Mountain Province Diamonds — Investor Presentation (September 2014)

31 slides from Mountain Province Diamonds's investor presentation, September 2014

  1. Slide 1: Corporate Presentation

    CORPORATE PRESENTATION

  2. Slide 2: Mountain Province - Best in Class

    Mountain Province - Best in Class World’s largest and richest new diamond mine Best in class - highest margin new diamond mine Projected to be third highest margin diamond mine in production Potential to be a Tier 1 asset - +20 year LOM, +$20 Billion in situ value

  3. Slide 3: Highest Margin New Diamond Mine

    Highest Margin New Diamond Mine Name Reserve Grade Total Diamond Revenue Operating Operating Production Carats Value per tonne Cost Margin (MMct/year) (Mt) (cpt) (MMct) ($/ct) ($/t) ($/t) ($/t) Gahcho Kué DeB/MPV 35.4 1.57 55.5 182 286 65 221 4.5 Canada Bunder Rio Tinto 37 0.74 27.4 50 38 20 18 0.7

  4. Slide 4: Third Highest Margin Diamond Mine

    Third Highest Margin Diamond Mine

  5. Slide 5: Capital Structure

    Capital Structure TSX : MPV Markets NYSE MKT : MDM Market cap ~$650M Shares outstanding 115M Fully diluted 116M Cash ~$38M

  6. Slide 6: Joint Venture with De Beers

    Joint Venture with De Beers MP 49% / De Beers 51% JV Board - 2 Representatives Each All material decisions by Consensus Effectively 50/50 JV Each market own share of diamonds De Beers Operator: Performance Obligations

  7. Slide 7: Canada's Diamond Fields

    Canada’s Diamond Fields “Northwest Territories | Gameti Wekweeti @ ey Diavik tt aoe ¥ } Whati t BeNchok® i Gahcho Kué Ndilo/Dettah Yellowknife raed Om Lutsel K’e Te > Ft. Providence ts Ft. Resolution Hay River» ig Feat iis

  8. Slide 8: Gahcho Kué Kimberlite Cluster

    Gahcho Kué Kimberlite Cluster 61M carat open-pit resource to +350 metres

  9. Slide 9: Reserve Statement

    Reserve Statement Pipe* Category Tonnes Grade Carats (Mt) (cpt) (Mct) 5034 Probable 13.4 1.74 23.2 Tuzo Probable 16.4 1.25 20.6 Hearne Probable 5.6 2.07 11.7 Total Probable 35.4 1.57 55.5 JDS Mining, March 2014

  10. Slide 10: Independent Diamond Valuations

    Independent Diamond Valuations Pipe Actual* Model** Model Esc*** 5034 169 138.19 167.35 Hearne 92 107.00 123.19 Tuzo 311 101.00 144.36 Total $182 $118.38 $149.66 *WWW International Diamonds Consultants, August 2014 **WWW, February 2014 ***Model price escalated by real 1.5% over life of mine (12 year

  11. Slide 11: Gahcho Kué Diamonds

    & Gahcho Kué Diamonds Mountain Province DIAMONDS

  12. Slide 12: 2014 Feasibility Update

    2014 Feasibility Update IRR 32.6% Capital (Jan 14) (49%) US$346M Contingency US$33M Working capital US$36M Sust. Cap LOM US$41M Operating cost US$65/tonne LOM 12 years LOM production 53.4 million carats Revenue US$150/carat JDS Mining/Hatch, March 2014

  13. Slide 13: Diamond Price Gearing

    Diamond Price Gearing Value IRR NPV $150/carat 32.6% $1.1B $174/carat 43% $1.85B $200/carat 62.5% $3.4B

  14. Slide 14: De Beers Major Capital Projects

    De Beers Major Capital Projects Project Capital Resource Cost ($/ct) Jwaneng $3B 102M $29.41 8-Cut Venetia Underground $2B 96M $20.83 Gahcho Kué $0.85B 54M $15.74 Gahcho Kué – Highest Return

  15. Slide 15: Potential Cash Flow (US$)

    Potential Cash Flow (US$) Revenue ~ $182 per carat Cost ~ $42 per carat Margin ~ $140 per carat Production ~ 4.5M carats/year Cash flow ~ $630M/year MPD 49% ~ $310M/year Per share ~ $2.38* * Based on post-financing 130M shares in issue

