.4B $18.1B $7.8 $14.5B $6.5 $11.1B $5.2 $6.9 $4.0 $5.7 $7.4B $4.6 $2.6 $3.5 $3.7B $2.4 $6.9 $1.2 $5.9 $1.1 $4.7 $3.

  14. Slide 14: Efficient Cost Recovery Mechanisms

    Efficient Cost Recovery Mechanisms Base Rates 31% Trackers 62% Forward Rates 7% Nearly 70% of 2019-2023 capital plan recovered through reduced lag mechanisms May Investor Meetings | aep.com 13

  15. Slide 15: Investing in Transmission

    INVESTING IN TRANSMISSION May Investor Meetings | aep.com 14

  16. Slide 16: AEP Transmission Holdco Legal Entity Structure

    AEP Transmission Holdco Legal Entity Structure AEP Transmission Company, LLC (AEP Transco) is wholly-owned by AEP Transmission Holding Company, LLC (AEP Trans Holdco) AEP Trans Holdco is a wholly-owned subsidiary of American Electric Power Company, Inc. (AEP), one of the largest utility holding comp

  17. Slide 17: Transmission Priorities

    Transmission Priorities Strategy Execution Results Targeted Capital Investments Infrastructure Improved Reliability/Resiliency Local Reliability, Telecom Earnings Growth Investment modernization, Asset Health Efficient Cost Recovery Improve Reliability, SCADA Modernize grid reducing Customer technol

  18. Slide 18: AEPTHC Target Earnings 2018 - 2021

    AEPTHC Target Earnings 2018 - 2021 AEPTHC EPS contribution grows from Over $13B projected by Significant 2021 (AEP Transcos and $0.31 in 2014 to $1.19-$1.22 in 2021 Investment the ownership percentage of Transource) Healthy Affiliate authorized ROEs ROEs ranging from 9.6% to 12.8% EPS Contribution &

  19. Slide 19: Transmission Investment Drivers

    Transmission Investment Drivers Key Transmission Investment Drivers Typical 2018-2023 Project Examples • Flushing-Smyrna (OH) – construct 13 miles to alleviate thermal overload Local Reliability • Sheridan Project (WV) – 10M T outage minutes in last 3 years • Greenland-VBI North (OK) – replace 41 mi

  20. Slide 20: Transmission Investment Categories

    Transmission Investment Categories As the foundation of the power system, transmission integrates generation and loads across large regional footprints. $4,000 $3,500  Growing complexity of the integrated power grid: distributed generation, diversity in generation fleet, $3,000 location and variabi

  21. Slide 21: Robust Transmission Capital Expenditure Opportunities

    Robust Transmission Capital Expenditure Opportunities Conductor Avg Age 47.6 years Area of Focus Life Expectancy 70 years Circuit Transmission Line Miles Transformers Breakers Life Expectancy (years) 70 60 50 Current Quantity over 6,085 234 998 Life Expectancy Quantity that will exceed Life Expectan

  22. Slide 22: Investing in Distribution

    INVESTING IN DISTRIBUTION May Investor Meetings | aep.com 21

  23. Slide 23: Robust Distribution Capital Expenditure Opportunities

    Robust Distribution Capital Expenditure Opportunities Station Circuit Distribution Transformers Breakers Life Expectancy (years) 60 50 Current Quantity over Life 923 993 Expectancy Quantity that will exceed Life Expectancy in next ten 514 977 years Total Renewal Opportunity 1,437 1,970 over ten year

  24. Slide 24: Examples of Incremental Distribution Investment Opportunities

    Examples of Incremental Distribution Investment Opportunities  Grid Modernization  Pole Replacement Programs  Distribution Supervisory  Obsolete Station Breaker Control and Data Acquisition Replacements  Smart Circuits  Capacity/Reliability Projects  Distribution Line Re-Conductoring  Distri

  25. Slide 25: Investing in Regulated Renewables

    INVESTING IN REGULATED RENEWABLES May Investor Meetings | aep.com 24

  26. Slide 26: SWEPCO and PSO Customer Savings Plan

    SWEPCO and PSO Customer Savings Plan  SWEPCO and PSO Integrated Resource Plans (IRP) continue to Current IRP Wind Nameplate Forecast indicate that customers will benefit from additional low-cost wind energy Wind Procurement * 2021-2023  Takes advantage of the federal Production Tax Credit SWEPCO U

  27. Slide 27: AEP Ohio – Solar Project Filing

    AEP Ohio – Solar Project Filing  Two solar REPAs with both facilities on line by end of 2021:  Highland Solar, 300 MW  Willowbrook Solar, 100 MW  Debt Equivalency Cost Mechanism to provide recovery for use of Balance Sheet (approximately $6M annually)  Green Tariff that allows all customer clas

