Slide 1: The World's Fastest Growing Drilling Contractor - 2Q 2006 Results
The World’s Fastest Growing Drilling Contractor 2Q 2006 Results Oslo, 1 September2006
Slide 2: Disclaimer
Confidential Disclaimer THIS PRESENTATION AND ITS ENCLOSURES AND APPENDICES (HEREINAFTER JOINTLY REFERRED TO AS THE “PRESENTATION” HAS BEEN PREPARED BY SEADRILL LIMITED. (”SDRL” , “SEADRILL or THE ”COMPANY”) EXCLUSIVELY FOR INFORMATION PURPOSES. THIS PRESENTATION HAS NOT BEEN REVIEWED OR REGISTERED
Slide 3: Contents
3 Contents Mission statement 2Q 2006 results Newbuilding program Contract status Market development and outlook Human resources Summary
Slide 4: Mission statement
4 Mission statement Create a world leading drilling contractor within 5 years
Slide 5: Highlights 2Q 2006
5 Highlights 2Q 2006 All drilling units on dayrate Net income of US$ 33.3 million and EPS of US$ 0.07 US$ 210 million sale and leaseback completed for newbuilt jack-up Seadrill 3 Ownership position in Eastern Drilling ASA maintained by participating in private placement New barge tender fr
Slide 6: Current operations
6 Current operations Norway - 4 units 2 Semis 1 Jack-up 1 Drillship Well Services 39.4% interest in Eastern activities Sakhalin 1 Jack-up Current operations Southeast Asia-10 units Previous operations 3 Semi-tenders West Africa - 4 units 6 Tender rigs 1 Semi-tender 1 Jack-up 1 Tender rig 33% interes
Slide 7: Condensed Income Statement
7 Condensed Income Statement Actual Pro forma Unaudited accounts in USD millions 2Q06 1Q06 Operating Revenues Operating revenues 224.3 187.1 Reimbursables 22.9 18.4 Other revenues 28.4 28.4 Total revenues 275.6 233.8 Operating expenses Vessel and rig operating expenses 133.3 125.6 Reimbursable expen
Slide 8: Condensed Consolidated Segment Information - Mobile Units
8 Condensed Consolidated Segment Information Mobile Units Actual Pro Forma Unaudited accounts in USD millions 2Q06 1Q06 Operating revenues 112.9 84.0 Reimbursables 15.2 6.5 Other revenues 24.3 24.3 Total revenues 152.4 114.8 Vessel and rig operating expenses 59.5 53.1 Reimbursable expenses 14.3 5.9
Slide 9: Condensed Consolidated Segment Information - Tender Rigs
9 Condensed Consolidated Segment Information Tender Rigs Actual Pro Forma Unaudited accounts in USD millions 2Q06 1Q06 Operating revenues 41.5 37.6 Reimbursables 2.3 1.5 Other revenues 4.1 4.1 Total revenues 47.9 43.2 Vessel and rig operating expenses 18.6 17.8 Reimbursable expenses 2.2 1.4 Deprecia
Slide 10: Condensed Consolidated Segment Information - Well Services
10 Condensed Consolidated Segment Information Well Services Actual Pro Forma Unaudited accounts in USD millions 2Q06 1Q06 Operating revenues 69.9 65.4 Reimbursables 5.3 10.3 Total revenues 75.2 75.7 Vessel and rig operating expenses 55.2 54.8 Reimbursable expenses 5.1 10.0 Depreciation and amortisat
Slide 11: Condensed Consolidated Balance Sheets
11 Condensed Consolidated Balance Sheets Unaudited accounts in USD millions Actual Pro Forma 30.06.06 31.12.05 Current assets Cash and cash equivalents 433.8 417.5 Receivables 243.4 153.8 Other investments - 302.2 Total current assets 677.2 873.5 Non-current assets Investment in associated companies
Slide 12: Newbuild projects
12 Newbuild projects 2 drillships at Samsung, Korea 2 semis at Samsung, Korea (Eastern Drilling ASA) 2 semis at Daewoo, Korea 2 semis at Jurong, Singapore 1 semi-tender and 4 jack-ups 2 tender barges in Singapore in Singapore and KFELS and PPL Malaysia, respectively Building the most modern fleet at
Slide 13: Seadrill newbuild characteristics
13 Seadrill newbuild characteristics Copies of existing units Proven technology Quality yards Delivery time reflects previous experience First units to be ordered Main yard installments to be paid at delivery Fixed price turnkey contracts Risk contained for on-schedule delivery
Slide 14: Newbuild deepwater program
14 Newbuild deepwater program Project phases Engineering Construction Commissioning West E-drill West E-drill II Jurong I Jurong II Daewoo I Daewoo II Mosvold I Mosvold II Projects are progressing according to plan
Slide 15: Mosvold drillships
15 Mosvold drillships Two deepwater drillships Builder: Samsung Delivery: Q2/4Q 2008 Design: Samsung 10,000 Rated water depth: 10,000 ft Rated drilling depth: 35,000 ft Riser: 7,000 ft Top Drive: 2 HPS 1,000 short tons (dual motor AC) Contract price: US$ 470 million * * Excluding s
