  1. Slide 1: Southern Company Overview June 2014

    Southern Company Overview June 2014

  2. Slide 2: Cautionary Note Regarding Forward-Looking Statements

    Cautionary Note Regarding Forward-Looking Statements Certain information contained in this presentation is forward‐looking information based on current expectations and plans that involve risks and uncertainties. Forward‐looking information includes, among other things, statements concerning earning

  3. Slide 3: Investor Relations Contact Info

    Investor Relations Contact Info • Dan Tucker Vice President, Investor Relations & Financial Planning 1-404-506-5310 dstucker@southernco.com • Jimmy Stewart Manager, Investor Relations 1-404-506-0747 jwstewar@southernco.com Main website: www.southerncompany.com IR website: http://investor.southerncom

  4. Slide 4: Environmental Reports

    Environmental Reports Carbon Disclosure Report This update for 2014 details actions the Southern Company system is taking on greenhouse gas emissions and incorporates information the company previously submitted to the Carbon Disclosure Project. http://www.southerncompany.com/what-doing/pdf/Carbon_D

  5. Slide 5: Southern Company – A Solid Foundation

    Southern Company – A Solid Foundation • >90% of earnings from our regulated subsidiaries • Forward-looking, constructive regulatory frameworks • Diverse, growing Southeast economy and customer base 5

  6. Slide 6: Other Hallmarks of Southern Company

    Other Hallmarks of Southern Company Southern Power – a premier wholesale generation company An Increasingly Diverse Energy Portfolio Dividend History 6

  7. Slide 7: Our Strategic Priorities

    Our Strategic Priorities • Excel at the Fundamentals • Achieve Success with Major Construction • Support Building National Energy Policy • Promote Energy Innovation • Value and Develop Our People 7

  8. Slide 8: Constructive, Proven Regulatory Frameworks

    Constructive, Proven Regulatory Frameworks 8

  9. Slide 9: Quality Southern Power Assets

    Quality Southern Power Assets 8,960 MWs of Capacity Business Model Build or buy assets supported by long‐term contracts with credit‐worthy counterparties Develop long‐term relationships / partnerships that leverage our operational excellence Minimize fuel and transmission risk Commitment to financia

  10. Slide 10: Financial Overview

    Financial Overview

  11. Slide 11: Earnings Per Share & Dividend Growth

    Earnings Per Share & Dividend Growth1 $3.03 Potential Longer-term $2.91 EPS Growth Drivers • Regulated Capacity $2.89 $2.80 • So Power Capacity • Environmental Rules $2.80 • Effluent Guidelines (ELG) • 316(b) $2.72 • Coal Ash Rules (CCR) • GHG Standards 2014 2015 2016 • Equity ratio Annual Dividends

  12. Slide 12: Dividend Growth Objectives

    Dividend Growth Objectives* Goal of regular, predictable, and sustainable EPS growth is supportive of a growing dividend * Future dividend increases are subject to board of directors’ approval 12

  13. Slide 13: Dividends are an integral component of our value proposition

    Dividends are an integral component of our value proposition Source: Bloomberg; assumes all dividends are reinvested and returns are compounded monthly, 2001 Mirant spin is treated as a dividend. 13

  14. Slide 14: 2014 Economic and Sales Forecast

    2014 Economic and Sales Forecast Economic Roundtable 2014 Sales Growth Forecast GDP projected to grow 2.5% – 3.0% Industrial activity continues to improve with many new entrants being international firms Housing markets continue to improve with housing-related sectors benefiting Economic momentum fr

  15. Slide 15: Q1 2014 Retail Sales

    Q1 2014 Retail Sales As Reported Weather Normal • 2nd coldest Q1 in 20 years Residential 14.8% 1.2% • 10,000 new residential customers Commercial 3.7% -0.2% • Economic development pipeline Industrial 2.8% 2.8% reflects a 58% increase in Total Retail 7.1% 1.3% potential projects Industrial Segment Hi