  16. Slide 16: Project Finance

    Project Finance Term loan US$370M Capital $254M Working capital $50M Capitalized interest $26M Fees $22M De Beers payment $10M Management fee $8M Equity US$210M 2013 $52.3M 2014 $81.2M 2015 (Jan/Feb) $76.5M Debt/equity: 64/36

  17. Slide 17: Development Schedule

    Development Schedule Federal government approval October 2013  Construction started December 2013  Current status: 40% complete end August 2014  Target for construction completion end 2015 Target for plant commissioning H1 2016 Target for start of production Q3 2016

  18. Slide 18: Construction at Gahcho Kué

    os) Construction at Gahcho Kué

  19. Slide 19: Gahcho Kué Mine Design

    & Gahcho Kué Mine Design sore se2000 sesaoo 586000 afi 988000 690000 3 NT-4201 7038000 os SS NT-4199 NT-4341 Ld Gahcho Kue —— Road ‘Structure L — Pipe . [TT Acevc seres uossos eT [TF Leaserermit Application or 7 el heal NT4731 74725 r) 0s 1 km g D 7 B De $ E DEERS gs NT-4737, NT-4738) Group oF Compa

  20. Slide 20: Phase 2 Inferred Resources

    Phase 2 Inferred Resources Pipe* Category Tonnes Grade Carats (Mt) (cpt) (Mct) 5034 Inferred 0.9 1.51 1.4 Tuzo Inferred 8.9 1.62 14.6 Hearne Inferred 1.4 1.67 2.4 Total Inferred 11.3 1.64 18.5 Further indicated resource of 1.1M carats Mine life potential from 12 to 17 years

  21. Slide 21: Phase 3: Tuzo Deep

    3 Phase 3: Tuzo Deep ntain Provi DIAMONDS

  22. Slide 22: Phase 3 Resource Potential

    Phase 3 Resource Potential Depth Volume Volume (meters) (tonnes) (carats) Phase 1 Surface to 350 16.4M 20.6M Reserve Phase 2 350 to 560 8.9M 14.6M Resource Phase 3 560 to 750 ~7M ~12M Potential 2014 Tuzo Deep drill program completed Kimberlite intersected to 740 meters Mine life potential from 17 to

  23. Slide 23: Phase 3 Mine Potential

    3 Phase 3 Mine Potential Tuzo s Pit Tuzo/5034 pits intersection 5034 Pit Mountain Province DIAMONDS

  24. Slide 24: Phase 4: Tesla & 5034/Hearne Deep

    Phase 4: Tesla & 5034/Hearne Deep Mine life potential + 20 years

  25. Slide 25: Phase 5 Exploration Potential

    Phase 5 Exploration Potential

  26. Slide 26: Path to Tier 1 Asset

    Path to Tier 1 Asset Phase Carats LOM Value est. Phase 1 Reserve 54M 12 years $9.4B Phase 2 Resource 18.4M 5 years $3.2B Phase 3 Tuzo Deep ~ 12M ~3 yrs. ~ $2B Phase 4 Tesla & Other ? ? ? Phase 5 New Targets ? ? ? Vision: +20 years LOM, +$20B in-situ Value

  27. Slide 27: Global Diamond Supply & Demand

    Global Diamond Supply & Demand Source: Rio Tinto

  28. Slide 28: Falling Diamond Supply

    Falling Diamond Supply Source: RBC Capital Markets

  29. Slide 29: Climbing Diamond Demand

    Climbing Diamond Demand Source: Rio Tinto

  30. Slide 30: Diamond Engagement Ring Demand

    Diamond Engagement Ring Demand Source: De Beers & Rio Tinto

  31. Slide 31: Corporate Information

    Corporate Information Head Office 161 Bay Street Suite 2315 Toronto, ON M5J 2S1 TSX: MPV Canada NYSE MKT: MDM Tel. ++1-416-361-3562 Fax. ++1-416-603-8565 www.mountainprovince.com info@mountainprovince.com This presentation may contain “forward looking” statements that involve known and unknown risks