  28. Slide 28: Projected Resource Additions

    Projected Resource Additions Solar Additions (MW) Wind Additions (MW) Natural Gas Additions (MW) Operating 2024- 2028- Operating 2024- 2028- Operating 2024- 2028- 2020-2023 2020-2023 2020-2023 Co: 2027 2030 Co: 2027 2030 Co: 2027 2030 AEP Ohio Up to 400 * - - AEP Ohio Up to 500* - - I&M - - 1,500 AP

  29. Slide 29: Integrated Resource Plan Status

    Integrated Resource Plan Status IRPs Underway/Planned Previously Approved Q4-18 Q1-19 Q2-19 Q3-19 Q4-19 IRPs 12/14/18 5/1/19 (AR) (VA) 9/30/19 12/20/19 (LA) 12/21/18 July / Aug 2019 Next IRP filing date for APCo (WV) is January 2021 May Investor Meetings | aep.com 28

  30. Slide 30: Investing in Competitive Business

    INVESTING IN COMPETITIVE BUSINESS May Investor Meetings | aep.com 29

  31. Slide 31: Large Scale Project Map with Recently Announced Contracted Renewables Transaction

    Large Scale Project Map with Recently Announced Contracted Renewables Transaction Black Oak Getty (78 MW) Solar 26% Apple Blossom (100 MW) Mehoopany (70 MW) AEP Today 351 MW Cedar Creek 2 (124 MW) Fowler Ridge 2 (100 MW) Wind Pavant (20 MWac) 74% Boulder (50 MWac) Flat Ridge 2 (235 MW) Jacumba (20 M

  32. Slide 32: Overview of Recently Announced Contracted Renewables Transaction

    Overview of Recently Announced Contracted Renewables Transaction Transaction Overview  724 net MW operating wind portfolio across seven states (CO, HI, IN, KS, MI, MN, PA) 1  Five of seven wind assets owned 50 / 50 with BP Wind Energy Operating Portfolio  Long-term PPAs with A/A2-rated 2 counterp

  33. Slide 33: Details of Recently Announced Contracted Renewables Transaction

    Details of Recently Announced Contracted Renewables Transaction MW Asset Off-taker COD PPA Expire Turbine O&M Net 1 Fowler Ridge 2 (IN) 100 2009 2029 Cedar Creek 2 (CO) 124 2011 2035 BP JV Projects Flat Ridge 2 (KS) 235 2012 2036 Mehoopany (PA) 70 2012 2032 Auwahi (HI) 11 2012 2032 Total 540 Black O

  34. Slide 34: Positioning for the Future: Financial Information

    POSITIONING FOR THE FUTURE FINANCIAL INFORMATION May Investor Meetings | aep.com 33

  35. Slide 35: Regulated Returns

    Regulated Returns Twelve Months Ended 3/31/2019 Earned ROE’s (non-GAAP operating earnings, not weather normalized) AEP OH1 I&M 13.2% 12.8% Trans APCo2 9.9% 9.5% KPCo 8.6% PSO2 AEP TX 8.0% SWEPCO2 7.6% 7.2% Regulated Operations ROE of 10.1% as of March 31, 2019 1 Adjusted to reflect ROE after roll-of

  36. Slide 36: Current Rate Case Activity

    Current Rate Case Activity AEP Texas I&M – Indiana SWEPCO – Arkansas1 Docket #: 49494 Docket #: 45235 Docket #: 19-008-U Filing Date: 05/01/2019 Filing Date: 05/14/2019 Filing Date: 02/28/2019 Requested Rate Base: $5.0B Requested Rate Base: $4.9B Requested Rate Base: $1.2B Requested ROE: 10.5% Reque

  37. Slide 37: Recently Settled Rate Cases

    Recently Settled Rate Cases APCo – West Virginia PSO – Oklahoma Docket #: 18-0646-E-42T Docket #: 201800097 Filing Date: 05/09/2018 Filing Date: 09/26/2018 Requested Rate Base: $4.1B Requested Rate Base: $2.5B Requested ROE: 10.22% Requested ROE: 10.3% Cap Structure: 49.84%D / 50.16%E Cap Structure:

  38. Slide 38: Bending the O&M Curve While Achieving Our Strategic Goals

    Bending the O&M Curve While Achieving Our Strategic Goals Actuals / 2019 Plan Inflation @ 2% Bending the Curve Trajectory 4.0 3.7 3.5  O&M targets focus on 3.1 3.1 3.1 3.1 bending the O&M 3.0 2.9 curve down to create 3.0 2.8 2.8 2.8 2.8 rate headroom 2.5  O&M actual spend $B represents adjusting 2

  39. Slide 39: Bending the O&M Curve (Initiatives)

    Bending the O&M Curve (Initiatives) AEP Transmission Spacer AEP Station Check In/Check Out Replacement Capital Program Application  The replacement program  The first true mobile application avoids approximately $80M of its kind saves valuable time in O&M expenditures over for field technicians an