  16. Slide 16: $17B Capital Expenditure Program (2014-2016)

    $17B Capital Expenditure Program (2014-2016) $6.9B $5.6B ‘14 - '16 Potential Southern Power $4.5B Growth Projects 1.4 Southern Power Base 0.4 Environmental 3.2 New Generation 3.3 Base T&D Growth 1.3 $15.5B Nuclear Fuel 0.9 Maintenance 5.4 Other 1.0 2014 2015 2016 Notes: Totals may not add due to rou

  17. Slide 17: 2014 – 2016 Financing Plan

    2014 — 2016 Financing Pian ($ in billions) 2014 2015 2016 Remaining Total Projected Projected Georgia DOE Loan $ 02 $ 12 $ 14 $ 04 Mississippi Secuntization - 09 : Capital Markets New Money 05 05 04 05 Maturity & Bridge Financing Replacement 04 04 13 13 Long Term Securities Issuances' $ 1414$ 21 $ 4

  18. Slide 18: Strong Credit Ratings Benefit our Customers

    Strong Credit Ratings Benefit our Customers 18

  19. Slide 19: Our Debt Portfolio Compares Favorably

    Our Debt Portfolio Compares Favorably 6.50 % 6.00 % Ameren Corp. 0% AEP 0% Con Edison 0% 5.50 % PG&E 0% Wisconsin Energy 9% Exelon Corp. 9% Average Cost (%) 5.00 % Dominion 4% NextEra 7% Entergy Corp. 16% Duke Energy 0% 4.50 % Public Service Entp. Grp. 0% Gulf 21% 4.00 % Alabama 5% Southern Co. 5% 3

  20. Slide 20: Generation Overview

    Generation Overview Including Major Construction Projects

  21. Slide 21: Committed to “All of the Above”

    Committed to “All of the Above” Plant McDonough-Atkinson 2,520 MW Natural Gas CC Among of the most efficient in the nation Utility Scale Solar at Southern Power and initiatives at Georgia Power Vogtle Units 3 & 4 ~1,005MW Ownership Multiple AP1000 technology Wind Energy PPAs Kemper County IGCC ~495M

  22. Slide 22: Transitioning the coal fleet to comply with EPA rules

    Transitioning the coal fleet to comply with EPA rules Coal MWs as of 12/31/13 20,860 MWs to Convert to Natural Gas 3,200 MWs fuel switch (to PRB) / ACI / DSI 1,200 MWs to be retired by 2015 2,900 Well‐controlled MWs for long‐term use (scrubber+) 13,200 EPA’s MATS rule will drive most of the Southern

  23. Slide 23: A Diverse Generation Fleet Benefits our Customers

    A Diverse Generation Fleet Benefits our Customers Resources What We’ve Used Future Flexibility (GWs of Capacity) (GWHs of Energy) (Depends on Fuel Prices) 2000 2013 2020E 2000 2013 2020E 2020E Nuclear 16% 16% Nuclear 18% 18% Hydro/Renew Nuclear 4% 4% Converted Gas Total Gas CTs 2013: 46% 23% 42% 202

  24. Slide 24: Historical Generation Mix Trends

    Historical Generation Mix Trends 24

  25. Slide 25: Historical GHG Intensity

    Historical GHG Intensity (CO2e lbs/MWH) 25

  26. Slide 26: Renewables

    Renewables Southern Power invested in ~260 MW of utility scale solar, mainly in desert Southwest Solar initiatives in Georgia initiated to provide ~800 MW of solar capacity to Georgia Power by 2016 • 90MW of PV solar to be located at military bases • 2014 Utility Scale RFP for 495 MW • Bids were due

  27. Slide 27: Vogtle 3&4 - New Nuclear Construction

    Vogtle 3&4 - New Nuclear Construction • Approved by Georgia Public Service Commission in 2009 • Westinghouse AP1000 Technology • Each unit totals approximately 1,100MW units • Georgia Power is a 45.7% owner (Oglethorpe, 30%; MEAG, 22.7%; and Dalton Utilities, 1.6%) • Received Combined Construction a