Slide 16: Jurong semis
16 Jurong semis Two semi-submersible rigs Builder: Jurong Delivery: Q1/4Q 2008 Design: Friede Goldman ExD Rated water depth: 10,000 ft Rated drilling dept: 35,000 ft Risers: 7,500 ft Top Drive: MH DDM 750/1,000 AC Contract price: US$ 395/407 million * * Excluding spares, constructi
Slide 17: Daewoo semis
17 Daewoo semis Two semi-submersible rigs Builder: Daewoo Delivery: Q1/3Q 2008 Design: GVA 7500 Rated water depth: 10,000 ft Rated drilling depth: 35,000 ft Risers: 7,500 ft Top Drive: MH DDM 750/1,000 AC Contract price: US$ 506/496 million * * Excluding spares, construction superv
Slide 18: West E-drill I and II
18 West E-drill I and II Two semi-submersible rigs Builder: Samsung Delivery: 4Q 2007/3Q 2008 Design: DP Drilling Vessel Rated water depth: 10,000 ft Rated drilling dept: 30,000 ft Dual Derrick Risers: 4,100 ft Contract price: US$ 580/578 million * * Including spares, construction
Slide 19: Investments in Capital Spares and Risers
19 Investments in Capital Spares and Risers The market for spare equipment is tight with increasing prices and long lead time Capital spares includes risers, top-drives, thrusters, mud pumps, drill pipe, BOP related equipment etc Increase flexibility and reduce down time risk Additional invest
Slide 20: Four jack-up newbuilds
20 Four jack-up newbuilds Three jack-ups at KFELS Two units to be delivered in 3Q07 One unit to be delivered in 2Q08 One jack-up at PPL Delivery scheduled for 4Q07 Progress according to plan and budget
Slide 21: Three tender rig newbuilds
21 Three tender rig newbuilds One semi-tender at KFELS Delivery scheduled for 4Q06 Two tender barges at Malaysia Marine & Heavy Engineering Delivery scheduled for 2Q07 and 2Q08 Option to build another tender barge at Malaysian MHE Progress according to plan and budget
Slide 22: Committed newbuild installments
22 Committed newbuild installments 800 700 654 577 600 US$ million 482 500 400 362 267 300 249 197 204 168 200 147 104 100 51 0 Paid 2Q06 3Q06 4Q06 1Q07 2Q07 3Q07 4Q07 1Q08 2Q08 3Q08 4Q08 Commited newbuild installments Committed newbuild installment schedule amounts to approximately US$ 3.5 billio
Slide 23: Contract status
23 Contract status 2006 2007 2008 2009 2010 Customer 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q Semi-submersibles West Alpha Statoil US$ 249,000 West Venture Norsk Hydro US$ 220,000 US$ 220,000 06.2011 West E-drill 1 Under construction Samsung - US$ 580M West E-drill II 1 Under cons
Slide 24: Contract status
24 Contract status 2006 2007 2008 2009 2010 Customer 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q Tender rigs T3 1 PTT US$ 40,000 US$ 42,000 US$ 51,000 US$ 58,000 US$ 70,000 06.2012 T4 Chevron US$ 40,000 T6 1 Carigali/CTOC US$ 60,000 US$ 86,000 12.2010 T7 Chevron US$ 40,000 US$ 51,000
Slide 25: Market characteristics
25 Market characteristics Increasing number of enquiries for newbuilds (both shallow and deep waters) Particular increase in interest for ultra deepwater units (3,000 meters) Term contracts from 3 years and upwards Deferral of drilling programs Mainly newbuilds available from 2008 Demand
Slide 26: Deepwater newbuilds
26 Deepwater newbuilds 33 deepwater newbuilds and conversions ongoing 12 units are signed on contract 21 units are without contract of which Seadrill controls 8 Current number of deepwater enquiries are close to 30 Demand supply situation as sound as ever
Slide 27: Ultra deepwater market
27 Ultra deepwater market Source: ODS Petrodata, Companies, Pareto Securities research
Slide 28: Deepwater market
28 Deepwater market Source: Fearnley Offshore
Slide 29: Jack-up Market
29 Jack-up Market Source: Fearnley Offshore
Slide 30: Human resources
30 Human resources Currently a pool of 4,300 employees as a basis More than 25 different nationalities Significant organic growth capacity 2,000 people to be hired to operated newbuilds State of the art rig fleet An attractive employer long term
Slide 31: Summary
31 Summary Newbuilding projects organized, resourced and well under way Strong market outlook in all segments Operations integrated and running according to plan Creating a world leading drilling contractor
Slide 32: Seadrill
32 Seadrill