  40. Slide 40: Bending the O&M Curve (Initiatives)

    Bending the O&M Curve (Initiatives) Charge Initiative ~$200M in digital and process-enabled savings over five years through O&M reductions/cost avoidance (50%), Capital Reduction/Efficiency (25%), Revenues (10%) & Operational Efficiency (15%)  Distribution/Transmission Field Time Reporting App – Mo

  41. Slide 41: Normalized Load Trends

    Normalized Load Trends Load figures are provided on a billed basis. Charts reflect connected load and exclude firm wholesale load. Historical and 2019 data adjusted to reflect reclass of industrial and commercial industry codes for certain customers; no revenue or earnings impact. May Investor Meeti

  42. Slide 42: Capitalization and Liquidity

    Capitalization and Liquidity Total Debt / Total Capitalization Credit Statistics Actual Target FFO to Total Debt 18.1% Mid Teens Represents the trailing 12 months as of 3/31/2019 Liquidity Summary (unaudited) 3/31/2019 Actual $ in millions Amount Maturity Revolving Credit Facility $4,000 Jun-22 Qual

  43. Slide 43: 2019 Debt Issuance and Maturities Overview

    2019 Debt Issuance and Maturities Overview Financing plans are subject to change depending on capital expenditures, regulatory outcomes, internal cash generation, market conditions and other factors May Investor Meetings | aep.com 42

  44. Slide 44: Long-Term Debt Maturity Profile

    Long-Term Debt Maturity Profile ($ in millions) Year 2019 2020 2021 2022 2023 2024 AEP, Inc. $0.0 $500.0 $400.0 $1,105.0 $0.0 $0.0 AEP Generating Company $45.0 $150.0 $0.0 $0.0 $0.0 $0.0 AEP Texas* $250.0 $110.6 $0.0 $425.0 $125.0 $0.0 AEP Transmission Company $85.0 $0.0 $50.0 $104.0 $60.0 $95.0 App

  45. Slide 45: AEP Credit Ratings

    AEP Credit Ratings Moody's S&P Company Senior Senior Unsecured Outlook Unsecured Outlook American Electric Power Company Inc. Baa1 S BBB+ S AEP, Inc. Short Term Rating P2 S A2 S AEP Texas Inc. Baa1 S A- S 1 AEP Transmission Company, LLC A2 S A- S 2 Appalachian Power Company Baa1 S A- S 2 Indiana Mic

  46. Slide 46: Sustainable Future

    SUSTAINABLE FUTURE May Investor Meetings | aep.com 45

  47. Slide 47: Emission Reduction Goals

    Emission Reduction Goals Environmental, Social & Governance (ESG) Reporting:  AEP’s Corporate Accountability Report  Clean Energy Strategy: American Electric Power: Strategic Vision for a Clean Energy Future  EEI ESG Sustainability Reporting: AEP’s 2018 EEI ESG Strategy to Achieve: Report  Inves

  48. Slide 48: Transforming Our Generation Fleet

    Transforming Our Generation Fleet 80% 70% 70% 66% 60% 50% Capacity 46% 40% 40% 30% 27% 27% 22% 22% 20% 19% 16% 10% 7% 6% 7% 7% 4% 4% 4% 4% 1% 1% 0% 1999 2005 2019 Future 1999 2005 2019 Future 1999 2005 2019 Future 1999 2005 2019 Future 1999 2005 2019 Future Coal Natural Gas Nuclear Hydro, Wind, Sola

  49. Slide 49: Delivering Clean Energy Resources

    Delivering Clean Energy Resources AEP's Expected Yearend 2019 Renewable Portfolio, in MW Hydro, Wind, Solar & Pumped Storage Owned MW PPA MW Total MW AEP Ohio 209 209 Appalachian Power Company 785 575 1,360 Indiana Michigan Power Company 36 450 486 Public Service Company of Oklahoma 1,137 1,137 Sout

  50. Slide 50: Largest Investment in Environmental Controls

    Largest Investment in Environmental Controls May Investor Meetings | aep.com 49

  51. Slide 51: Dramatic Reductions in Emissions

    Dramatic Reductions in Emissions 1990-2018 ACTUAL SO2 96% NOx 92% 2001-2018 ACTUAL Hg 95% May Investor Meetings | aep.com 50

  52. Slide 52: Dramatic Reductions in Emissions

    Dramatic Reductions in Emissions 2000-2018 Actual CO2 59% May Investor Meetings | aep.com 51

  53. Slide 53: Higher Growth, Higher Dividends, More Certainty

    HIGHER HIGHER growth dividends The Premier Regulated Energy Company MORE MORE certainty regulated Positioned to Deliver Superior Risk Adjusted Returns May Investor Meetings | aep.com 52

American Electric Power Company — Non-Deal Roadshow (May 2019) on 6ix