  28. Slide 28: Latest Vogtle Construction Monitoring Report (9th/10th VCM)

    Latest Vogtle Construction Monitoring Report (9th/10th VCM) Summary of Customer Benefits As reflected in VCM 9 & 10 • $389M of capital spend in 2013 Interest Savings Total • Projected in-service dates of Q4 2017 $750M $2.3B and Q4 2018 for units 3 & 4, respectively DOE LG $250M • $2.3B of anticipate

  29. Slide 29: No Change in Latest Cost Estimate (9th/10th VCM)

    No Change in Latest Cost Estimate (9th/10th VCM) Largely schedule‐related costs 29

  30. Slide 30: Estimated Cumulative Rate Impact of 6% to 8% at COD

    Estimated Cumulative Rate Impact of 6% to 8% at COD • Fuel savings, along with the additional customer benefits, significantly lessen the overall rate impact to customers at the time the units are put into service. The remaining projected rate impact for customers is only 2 to 4 percent 30

  31. Slide 31: DOE Loan Guarantee – Georgia Power

    DOE Loan Guarantee – Georgia Power • Finalized February 20, 2014 • Credit Facility = $3.46B (70% of eligible project costs) • Draws mature February 20, 2044, with amortization of principal beginning in 2020. • Interest Rate = Treasury + 0.375% • First draw of $1B taken the day of closing • Estimated

  32. Slide 32: Vogtle Construction Update

    Vogtle Construction Update Unit 3 Unit 4  Set CA-20  Set containment cradle Progress  Concrete under bottom head  Containment vessel bottom head set  Set turbine island condensers  Condenser assembly  Cooling tower above 300’  Cooling tower above 50’ Upcoming • Set CA-05 (wall module) • Modu

  33. Slide 33: Vogtle 3&4 Update – Key Risk Mitigations

    Vogtle 3&4 Update – Key Risk Mitigations • 100% fixed/firm EPC contract • Significant front-end engineering during NRC design certification • PWR is not new technology (safety features of AP1000 are new) • Significant oversight (SNC, NRC, GPSC, co-owners) • Remaining annual rate increases <1% per ye

  34. Slide 34: Vogtle 3 & 4 – Construction Site

    Vogtle 3 & 4 – Construction Site 34

  35. Slide 35: Vogtle Unit 3 Nuclear Island – 2014 Activity

    Vogtle Unit 3 Nuclear Island – 2014 Activity CA-20 Current View CA-04 CB-65 Auxiliary Building Walls to Elevation 82’6” CA-03 CA-01 CA-20 CA-02 (Inside Vessel) Target Middle Ring Year-End Lower Ring CA-05 (Inside Vessel) View Auxiliary Building Walls to Elevation 100’ Shield Building Panel Installat

  36. Slide 36: AP1000 Nuclear and Turbine Islands

    AP1000 Nuclear and Turbine Islands 36

  37. Slide 37: Vogtle 3 Nuclear Island & Cooling Tower

    Vogtle 3 Nuclear Island & Cooling Tower 37

  38. Slide 38: Major Vogtle 3 Components

    Major Vogtle 3 Components CA‐05 Module Containment Vessel Rings inside Module Assembly Building (MAB) Shield Building Turbine Wall Panels Building 38

  39. Slide 39: Vogtle 4 Nuclear Island

    Vogtle 4 Nuclear Island \ a 7 v “* fl oe \)

  40. Slide 40: Kemper County IGCC

    Kemper County IGCC • First of a kind technology developed by SO and KBR • Carbon footprint equivalent to a combined cycle natural gas unit – 65% CO2 capture for enhanced oil recovery (EOR) • Affordable, abundant, low-rank coal resource – Mine mouth lignite coal 40

  41. Slide 41: TRIG Attributes / Advantages

    TRIGTM Attributes / Advantages Presalter Cyclone syngas • Simple, well established design – Based on technology in use for 70 years Standpipe • Either Air- or Oxygen-blown Cyclone – Air for power – Oxygen for liquid fuels and chemicals • High Reliability Design Riser – Non-slagging design: – Expect

  42. Slide 42: Kemper IGCC Update

    Kemper IGCC Update • Pneumatic testing of Gasifer A complete in May 2014; Gasifer B scheduled for June • First gasifier heat-up targeted for mid to late summer 2014 • Combined cycle expected in-service in summer 2014 • Current cost estimates assume in-service date extension to May 31, 2015 • Prudenc

  43. Slide 43: Kemper IGCC – Construction Site

    Kemper IGCC – Construction Site Lignite Gasifier Delivery Combined Cycle Gas Clean- Up Cooling Towers 43

  44. Slide 44: Kemper IGCC – Major Components

    Kemper IGCC – Major Components Acid Gas Removal Area Gasifier Structure CO2 Flash Drums Gasifier 44

  45. Slide 45: Kemper IGCC – Combined Cycle

    Kemper IGCC – Combined Cycle 45

  46. Slide 46: Appendix

    APPENDIX

  47. Slide 47: 2014 – 2016 CapEx Forecast – Company

    2014 – 2016 CapEx Forecast – Company Total $billions 2014 2015 2016 '14 - '16 Alabama Power $1.7 $1.7 $1.2 $4.6 Georgia Power 2.5 2.4 2.1 7.0 Gulf Power 0.4 0.3 0.2 0.9 Mississippi Power 1.6 0.5 0.2 2.3 Other Subsidiaries 0.2 0.1 0.1 0.3 Traditional OpCo Total $6.4 $4.9 $3.8 $15.1 Southern Power 0.2

  48. Slide 48: 2014 – 2016 CapEx Forecast – Functional

    2014 – 2016 CapEx Forecast – Functional Total $billions 2014 2015 2016 ‘14-’16 New Generation $2.0 $0.9 $0.5 $3.3 Environmental Compliance 1.5 1.1 0.6 3.2 Transmission 0.1 0.2 0.1 0.4 Distribution 0.3 0.3 0.3 0.9 Total T&D Growth 0.4 0.4 0.4 1.3 Generation 0.9 0.9 0.8 2.7 Transmission 0.6 0.5 0.4 1.

  49. Slide 49: 2014 – 2016 Long-term Securities Issuances

    2014 – 2016 Long-term Securities Issuances , 49

  50. Slide 50: 2014 Key Regulatory Dockets

    2014 Key Regulatory Dockets Georgia Power • Vogtle Construction Monitoring Report (VCM) – Docket 29849 • Advanced Solar Initiative – Docket 36498 & 36325 Mississippi Power Company • Kemper IGCC Project – Docket 2009-UA-0014 • 7 Year Rate Mitigation Plan for Kemper IGCC Project – Docket 2013-UN-0039

  51. Slide 51: Georgia Advanced Solar Initiatives – 735MW

    Georgia Advanced Solar Initiatives – 735MW PSC approved the 210 MW ASI program in November 2012 PSC approved the 525 MW of additional solar in the 2013 IRP order  Distributed Generation: 100 MW  Utility Scale: 425 MW Program 2014 2015 2016 ASI DG 45MW 45MW 2013 ASI Utility Scale 60MW 60MW ASI Prim

  52. Slide 52: Georgia Power Rate Settlement Summary (Docket 36989)

    Georgia Power Rate Settlement Summary (Docket 36989) Original Filing • Original filing of $482M levelized rate ROE midpoint reduced 20bps from increase ($1,446M over 3 years) current level (11.15% to 10.95%) • 11.5% ROE (band of 10.25% to 12.25%) Top end of allowed retail range Settlement dropped 25

  53. Slide 53: Gulf Power Rate Settlement Summary (Docket 130140-EI)

    Gulf Power Rate Settlement Summary (Docket 130140-EI) Original Filing • Original filing of $74M in 2014 & $16M in 2015 – Rates effective April 2014 ($56M collection) Maintains current allowed & July 2015 ($8M collection) ROE midpoint and range with • Midpoint of 11.5% ROE potential for an increase S